The document appears to be a Performance Work Statement (PWS) excerpt that outlines the quality control standards and acceptance criteria for an epoxy floor coating application. It specifies that all painted surfaces must be inspected for defects such as brush/roller marks, poor coverage, and damage due to improper application. Painted surfaces will be considered unacceptable if visible defects are evident from the normal viewing distance. Any rejected work must be corrected at the contractor's expense.

The related federal contract opportunity is for a construction project to repair a Fire Department building in Syracuse, NY. The project has an estimated value between $250,000 and $500,000 and is being solicited as a 100% small business set-aside under NAICS code 236220. Award will be made to the responsible bidder whose bid conforms to the invitation and is most advantageous to the Government considering only price and price-related factors. Bids are required to be valid for at least 90 days, and no electronic bids will be accepted.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Epoxy Floor Coating PWS

3.7 Field Quality Control / Standard of Acceptance:

1. All surfaces, preparation and paint applications shall be inspected

2. Painted exterior and interior surfaces shall be considered to lack uniformity and soundness if any of the following defects are apparent to the Painting Inspection Agency inspector:

a. Brush / roller marks, streaks, laps, runs, sags, drips, heavy stippling, hiding or shadowing by inefficient application methods, skipped or missed areas, and foreign materials in paint coatings.

b. Evidence of poor coverage at rivet heads, plate edges, lap joints, crevices, pockets, corners and re-entrant angles.

c. Damage due to touching before paint is sufficiently dry or any other contributory cause.

d. Damage due to application on moist surfaces or caused by inadequate protection from the weather.

e. Damage and/or contamination of paint due to blown contaminants (dust, spray paint, etc.).

3. Painted surfaces shall be considered unacceptable if any of the following are evident under natural lighting source for exterior surfaces and final lighting source (including daylight) for interior surfaces:

a. Visible defects are evident on vertical surfaces when viewed at normal viewing angles from a distance of not less than 1000 mm (39”).

b. Visible defects are evident on horizontal surfaces when viewed at normal viewing angles from a distance of not less than 1000 mm (39”).

c. Visible defects are evident on ceiling, soffit and other overhead surfaces when viewed at normal viewing angles.

d. When the final coat on any surface exhibits a lack of uniformity of color, sheen, texture, and hiding across full surface area.

4. Painted surfaces rejected by the inspector shall be made good at the expense of the Contractor.

Small affected

5. Areas may be touched up; large affected areas or areas without sufficient dry film thickness of paint shall be repainted.

6. Runs, sags of damaged paint shall be removed by scraper or by sanding prior to application of paint