Attch 1 - VOF Specifications 8-11-20.pdf
PDF 849 KB Posted
- Attached to
- VALLEY OF FIRES PAVEMENT REHABILITATION
- Solicitation number
- 140L0620Q0070
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L0620Q0070_Amd_0001.pdf | ||
| Sol_140L0620Q0070.pdf | ||
| Attch 5 - Amendment 0001 Sol_140L0620Q0070 SF18_0001.pdf | ||
| Attch 4 - VOF Price Worksheet.xlsx | XLSX spreadsheet | |
| Attch 2 - VOF Pavement 2020 Plans 8-11-20.pdf | ||
| Attch 3 - VOF Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bureau of Land Management
Valley of Fires
Pavement Rehabilitation 2021
Standard Construction Specifications
Bureau of Land Management Roswell Field Office
Carrizozo, New Mexico July 2020
TABLE OF CONTENTS TOC - 1
Valley of Fires Pavement Rehabilitation 2020
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY
012200 UNIT PRICES
012600 CONTRACT MODIFICATION PROCEDURES
012973 SCHEDULE OF VALUES
013100 PROJECT MANAGEMENT AND COORDINATION
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017340 EXECUTION
017700 CLOSEOUT PROCEDURES
DIVISION 02 – SITE CONSTRUCTION
027650 PAVEMENT MARKINGS
027850 CHIP SEAL
July 2020 SUMMARY Valley of Fires Pavement Rehabilitation 2021 011000-1
SECTION 011000 – SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work phases.
4. Work under other contracts.
5. Use of premises.
6. Public use of site.
7. Occupancy requirements.
8. Work restrictions.
9. Specification formats and conventions.
1.2 PROJECT INFORMATION
A. Project Identification: Valley of Fires Pavement Rehabilitation 2021
1. Project Location: US 380, 3.95 miles northwest of Carrizozo, Lincoln County, NM.
Valley of Fires Recreation Area.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work consists of the following:
1. The Work includes furnishing all labor, material and equipment to complete a double application chip seal, fog seal and other incidentals necessary to complete work.
B. Project will be constructed under a single prime contract. All work described in plans and specifications shall be completed within 30 calendar days of notice to proceed. Suspension of contract time will be allowed for reasonable cause between chip seal and fog seal. Suspension of contract time will also be allowed for reasonable cause between fog seal and pavement marking.
1.4 WORK PHASES
A. The Work shall be conducted in four phases (crack sealing, double chip seal, fog seal, pavement marking) in the following order:
1. Roadway shall be examined with project manager and crack sealing as described in these specifications shall be performed.
Valley of Fires Pavement Rehabilitation 2021 011000-2
2. Roadway shall be swept and prepared for chip seal application. Double chip seal application shall be completed.
3. Roadway shall be prepared for fog seal application. Fog seal shall be completed.
1.5 WORK UNDER OTHER CONTRACTS
A. Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
1.6 USE OF PREMISES
A. Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits.
B. Schedule operations so that Work is conducted during regular business hours between 7 AM and 5 PM.
C. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
D. Limit use of premises to paved areas within the project limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Government Occupancy: Allow for Government occupancy of Project site and use by the public. Government personnel will be continuously occupying areas of the building immediately adjacent to the work area. Conduct work in a manner that will minimize needs for disruption of normal Government operations. Provide minimum 72 hours advance notice to Contracting Officer of activities that will impact normal Government operations. Secure Contracting Officer's written approval of activities that will impact normal Government operations to avoid delays in overall construction and permit proper installation or work.
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials. There will be an area near visitor center available for parking vehicles and some equipment.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
Valley of Fires Pavement Rehabilitation 2021 011000-3
1.7 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Temporary road closures will be permitted to allow placement and curing of chip seal and fog seal. Contractor shall notify any users of recreation site one day in advance and again one hour in advance of any closures.
1.8 OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy site and Visitor Center building during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government day-to-day operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
B. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Will not be allowed.
2. Early Morning Hours: Will not be allowed.
3. Contractor may work on/repair equipment and conduct cleanup operations until 8 p.m., but may not perform other Work specified by this contract.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without showing of good cause and prior consent from the Contracting Officer. Submit requests 48 in advance of the work to the Contracting Officer for approval.
C. No advertisements shall be displayed on the construction site or within the premises unless approved by the Contracting Officer.
D. Existing Utilities
Valley of Fires Pavement Rehabilitation 2021 011000-4
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for any excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
F. Smoking is not permitted within any buildings or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.10 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the CSI/CSC's "MasterFormat" numbering system.
1. Division 01 – General Requirements: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.
Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
C. Terminology: All references to “Owner,” “Architect,” and “Contracting Officer” shall be replaced with the term “Government” or “Contracting Officer Representative” (when referring to the person acting for the Contracting Officer).
Valley of Fires Pavement Rehabilitation 2021 011000-5
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
July 2020 UNIT PRICES Valley of Fires Pavement Rehabilitation 2021 012200-1
SECTION 012200 – UNIT PRICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
1.2 DEFINITIONS
A. Unit price is a price per unit of measurement for materials or services added to or deducted from
1.3 the Contract Sum by appropriate modification, if estimated quantities of Work required by the Contract Documents are increased or decreased in accordance with FAR 52.211-18 Variation in Estimated Quantity.
PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, taxes, overhead, and profit.
B. Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government expense, by an independent surveyor acceptable to Contractor.
C. List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price. Lump Sum item Mobilization/Demobilization will be paid for as indicated in New Mexico Department of Transportation Standard Specifications for Highway and Bridge Construction, 2019 edition.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF UNIT PRICES
A. Pay Item 2 – Crack Sealing
1. Description: Includes all labor and materials to examine, clean, prepare and seal crack in existing asphalt pavement as directed in Plans and Specifications. See Section 02785.
July 2020 UNIT PRICES Valley of Fires Pavement Rehabilitation 2021 012200-2
2. Unit of Measurement: Linear Foot.
3. The Variation in Estimated Quantity Clause applies to this item.
B. Pay Item 3 – Asphalt Emulsion, CRS-2P
1. Description: Includes all labor and materials to furnish and install CRS-2P emulsion as directed in Plans and Specifications. See Section 02785.
2. Unit of Measurement: Ton.
C. Pay Item 4 - Crushed 3/8 inch Aggregate
1. Description: Includes all labor and materials to furnish and install 3/8 inch aggregate as directed in Plans and Specifications. See Section 02785.
2. Unit of Measurement: Ton.
D. Pay Item 5 – Asphalt for Fog Seal, CSS-1H
1. Description: Includes all labor and materials to furnish and install fog seal as directed in Plans and Specifications. See Section 02785.
2. Unit of Measurement: Ton.
E. Pay Item 6A (Additive Item) – Crushed 1/4 inch Aggregate
1. Description: Includes all labor and materials to furnish and install 1/4 inch aggregate as directed in Plans and Specifications. See Section 02785.
2. Unit of Measurement: Tons.
F. Pay Item 7A (Additive Item) – Asphalt Emulsion CRS-2P
1. Description: Includes all labor and materials to furnish and install Asphalt Emulsion CRS-2P as directed in Plans and Specifications. See Section 02785.
2. Unit of Measurement: Tons.
G. Pay Item 8 – Reflectorized Painted Pavement Markings 4”
1. Description: Includes all labor and materials to furnish and install 4” pavement markings as directed in Plans and Specifications. See Section 02765.
2. Unit of Measurement: Linear Foot.
END OF SECTION 012200
July 2020 CONTRACT MODIFICATION PROCEDURES Valley of Fires Pavement Rehabilitation 2021 012600-1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
1.2 MINOR MODIFICATIONS IN THE WORK
A. Contracting Officer will issue supplemental instructions authorizing minor modifications in the Work, not involving adjustment to the Contract Sum or the Contract Time
1.3 PROPOSAL REQUESTS
A. Government-Initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed modifications in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Proposal Requests issued by Contracting Officer are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed modification.
2. Within 20 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the modification.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the modification.
d. Include an updated Contractor's Construction Schedule that indicates the effect of the modification, including, but not limited to, modifications in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
B. Contractor-Initiated Proposal Requests: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose modifications by submitting a request for a modification to Contracting Officer.
1. Include a statement outlining reasons for the modification and the effect of the modification on the Work. Provide a complete description of the proposed modification.
Indicate the effect of the proposed modification on the Contract Sum and the Contract Time.
July 2020 CONTRACT MODIFICATION PROCEDURES Valley of Fires Pavement Rehabilitation 2021 012600-2
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the modification.
5. Include an updated Contractor's Construction Schedule that indicates the effect of the modification, including, but not limited to, modifications in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Division 01 Section "Product Requirements" if the proposed modification requires substitution of one product or system for product or system specified.
C. Proposal Request Form: Use forms provided by Contracting Officer.
1.4 MODIFICATION PROCEDURES
A. On Contracting Officer's approval of a Proposal Request, Contracting Officer will issue a Modification for signatures of Contracting Officer and Contractor on [form included at end of Part 3].
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012600
July 2020 SCHEDULE OF VALUES Valley of Fires Pavement Rehabilitation 2021 012973-1
SECTION 012973 – SCHEDULE OF VALUES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements to prepare schedule of values.
1.2 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment and Construction Schedule.
2. Submit the Schedule of Values to Contracting Officer at earliest possible date but no later than ten calendar days after the Notice to Proceed.
B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the Schedule of Values:
a. Project name and location.
b. Name of Contracting Officer.
c. Contractor's name and address.
d. Date of submittal.
2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate.[ Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training in the amount of 5 percent of the Contract Sum.]
3. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
4. Provide a separate line item in the Schedule of Values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
5. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
6. Each item in the Schedule of Values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.
July 2020 SCHEDULE OF VALUES Valley of Fires Pavement Rehabilitation 2021 012973-2
7. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Modifications or Construction Change Directives result in a change in the Contract Sum.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012973
July 2020 PROJECT MANAGEMENT AND COORDINATION Valley of Fires Pavement Rehabilitation 2021 013100-1
SECTION 013100 – PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions.
2. Informational submittals.
3. Coordination procedures.
4. Coordination drawings.
5. Project meetings.
6. Requests for Interpretation (RFIs).
7. Digital project management procedures.
8. Environmental coordination.
9. Permits.
B. See Division 01 Section "Execution Requirements" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
1.2 DEFINITIONS
A. Request for Interpretation (RFI): Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.3 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
1.4 COORDINATION PROCEDURES
A. Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
Valley of Fires Pavement Rehabilitation 2021 013100-2
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Contracting Officer and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
9. Project closeout activities.
10. Commissioning activities.
1.5 COORDINATION DRAWINGS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer for
Valley of Fires Pavement Rehabilitation 2021 013100-3 resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
B. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
1.6 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Contracting Officer of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Contracting Officer, within five days of the meeting.
B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Contracting Officer, but no later than 30 days after execution of the Agreement. Hold the conference at Project site or another convenient location.
Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.
1. Attendees: Authorized representatives of Government, and its consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Modifications.
f. Procedures for RFIs.
Valley of Fires Pavement Rehabilitation 2021 013100-4
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. LEED requirements.
l. Preparation of Record Documents.
m. Use of the premises.
n. Work restrictions.
o. Government occupancy requirements.
p. Responsibility for temporary facilities and controls.
q. Construction waste management and recycling.
r. Parking availability.
s. Office, work, and storage areas.
t. Equipment deliveries and priorities.
u. First aid.
v. Security.
w. Progress cleaning.
x. Working hours.
3. Minutes: Record and distribute meeting minutes.
1.7 REQUESTS FOR INTERPRETATION (RFIs)
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.
1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:
1. Project name.
2. Date.
3. Name of Contractor.
4. Name of Contracting Officer
5. RFI number, numbered sequentially.
6. Specification Section number and title and related paragraphs, as appropriate.
7. Drawing number and detail references, as appropriate.
8. Field dimensions and conditions, as appropriate.
9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
10. Contractor's signature.
11. Requested date for response.
12. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop
Drawings, and other information necessary to fully describe items needing interpretation.
Valley of Fires Pavement Rehabilitation 2021 013100-5
Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFIs: Provided by Contracting Officer
1. Identify each page of attachments with the RFI number and sequential page number.
D. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and return it. Allow 21 calendar days for Contracting Officer's response for each RFI.
RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor’s means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Contracting Officer's actions on submittals.
g. Incomplete RFIs or RFIs with numerous errors.
2. Contracting Officer's action may include a request for additional information, in which case Contracting Officer's time for response will start again.
E. On receipt of Contracting Officer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven days if Contractor disagrees with response.
F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log monthly. (If there are no RFIs on project, RFI log will not need to be submitted.)
Include the following in submittal of RFI log:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Contracting Officer.
4. RFI number including RFIs that were dropped and not submitted.
5. RFI description.
6. Date the RFI was submitted.
7. Date Contracting Officer's response was received.
8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.
1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Digital Data Files Not Available: BLM will not provide CAD drawing digital data files for Contractor's use during construction.
B. PDF Document Preparation: Where PDFs are required to be submitted, prepare as follows:
Valley of Fires Pavement Rehabilitation 2021 013100-6
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.9 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Ensure compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Monitor and document environmental procedures.
B. Perform project quality control in accordance with specified requirements including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Construction Waste Management.
C. Contractor’s Environmental Training Program: Provide environmental training for workers performing work on the project site, include:
1. Overview of environmental issues related to the Project.
2. Review of site specific procedures and management plans:
a. Construction Waste Management.
3. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
D. Green Building Rating
1.10 PERMITS
A. General:
1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for
Valley of Fires Pavement Rehabilitation 2021 013100-7 complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.
B. Government Furnished Permits: During the development of the project’s design the permits listed below were negotiated and agreed to by the Government. The terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. None.
C. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, to avoid conflicts and to ensure orderly execution of the Work.
2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.
3. Provide copies of permits to Contracting Officer upon request.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
July 2020 CONSTRUCTION PROGRESS DOCUMENTATION Valley of Fires Pavement Rehabilitation 2021 013200-1
SECTION 013200 – CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Submittals Schedule.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Float: The measure of leeway in starting and completing an activity.
E. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
F. Major Area: A story of construction, a separate building, or a similar significant construction element.
1.3 SUBMITTALS
A. Submittals Schedule: Submit electronic (pdf) copy of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
Valley of Fires Pavement Rehabilitation 2021 013200-2
4. Name of subcontractor.
5. Description of the Work covered.
6. Scheduled date for Contracting Officer's final release or approval.
B. Contractor's Construction Schedule: Submit electronic (pdf) copy of initial schedule in Gantt Chart format, large enough to show entire schedule for entire construction period.
1. Submit an electronic copy of schedule, using software indicated, labeled to comply with requirements for submittals. Include type of schedule (Initial or Updated) and date on label.
1.4 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.5 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.
2. Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
1.6 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Modification.
B. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
Valley of Fires Pavement Rehabilitation 2021 013200-3
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Contracting Officer.
2. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.
3. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Contracting Officer's administrative procedures necessary for certification of Substantial Completion.
C. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion, and the following interim milestones:
1. Chip Seal Completion.
2. Fog Seal Completion.
3. Pavement Marking Completion.
D. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
E. Distribution: Distribute copies of approved schedule to Contracting Officer.
1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 15 days of date established for the Notice of Award.
Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.
B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.
1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.
Valley of Fires Pavement Rehabilitation 2021 013200-4
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION (Not used)
END OF SECTION 013200
July 2020 SUBMITTAL PROCEDURES Valley of Fires Pavement Rehabilitation 2021 013300-1
SECTION 013300 – SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals.
B. See Division 01 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule.
C. See Division 01 Section "Quality Requirements" for submitting test and inspection reports.
D. See Division 01 Section "Closeout Procedures" for submitting warranties.
E. See Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.
F. See Division 01 Section "Operation and Maintenance Data" for submitting operation and maintenance manuals.
G. See Division 01 Section "Demonstration and Training" for submitting video of demonstration of equipment and training of Government personnel.
H. See Division 02 for lists of specific items that will require approved submittals before installation.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer's responsive action.
B. Informational Submittals: Written information that does not require Contracting Officer's responsive action. Submittals may be rejected for not complying with requirements.
C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
Valley of Fires Pavement Rehabilitation 2021 013300-2
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.
D. Paper Submittals:
1. Place a permanent label or title block on each submittal for identification; include name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Contracting Officer.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Architect.
d. Name and address of Contractor.
e. Name and address of subcontractor.
f. Name of firm or entity that prepared submittal.
g. Name and address of supplier.
h. Name of manufacturer.
i. Submittal number or other unique identifier, including revision identifier.
Valley of Fires Pavement Rehabilitation 2021 013300-3
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A). Work schedule and value schedules shall be numbers
01000.01 and 01000.02.
j. Number and title of appropriate Specification Section.
k. Drawing number and detail references, as appropriate.
l. Location(s) where product is to be installed, as appropriate.
m. Other necessary identification.
E. Approved Equals:
1. For each item proposed as an “or approved equal,” submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
F. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
G. Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other format indicated by Project software website.
H. Additional Copies: Unless additional copies are required for final submittal, and unless Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
I. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Contracting Officer will return submittals, without review received from sources other than Contractor.
1. Transmittal Form: Use form as directed by Contracting Officer.
Valley of Fires Pavement Rehabilitation 2021 013300-4
J. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked "<Insert approval notation from Contracting
Officer's action stamp>."
K. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
L. Use for Construction: Use only final submittals with mark indicating "“Approved” or “Approved with notations”. taken by Contracting Officer.
1.4 ACTION SUBMITTALS
A. Prepare and submit Action Submittals required by individual Specification Sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Printed performance curves.
g. Operational range diagrams.
h. Compliance with specified referenced standards.
i. Testing by recognized testing agency.
j. Standard color charts
k. Availability and delivery time information
l. Clearances required to other construction, if not indicated on accompanying Shop
Drawings
4. Number of Copies: Submit three copies of Product Data, unless otherwise indicated.
Contracting Officer will return two copies. Mark up and retain one returned copy as a Project Record Document.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale.
This is the start of the file's text. The full file is on GovTribe.