This document is a Statement of Work (SOW) for the upgrade of the DC power plant that supports the Ciena equipment in Building 90215 located on Hurlburt Field, FL. The key requirements include installing a new 48VDC power plant system with 1200amp FLATPACK2 HE rectifiers or equivalent, extending the existing cable rack, installing a new aisle ground and 750MCM reference ground, adding two 827E inverter modules, and removing the existing Peco II rectifier bay. The work must be completed with zero downtime to facility operations and in accordance with the Davis-Bacon Act wage rate requirements. The government will provide access to the facility and coordinate the maintenance window. The contractor must provide a project schedule that includes client milestones, design, configuration, on-site work, and customer training. This SOW is associated with Solicitation Number FA441724Q0095 issued by the Department of the Air Force Special Operations Command for the DC Power Plant Upgrade at Building 90215.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001 - Combined Synopsis Solicitation - DC Power Plant Upgrade.pdf.pdf | ||
| Attch 1 - SOW - DC Power Plant Upgrade Bldg 90215 (Revised 9 May 2024).pdf | ||
| Site Visit Briefing - DC Power Plant Upgrade Bldg 90215.pdf | ||
| Attch 2 - Wage Determination FL20240217.pdf | ||
| Combined Synopsis Solicitation - DC Power Plant Upgrade.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW) for AFSOC SOACS Provide/Install DC Power Plant, Building 90215
Hurlburt Field, FL 16 April 2024
1. AFSOC SOACS requires an upgrade of the DC power plant that supports the Ciena equipment located in building 90215 located on Hurlburt Field, FL.
2. Requirements/New Equipment.
• Eltek EcoTower DC plant or equivalent o 48VDC power plant system o 1200amp
• FLATPACK2 HE RECTIFIER or equivalent.
o Rectifier 3000W 48V, -INPUT: 85-305VAC; FAN COOLED (FRONT TO
BACK); -OUTPUT: 3000W @ 176-305VAC, 3000W @ 176VAC LINEARLY
TO 1382W @ 85VAC. -EFFICIENCY: >96.2%; -OPERATING
TEMPERATURE: -40 TO +45°C: 3000W; LINEARLY DERATE FROM
3000W @ 46°C TO 2100W @ 75°C; SHUTDOWN AT 75°C,
AUTOMATICALLY RESTART AT LOWER TEMPERATURE -STORAGE
TEMPERATURE: -40 TO +85°C or
• Inverter Expand 1 2KVA Power Module. PN: SI10A120PME o Must fit into existing PECO 827E inverter shelf
• Cable, lugs, anchors, wire, etc. as required for installation.
Requirements:
• Install (1) DC plant.
• Extend existing cable rack above new DC plant.
• Install new aisle ground for DC power line up.
• Install new 750MCM reference ground.
• Install (12) 3000watt rectifiers.
• Cable new DC system to existing distribution and battery strings.
• Turn down and remove existing Peco II rectifier bay.
• Add (2) 827E inverter module to the existing 827E inverter Rectifier.
• Follow NEC code book
Construction-related:
• With zero (0) downtime to facility operations and without replacing the entire breaker panel, certified electricians shall make all necessary modifications to the existing electrical panel to ensure all systems and installed equipment are fully operational. Wage Rate Requirements (Construction), formerly known as the Davis-Bacon Act, will be in effect.
Assumptions:
• Assumed DC plant load of 410 amps and existing batteries will remain.
3. The Government will be responsible for and provide the following:
• Coordinating maintenance window as required.
• Access to the facility.
STATEMENT OF WORK (SOW) for AFSOC SOACS Provide/Install DC Power Plant, Building 90215
Hurlburt Field, FL 3 April 2024
4. Project schedule must be provided, which will include client milestones, design, configuration, on-site work, and customer training and is based on the assumptions listed above.