SFO - 2021 HSP Chupadera Mesa Wildlife Water Fence and Catchment

SFO - 2021 HSP Chupadera Mesa Wildlife Water Fence and Catchment Socorro County, New Mexico

Statement of Work 2021 HSP Chupadera Mesa Wildlife Water Fence and Catchment includes work on a water catchment and a pipe fence exclosure. The catchment and associated fence are existing New Mexico Department of Game and Fish Habitat Stamp Program projects. Details are included in this Statement of Work.

Location of Project The project area is located on Bureau of Land Management (BLM) administered lands on Chupadera Mesa about 40 miles East of Socorro, New Mexico in Socorro County. In Section 5 of Township 5 South, Range 7 East, see Maps.

Boundaries of Project Areas At the site, the desired location of the catchment, the storage tank, and the trough will be marked. Also, the fence corners (four) will be marked with lathe and flagging.

Access From Socorro travel south on Interstate 25 approximately 8 miles to San Antonio, NM. Then take HWY 380 east approximately 30 miles until CR 175 heading north. Drive approximately 12 miles of county roads and 2.5 miles two tracks, with ¼ mile of off-road travel to the project area (see map). All vehicles shall remain on existing roads, except for the temporary access route to project site. No Off-Highway Vehicle (OHV) use is authorized nor permitted as part of the project. No vehicle access will be allowed off existing travel routes other than that outlined to implement the project.

Project Purpose The purpose of this contract is to reconstruct wildlife water catchment facilities with exclosure fence to provide improved wildlife habitat.

A.1.0

GENERAL

A.1.1

DESCRIPTION OF WORK

The Bureau of Land Management-Socorro Field Office (BLM-SFO) has a requirement to construct an exclosure, 1.5 acre in size (approximately 1100 ft. +/- 50 ft.). The exclosure fence will be a pipe rail with two cable strands (see attached drawings). Also, to be constructed is a water catchment structure - constructed of pipe and purlins, with a propanel roof. The water catchment roof is composed of two- 20’ X 25’ structures which sloped inward and drained into a 6” galvanized gutter. The catchment will feed into a UV resistant HDPE 5,000-gallon low profile storage tank. The contractor will bury the storage tank to 20”, level, and bed the bottom of the hole and ensure tank is level and tank bed is free of sharp rocks that could puncture tank. The storage tank will be plumbed to a 1 ¼” brass ball valve to be enclosed in a HDPE valve box. The storage tank will then be plumbed with 1 ¼” HDPE poly pipe which will feed the rainmaker trough that has a self-contained plumbing float valve built in. HDPE poly fittings will be welded with a pipe welder and pipe will be buried to 24”. The contractor shall complete tasks described under section A.4.0 as SPECIFIC TASKS and abide by items described under section A.6.0 and A.7.0. The contractor shall ensure that all equipment, tools, supervision, and other items and services are provided to perform required tasks, except as specified in section A.3 as GOVERNMENT FURNISHED PROPERTY AND SERVICES. The construction project shall be completed between March 1 and May 15, 2021, as conditions allow.

A.1.2

PROJECT LOCATION

The project area is located on Bureau of Land Management (BLM) administered lands on Chupadera Mesa about 40 miles East of Socorro, New Mexico in Socorro County. In Section 5 of Township 5 South, Range 7 East, see Maps.

A.2.0

CONTRACTOR FURNISHED ITEMS

1. Vehicle

2. Vehicle and trailer to haul government furnished supplies from Socorro, NM to project site. Project materials will be in Socorro, NM at Middle Rio Grande Conservancy District Yard. ACCESS and loading arrangements must be made with BLM to pick up supplies Monday through Thursday during business hours. The quikrete concrete mix will be available for pick up from a local vendor in Socorro or Lemitar, NM.

3. All tools required to perform construction operations.

4. Water for mixing of quikrete Redi-mix concrete.

5. All construction equipment necessary to complete project, such as welder to weld structure and fence, auger to drill post holes, implement necessary to trench poly pipe to 24”, and equipment needed to set and bed tank at 20” deep.

6. HDPE Poly pipe welder to weld fusible fittings.

7. Equipment necessary to move and stretch cable up to 5/8” diameter in size.

A.2.1 The Government assumes no responsibility for damage to equipment due to work that is within the scope of this contract.

A.3.0

GOVERNMENT FURNISHED PROPERTY AND SERVICES

1. Inspections, Map, Specifications, and drawings

2. Custom 6” gutter

3. 1 ¼’ HDPE Poly pipe that goes between storage tank and wildlife drinker

4. Rainmaker trough which includes self-contained float

5. 2 3/8” heavy wall pipe, quikrete, cable size 3/8” minimum, and fence hardware (springs, clips, and turn buckles).

6. 2 3/8” heavy wall pipe for frame of water catchment, quikrete, 6” C Purlin, 6”x ¼” gussets, 4” x ¼” lateral gussets for corners, 2 ½”x ¼” straps, 26-gauge green propanel, lap green propanel screws for tin to tin, self-tapping green propanel screws for drilling tin to purlins, green J trim for two 25’ outside sides, green gable trim for four 20’ sides, caps for drill pipe ends, any other items shown in drawings.

7. One - UV Resistant HDPE water storage tank: 5,000 gallon, dimensions: 12’ diameter, 8’ in height.

8. Schedule 80 PVC pipe and plumbing fittings from custom 6” gutter to storage tank, 1 ¼” brass ball valve, fusion fittings, valve box, and plumbing from 1¼” poly to trough.

A.4.0

SPECIFIC TASKS FENCE

A. Construction Operations

1. Transport all government provided project materials and supplies (pipe, quikrete, cable, and hardware) to project site.

2. Supports: Bury and set-in cement all top rail supports/uprights (pipe fence posts) at a depth of 2 feet below ground, except for gate hinge post and corner posts which shall be buried 3 feet below ground level. All supports shall be set at 40 inches above natural grade contour of ground. Fence Posts shall have a saddle cut in them to accommodate top rail. Spacing between supports (posts) will be 12 feet.

3. Top rail: top rail shall be welded to rail supports at a height of 40 inches above ground. Top rail shall be one continuous piece and shall not contain any step downs or irregularities. No exceptions will be granted!

4. Expansion Sleeves: Expansion sleeves shall be incorporated into the fence at each corner (see diagram). A one-foot piece of 2 7/8” heavy drill stem pipe shall be used for the expansion sleeves. Sleeve shall have at least six inches of expansion distance once installed. Sleeves shall be installed in the center of each straight run. If topography causes an abrupt break in the run, more than one sleeve may be needed.

5. The cable clips are 3/8” hot rolled bracket as shown in drawings. Clips shall be welded at a height of 16 inches and a height of 26 inches above natural grade contour of ground to accommodate cable. Clips shall be welded on the outside of post. Clips shall be 3/8” x 4”.

6. Cable: Cable diameter shall be a minimum of 3/8” diameter. If used cable is utilized, cable shall be free of obvious rust or other damage which would cause the cable to become weak and brittle.

7. Cable Installation: Cable shall be strung through clips welded on uprights at heights of 16 inches (bottom strand) and 26 inches (second strand) above ground level, and cables shall be stretched tight with a single stand (no splices) from corner post to corner post. Cable shall be installed on the outside of exclosure. Cable shall be in complete runs from corner post to corner post. Two pieces of cable shall not be spliced together to form one length between corners nor shall one strand of cable be used to around the entire exclosure.

8. Springs: springs shall be installed at each corner for a minimum of one per side. Springs shall be 12 inches in length (see diagram). Sample springs will be available at project site visit. Springs shall be installed opposing the turnbuckles at each corner.

9. Turn Buckles: turn buckles shall be installed at each corner for a minimum of one per side. Turn buckles shall be a minimum 20 inches in length and designed to be utilized with 5/8 or ½” cable (see diagram). Turnbuckles shall be the closed eye type only. Sample turnbuckles will be available at project site visit. Turnbuckles shall be installed opposing the springs at each corner.

10. Cable Clamps: A minimum of two clamps per terminal end need to be installed. All clamp nuts shall be welded upon installation.

11. Spacing specifications (16”, 26”, and 40”) shall be consistent at all points along fence, such as in between posts, and not just at uprights or posts. Keep in mind that additional posts or uprights may need to be installed for the fence to be in compliance with contract fence spacing specification’s, particularly within drainage crossings and uneven slopes, so plan accordingly. [This may mean that additional posts/uprights may need to be installed within that 12-foot spacing between uprights.]

12. Gate: A 12-foot gate shall be constructed at the designated site along enclosure. Gate shall be constructed utilizing 2 3/8” heavy wall pipe at the same spacing as the fence. A locking mechanism/hasp shall be installed to accommodate a lock (see diagram). Hasp shall be constructed of ¼ inch thick x 4 inches wide strap metal and a 3/8 inch half chain link (see diagram). Gate shall follow same spacing and contour as fence rail and cables.

13. SPECIFIC TASKS WATER CATCHMENT

1. Vertical drill stem support posts will be buried 36” and filled with concrete with a minimum of 3” concrete cover between ground and pipe.

2. The structure is composed of two separate frames. The outer members of each frame shall be constructed of 4 each 6” receiver channel purlins. All receiver channel purlin-to-pipe and purlin-to-purlin vertical and lateral connections must have a gusset installed.

3. Welds shall be continuous along all mating surfaces, no tack welds.

4. Where C-purlins tie into receiver channel purlins along outer edges of frame will have continuous welds.

5. Straps connecting purlins to pipe support frame are 2 ½” x ¼”.

6. Pipe to pipe gussets are to be a minimum 6” x ¼”.

7. Vertical-pipe-to-purlin gussets are to be minimum 6” x ¼”. Lateral-pipe-to purlin gussets are to be minimum 6” x ¼”. All gussets welded to pipe shall be saddle-cut for proper weld connection.

8. Pipe-to-pipe connections: vertical pipe shall be saddle-cut for proper welded connection.

9. Gap between frames should be no less than 6 ½” to accommodate 6” gutter (to storage).

10. Frame is level front-to-back. Gutter is sloped vs sloping frame. Slope gutter 3” toward storage.

11. Vertical distance from bottom of gutter fitting to reservoir inlet shall be no less than 24” to accommodate plumbing. Horizontal distance from the catchment frame to the reservoir shall be no less than 3 feet.

12. There shall be no overhang of tin roofing past edge purlin. Fold sheet metal over purlin edge.

13. All open pipes shall be capped at ends.

14. Sheet metal gutter to be provided by BLM and installed by contractor.

15. Height of catchment varies from site to site due to changes in terrain, etc. Install per government instructions.

16. Green 2 ½’ J-trim will be installed on the two 25’ outside sides. Green 4” gable trim will be installed on the four 20’ sides.

SPECIFIC TASKS STORAGE TANK & WILDLIFE DRINKER

1. A 3” schedule 80 PVC pipe with appropriate elbows will be placed to get water from gutter into storage tank. After dry fitting the pipes will be glued with pvc cement.

2. Bury storage tank base to 20” deep, level, and bed the bottom of the pad and ensure tank is level and pad is free of sharp rocks that could puncture tank.

3. The storage tank will be plumbed from standard 2” bulkhead to a 1 ¼” brass ball valve to be enclosed in a valve box.

4. The storage tank will then be plumbed with 1 ¼ “poly which will feed the rainmaker trough which had self-contained plumbing built in.

5. Poly fittings will be welded with a pipe welder and pipe will be buried to 24”

6. Inlet to wildlife drinker is 1 inch in size, so a 1 ¼” to 1” reducer will be needed.

7. Wildlife drinker will be leveled first then backfilled.

A.5.0 Prohibited Tasks:

A.5.0 Prohibited Tasks:

Live shrubs and trees shall not be removed unless approved by BLM representative.

No blading, shoveling, digging, scarping or other surface disturbance shall occur to create additional project access, to level off project site, or to get fence spacing in compliance with project specifications, within and around the project site.

No additional project vehicular access shall be created or utilized other than the one identified by the BLM representative.

Work will not be done when wet or times that additionally resource damage would occur.

Contractor is responsible for all fire prevention, suppression and containment.

A.6.0 Project Site Reclamation:

· Project area shall be reclaimed to pre-project conditions. Disturbed areas shall be raked and where possible debris placed across tracks and disturbed areas.

· All trash and project debris shall be picked up and removed from project site.