Attatchment 1- Specs CLAMP (WLIC 75D) DD FQ1 BMS 26R0.pdf

PDF 1 MB Posted

Attached to
USCGC CLAMP (WLIC 75310) & USCG 68B BARGE (68016) Dry Dock Availability (FY25) FY26
Solicitation number
70Z08526QIBCT0001
Issued by

About this file

This document is a detailed specification for the drydock availability of the USCGC CLAMP (WLIC 75D) tender and a 68' Coast Guard Barge (CGB 68016) for Fiscal Year 2026. The specification covers comprehensive maintenance and repair work, including hull plating renewal, propulsion shafting inspections, rudder assembly removal and reinstallation, cathodic protection zinc anode replacement, fathometer transducer maintenance, and drydocking procedures. The work will be performed at a commercial contractor's facility, with specific technical requirements outlined for each work item, such as surface preparation, coating, inspections, and testing.

The solicitation is a 100% small business set-aside, with award determined by evaluating price and non-cost factors, with technical and past performance being more important than price. Offerors must provide a minimum 60-day warranty on all repair work and fully comply with all solicitation requirements. The contract involves detailed technical specifications for multiple vessel systems, including ultrasonic testing, coating preservation, mechanical overhauls, and operational testing of various shipboard components, with the goal of maintaining the operational readiness of the USCG tender and barge.

View the file

Other files

File Type Posted
Attatchment 2-Blank Section B.xlsx XLSX spreadsheet
Attachment 3 - Past Performance Information Form CLAMP.docx DOCX document
70Z08526QIBCT0001_Review Revised.pdf PDF
Attatchment 5.pdf PDF
Attachment 4 - Request for Clarification Form.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC CLAMP (WLIC 75306)

USCG 68B BARGE (68016)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2026

Developed By: Brandee M Schiller

(Rev-0, 24 April 2025)

USCGC CLAMP (WLIC-75D) DRYDOCK AVAILABILITY FY2026

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record...............................................................................................................................iii Consolidated List of References .........................................................................................................iv Consolidated List of Government-furnished Property .........................................................................viii Consolidated List of Critical Inspection Items .....................................................................................ix Principal Characteristics - Tender ........................................................................................................x Principal Characteristics - Barge .........................................................................................................xi General Requirements WORK ITEM 1: Fire Prevention Requirements WORK ITEM 2: Hull Plating, U/W Body, Inspect - Tender WORK ITEM 3: Hull Plating, U/W Body, Ultrasonic Testing - Tender WORK ITEM 4: Hull and Structural Plating, General, 10.2 lbs. Steel, Renew - Tender WORK ITEM 5: Hull and Structural Plating, General, 12.75 lbs. Steel Plate, Renew - Tender WORK ITEM 6: Hull and Structural Plating, General, 15.3 lbs. Steel Plate, Renew - Tender WORK ITEM 7: Hull And Structural Plating, General, 20.4 lbs. Steel Plate, Renew - Tender WORK ITEM 8: Hull and Structural Plating, General, 7.65 lbs. Steel Plate, Renew - Tender WORK ITEM 9: Hull and Structural Plating, General, Degraded Weld, Steel, Repair - Tender WORK ITEM 10: Propulsion Shafting, Strain Gage Alignment, Inspect WORK ITEM 11: Propulsion Shafting; Remove, Inspect, and Reinstall WORK ITEM 12: Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renew WORK ITEM 13: Propulsion Shaft Bearings, External, Renew WORK ITEM 14: Propeller s, Remove, Inspect, and Reinstall WORK ITEM 15: Keel Coolers, Clean, Inspect and Hydro WORK ITEM 16: Rudder Assembly, Remove, Inspect And Reinstall WORK ITEM 17: Rudders, Preserve, 100 Percent WORK ITEM 18: Cathodic Protection, Zinc Anodes, Renew, - Tender WORK ITEM 19: Drydock - Tender WORK ITEM 20: Temporary Services, Provide - Tender WORK ITEM 21: Sea Trial Performance, Support, Provide WORK ITEM 22: Hull Plating, U/W Body, Inspect - Barge WORK ITEM 23: Hull Plating, U/W Body, Ultrasonic Testing - Barge WORK ITEM 24: Hull and Structural Plating, General, 10.2 lbs. Steel, Renew - Barge WORK ITEM 25: Hull and Structural Plating, General, 12.75 lbs. Steel Plate, Renew - Barge WORK ITEM 26: Hull and Structural Plating, General, 15.3 lbs. Steel Plate, Renew - Barge WORK ITEM 27: Hull and Structural Plating, General, 7.65 lbs. Steel Plate, Renew - Barge WORK ITEM 28: Hull and Structural Plating, General, Degraded Weld, Steel, Repair - Barge WORK ITEM 29: Fathometer Transducer, General Maintenance - Barge WORK ITEM 30: Cathodic Protection, Zinc Anodes, Renew - Barge WORK ITEM 31: Temporary Services, Provide - Barge Barge WORK ITEM 32: Hull Fittings, Weight Handling Rigging Hardware, Inspect and Test - Barge WORK ITEM 33: Spuds, Overhaul - Barge WORK ITEM 34: Drydock - Barge WORK ITEM 35: Fathometer Transducer, General Maintenance WORK ITEM 36: Hull And Structural Plating, General, 20.4 lbs. Steel Plate, Renew - Barge WORK ITEM 37: Propulsion Shaft Rope Guards, Inspect WORK ITEM 38: Barge, Diesel Engine Exhaust Piping, Commercial Clean iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev -0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

75 WAGL 2200-010, -Rev D, Main Rudder Stock And Fittings For Jastram S2-16-2-35 Steering System

75 WAGL 2200-011, Rev D, Flanking Rudder Stock And Fittings For Jastram S2-16-2-35 Steering System

APM: Ensure all references are latest version in CG-LIMS. If editing a WI's References, change the same ref. in the Spec's Consolidated List of References and contact the SES section chief to change the source WI. Ensure any MS Word “Comments” and Tracked Changes are removed before uploading the Spec package or delivering to CPD.

Coast Guard Drawing 68 CGB 0700-003, Rev -, 68FT Steel Barge Docking Block Arrangement (“A” and “B” Class)

Coast Guard Drawing 68 CGB 0700-003, Rev-, 68FT Steel Barge Docking Block Arrangement (“A” and “B” Class)

Coast Guard Drawing 68 CGB 0700-003, Rev. -, 68FT Steel Barge Docking Block Arrangement (“A” and “B” Class)

Coast Guard Drawing 68 CGB 1101-001, Rev -, 68FT Steel Barge Structural Sections & Details (CGB 68012-68014)

Coast Guard Drawing 68 CGB 1101-003, Rev C, 68FT Steel Barge Lines, Plating, and Deck & Bottom Framing Plans (CGB 68016-68017)

Coast Guard Drawing 68 CGB 1101-003, Rev C, 68FT Steel Barge Lines, Plating, and Deck & Bottom Framing Plans (CGB 68018-68020)

Coast Guard Drawing 68B CGB 2901-004, Rev -, Curves of Form

Coast Guard Drawing 68B CGB 2901-004, Rev-, Curves of Form

Coast Guard Drawing 68B-CGB 1103-1, Rev C, Lines, Plating & Deck & Bottom Framing Plans

Coast Guard Drawing 68-CGB 1101-1, Rev -, Structural Sections & Details

Coast Guard Drawing 68-CGB 1112-2, Rev -, Transducer Wet Wall & Blister Installation

Coast Guard Drawing 75 WAGL 0700-004, Rev A, Docking Plan

Coast Guard Drawing 75 WAGL 2901-004, Rev -, Curves of Form

Coast Guard Drawing 75 WAGL 633-001, Rev A, Cathodic Protection

Coast Guard Drawing 75 WLIC 111-002, Rev -, Grid Cooler Recess (AXE)

Coast Guard Drawing 75 WLIC 536-001, Rev -, Diagram Jacket Water System (AXE)

Coast Guard Drawing 75 WLIC 536-002, Rev A, Main Engine & Generator Jacket Water System Arrangement & Details (AXE) v (Rev-0)

Coast Guard Drawing 75B WAGL 4301-005, Rev D, Shafting Installation to Suit IF 1312 MDE (VISE &

MALLET)

Coast Guard Drawing 75B WAGL 4301-006, Rev C, Shafting Installation to Suit IF 1312 MDE

(SLEDGE)

Coast Guard Drawing 75D 2200-016, Rev D, Rudder Post Installation For Jastrum S2-16-2-35 Steering System

Coast Guard Drawing 75D WAGL 0500-003, Rev -, Lines and Offsets

Coast Guard Drawing 75D WAGL 0700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement

Coast Guard Drawing 75D WAGL 1101-001, Rev C, Shell Expansion (75306)

Coast Guard Drawing 75D WAGL 1101-001, Rev C, Shell Expansion (75306-75307)

Coast Guard Drawing 75D WAGL 1101-006, Rev B, New Grid Cooler Pocket P/S to Suit 80MDDCD

SSDG (CLAMP & HATCHET)

Coast Guard Drawing 75D WAGL 4103-021, Rev C, Jacket Water Mods to Suit 80MDDCD SSDG

(CLAMP & HATCHET)

Coast Guard Drawing 75D WAGL 4103-024, Rev A, Jacket Water Mods to Suit IF1312 MDE (CLAMP

& HATCHET)

Coast Guard Drawing 75D WAGL 4301-003, Rev E, Shafting Installation to Suit IF 1312 MDE

Coast Guard Drawing 75D WAGL 700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement

Coast Guard Drawing 75D-WAGL 4301-3, Rev -, Shafting Installation to Suit If 1312 MDE

Coast Guard Drawing 75D-WAGL 4301-3, Rev E, Shafting Installation to Suit If 1312 MDE

Coast Guard Drawing 75D-WAGL 4301-3, Rev E, Shafting Installation to Suit If 1312 MDE

Coast Guard Drawing 75D-WAGL-2200-014, Rev B, Steering System Arrangement For Jastram S2-16- 2-35

Coast Guard Drawing 75D-WAGL-2200-015, Rev C, Flanking Steering System Arrangement For Jastrum S2-16-2-35

Coast Guard Drawing 75-WAGL 4301-5, Rev N, Shafting Machining Details to Suit If 1312 MDE

Coast Guard Drawing 75-WAGL 4400-3, Rev L, Propeller to Suit IF1312 MDE

Coast Guard Drawing 75-WAGL 4301-5, Rev N, Shafting Machining Details to Suit If 1312 MDE

Coast Guard Drawing 75-WAGL 4400-3, Rev L, Propeller to Suit IF1312 MDE

Coast Guard Drawing 75-WLIC 4901-001, Rev -, Emergency Shaft Seal Air Supply

Coast Guard Drawing FL 6713-203, Rev -, CRP-V850 Transducer (SS505) Adapter Assembly

Coast Guard Fleet Drawing FL 2602-10, Rev R, Spud Arrangements and Details

NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes

Coast Guard Drawing 68B CGB 5501-1, Rev B, Fuel Oil & Exhaust Piping – Plan & Details

COAST GUARD PUBLICATIONS

«REF_A»

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 3494, 09-DEC-03, Shaft Seal - Type Fse

Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock Seal Type EL

Coast Guard Technical Publication (TP) 5491, SWBS 256, Apr 2013, Keel Grid Cooler (Duramax) vi (Rev-0)

Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2020, Drydocking

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary Services

OTHER REFERENCES

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN)

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene Glycol (For Caterpillar equipment applications, use CAT Extended Life Pre-Mix coolant.)

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust- Petrolatum

Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert

International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation vii (Rev-0)

MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold -Application

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning

The Society for Protective Coatings SSPC-SP 10/NACE No.2, Jan 2007, Near-White Blast Cleaning

The Society for Protective Coatings SSPC-SP 11, Jul 2012, Power Tool Cleaning to Bare Metal viii (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

11 Y **Propeller shaft NSN: 2010-01-557-1512 1 ea. 19,184.17

12 N Wartsila FSE H74537- 02 Major Overhaul Kit

(WLP001365-001)

NSN: 01-560-3274 2 ea. 7,680.00

14 Y Propeller right hand NSN: 2010-01-534-9089 1 ea. 10,129.00 14 Y Propeller left hand NSN: 2010-01-534-9095 1 ea. 10,129.00

15 Y MDE Keel Cooler NSN: 2040-01-F11-2291 PN:

SC-418DP-114

2 $10,621.50

16 Y **Rudder - Steering NSN: 2040-01-530-9095 2 ea. 42,634.59 16 Y **Rudder - Flanking NSN: 2040-01-531-4393 2 ea. 51707.25

16 N **Upper Rudder bearing (SKF PN

23222CC/W33)

NSN: 3110-01-F11-2241 4 ea. 709.75

16 N Rudder EL Seal, Major Overhaul Kit (WLP-

001427001)

NSN: 5330-01-646-5935 4 ea. 3,795.62

19 Y *Transducer Cover Plate

N/A 1 ea. 50.00

29 N ***Fathometer Transducer, Shallow Water, 50-200 kHz (Airmar Technology

SS505)

NSN: 5845-01-470-2500 1 ea. 343.63

34 Y *Transducer Cover Plate

N/A 4 ea. 50.00

35 N Water-Air Reel and Hose Assy

NSN: 4910-01-546-0956 1 ea. 380.25

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter ix (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item

Title

3 Hull Plating, U/W Body, Ultrasonic Testing - Tender

11 Propulsion Shafting; Remove, Inspect, and Reinstall

12 Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renew

13 Propulsion Shaft Bearings, External, Renew

16 Rudder Assembly, Remove, Inspect And Reinstall

23 Hull Plating, U/W Body, Ultrasonic Testing - Barge x (Rev-0)

PRINCIPAL CHARACTERISTICS - TENDER

75' WLIC (D-CLASS), TENDER

PHYSICAL

Length overall 75' 0"

Depth 7' 7-3/4"

Maximum beam 22' 0"

Height of highest projection 32' 0"

Full load draft 4' 4 11/16" LCF Draft

Full load displacement 148.49 Long Tons Fresh Water

Shore tie voltage requirements 440 VAC / 3 Phase

Frame spacing 1' 6"

HULL

Hull material Steel

MACHINERY

Number of propellers 2

Number of blades 4

Diameter of propeller 48"

Pitch 40" fixed

RPM 400

Shaft Diameter 4.5”

TANK CAPACITIES

Fuel tanks

Fresh water tanks

Lube oil xi (Rev-0)

PRINCIPAL CHARACTERISTICS - BARGE

68' CGB (B-CLASS: 68016 -68020), BARGE

PHYSICAL

Length overall 68' 6-1/2"

Depth 7' 0"

Maximum beam 28' 0"

Full load draft 3' 0"

Full load displacement 117 Long Tons

Shore tie voltage requirements 440 VAC / 3 Phase

Frame spacing 1' 0"

1 (Rev-0)

00000_0824_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under

2 (Rev-0) the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3 (Rev-0)

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in

NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, 4 (Rev-0) code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close -out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final sy stem cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

8 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

10 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

11 (Rev-0)

4.2 Tank and Void Assessment form.

12 (Rev-0)

13 (Rev-0)

55500_ACC_0323_IBCT

WORK ITEM 1: Fire Prevention Requirements

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to minimize shipboard fire risk and to clarify the Contractors’ role in fire prevention and response.

NOTE

This work item is not separately priced. Factor fire prevention and response costs into bid of affected work items.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 Fire Plan. The Contractor must develop and implement a written fire plan in accordance SFLC Std Spec 5550. The Contractors Fire Plan must address Fire Protection and Response specifics as required in this Work Item.

3.1.1 The availability’s specific Fire Plan must always address the following:

• material condition and fire protection boundary obstruction mitigations

• inoperable fittings log

• fire alarms

14 (Rev-0)

• firefighting equipment disposition

3.1.2 The Fire Plan must also address the following:

• fire protection system status

• communication links

• temporary services

• power disconnects

• fire prevention and safety inspections

3.2 Fire Prevention Responsible Party. The Contractor must appoint a Fire Prevention Responsible Party (FPRP) who acts as the Contractor’s Responsible Person for fire prevention concerns during the entire availability.

3.3 Fire Prevention and Response Conference. The Contractor must participate in the Fire Prevention and Response Conference as required in Std Spec 5550, paragraph 3.12. The participants must address the contents of SFLC Std Spec 5550, paragraph 3.12.1, as applicable.

3.4 Fire Responsibility Familiarization Tour and Initial Inspection. The Contractor must participate in the Fire Responsibility Familiarization Tour and Initial Inspection as required in Std Spec 5550, paragraphs

3.12.2 through 3.12.4.

3.5 Material Condition and Fire Protection Boundary Obstruction Mitigation Requirements. The Contractor must conform to all material condition and fire protection boundary obstruction mitigation requirements detailed in SFLC Std Spec 5550, paragraph 3.2.

3.6 Inoperable Fittings Log Requirements. The Contractor must conform to all inoperable fittings log requirements detailed in SFLC Std Spec 5550, paragraph 3.3.

3.7 Fire Prevention Service Particulars. The Contractor must conform to the below listed fire prevention service requirements, in accordance with SFLC Std Spec 5550..

TABLE 1 – FIRE PREVENTION SERVICE SELECTION

*SUB-

PARAGRAPH

TITLE Y/N

3.4 Fire prevention system status

Y [Fire

Plan]

3.4.1 Temporary firefighting system proposal Y

3.4.2 Emergent firefighting system inoperability

approval and notification N

3.4.3 “Disabled equipment” signage for disabled initial responder equipment N

3.4.4 Firefighting system inoperability allowance for

removed hazards N

3.4.5 Maintain sprinkling zone operability N

3.4.6 including all subparagraphs

Hazard mitigation for maintenance of fixed extinguishing systems

N

3.4.7 Procedure implementation for enabling/disabling

fire suppression systems N

3.4.8 Portable water pumping requirement for vessels N

15 (Rev-0)

*SUB-

PARAGRAPH

TITLE Y/N

w/o installed capability

3.4.9 Limitations on operation of major machinery

while firefighting systems are offline N

3.4.10 Liquid fuel pumping requirement for operational

permanent or temporary firefighting systems N

3.4.11

Mechanical AFFF equipment must be available to initial responders in compartments with risk of flammable/combustible liquid spillage

N

3.4.12 including all subparagraphs

Portable fire extinguisher requirements N

3.4.13 Hose and reel protection N

3.4.14 including all subparagraphs

Drydock firefighting requirements Y

3.4.15 Fire protection system status in Fire Plan

Y [Fire

Plan]

3.5 Fire response related communication links in Fire

Plan

Y [Fire

Plan]

3.6 Fire response related temporary services in Fire

Plan

Y [Fire

Plan]

3.6.1 Minimize downtime of fixed extinguishing

systems N

3.6.2 through 3.6.10

Firemain and related equipment requirements N

3.6.11 Permanent lighting requirements Y

3.6.12 including all subparagraphs

Temporary lighting requirements Y

3.6.13 Electrical power, firefighting water, and lighting

source location and testing identified in Fire Plan

Y [Fire

Plan]

3.7 including all subparagraphs

Fire alarm requirements Y [Fire

Plan]

3.8 Shore power manual disconnect locations

identified in Fire Plan

Y [Fire

Plan]

3.9 Other power manual disconnect locations

identified in the Fire Plan Y [Fire Plan]

3.10 including subparagraph

Vessel firefighting equipment placement and disposition info in Fire Plan

Y [Fire Plan]

3.11 Fire prevention and safety inspections in Fire Plan

Y [Fire

Plan]

3.11.1 Initial and daily inspection requirements Y

3.11.2 Additional details in fire inspection reports Y

*Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 5550.

3.5 Extended fire prevention services. If the performance period of the contract is extended by the KO, the contractor must continue to provide all fire prevention services as specified herein for the extension period.

16 (Rev-0)

4. NOTES

This section is not applicable to this work item.

17 (Rev-0)

11000_ESD_0723_FLT

REC_11000_UWHIB_FLT_75’ WLIC (‘D’ Class: Hulls 75306, 75309, 75310) (0121)

WORK ITEM 2: Hull Plating, U/W Body, Inspect - Tender

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 75D WAGL 0700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement

Coast Guard Drawing 75D WAGL 1101-001, Rev C, Shell Expansion (75306-75307)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

18 (Rev-0)

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor must accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor must provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:

• A hull repair supervisor and a marker.

• Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor must inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor must inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor must inspect all sea chests, sea beam arrays, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor must check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor must inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.

3.2.5 Transducers. The Contractor must check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

3.2.6 Zinc anodes.

19 (Rev-0)

3.2.6.1 The Contractor must remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, sea beam array, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.

3.2.6.2 The Contractor must visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor must accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB).

Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

3.2.7.2 Dry film thickness (DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.

3.2.7.3 Coating system thickness and scheme inspection. Perform a microscopic observation of precision angular cuts in the coating system film (“Tooke Paint Inspection”), in accordance with ASTM D4138, and measure the total coating thickness and thickness of each individual coat of paint, in addition to identifying/verifying the existing color scheme for each coat of paint comprising the coating system.

NOTE

The Tooke Paint Inspection Gage/Gauge (Plastic) is a precision tool for inspection and thickness measurement (ASTM D4138) of single or multiple coats on any substrate, and for microscopic observation and measurement of substrate and film defects. The gage uses an illuminated 50-power microscope with measuring reticle, and mounts tungsten carbide cutting tips for precise incision of the work surface.

Direct measurement of total coating thickness and thickness of individual coats of paint is a unique capability of the Tooke Paint Inspection

Gage/Gauge. Thus, in addition to routine use, it often serves as a “referee” instrument to calibrate indirect or non-destructive thickness measuring instruments.

Other uses include assessment of substrate conditions and coating adhesion, and observation of microscopic cracking, tendency for brittleness, cratering, or other microscopic film symptoms.

3.2.7.3.1 Take a total of four readings in locations designated by the Coast Guard Inspector, and as follows: one each, port and starboard, in the boot-top area; and one each,…