This solicitation requests inert seat retraction thruster parts. The Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base is seeking these parts to support the B-1 aircraft munitions program. Offerors should provide pricing for the inert parts, which include metal housings and internal hardware, and meet all requirements for packaging, preservation, and marking by the specified response date.

View the file

Other files

File Type Posted
FA8213-22-R-3006 - Extension 04.14.2022.pdf PDF
FA8213-22-R-3006.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

Contractor Name CAGE code

DCMA QAR Reviewer

Date Review Completed

Date Issued to Contractor

PR No. FD2020-

Date Contract Awarded

Final Delivery Date (FDD)

Program Name

DODIC

Part Number

The contractor is required to impose the listed below DCMA Inspection Points into the appropriate Work Orders.

All Work Orders pertaining to CRITICAL FLIGHT ITEMS must be identified on folders.

Mandatory - M: Stamp and/ or Signature on original documentation (i.e., Mfg. Planning, ATP, FAT Report, etc.)

Witness - W: GSI required to attend, may reduce level of effort after 50% of production lots found acceptable

Verification - V: Stamp and/or Signature required unless noted otherwise (may be done by written verification)

Monitor - R: Will monitor testing, may reduce to verification

Notify - N: By phone or daily schedule 24( R ) - 48 ( NR ) hours in advance

Additional requirements: (DCMA reserves the right to impose additional inspection points as deemed necessary.)

Prepared by:

Date

Concurrence Signature by QAR/DCMA:

QAR/DCMA

THIS PLANNING SHEET WILL BE UPDATED IF NECESSARY.

QUALITY ASSURANCE LETTER OF INSTRUCTION

Planning Requirements

COMMENTS

NOTICE

Engineer

Date

Devin Swanson

Sheet1

Contract No: 21-50071

Date Contract Awarded:

Final Delivery Date FDD:

Program Name: B1B

DODIC: 816950-12

undefined: V undefined_2: V undefined_3: V undefined_4: M undefined_5: W undefined_6: V undefined_7: V undefined_8: V undefined_9: N undefined_10:

undefined_11:

undefined_12:

Text19: PacSci CA

Text20:

Text21:

Text22:

Text23:

Text24: 1.Inspection

Text25: 2. Leak Test

Text26: 3. X-Ray/N-Ray

Text27: 4. LAT Sample Selection

Text28: 5. LAT

Text29: 6. Preparation for Shipment

Text30: 7. AMMO Data Card Review

Text31: 8. Shippers (DD250, DD1149, Reports)

Text32: 9. Additional Requirements

Text33:

Text34:

Text35:

Text36: 1. Explosive Weight

2. Verify ATP contains both gross and fine leak checks, and gross leak and fine leak checks are performed.

3. Ensure film labeling correct. Ensure radiographic film readable/well-defined. DCMA not required to interpret film.

4. Randomly select LAT units per latest government approved ATP.

5. Prior to LAT ensure proper calibration and validation of all test equipment. Testing should occur in accordance with latest government approved ATP.

6. Ensure Paperwork is correct.

7. Verify all energetic materials: list original manufacturer, original lot no., and latest certification/recertification date < 24 months.

8. Ensure Paperwork is correct. Verify Packaging, Packing, Preservation & Marking (PPP&M)

9. Any additional requirements imposed by DCMA shall be approved by Project Engineer

Text46: 06/09/2020

Text49:

Part Number: MT51

Noun:

REPSHIP Data Requirements for Individual Shipments of Hazardous Material (HAZMAT) and Inert Component Parts - Continental United States (CONUS) to CONUS, CONUS to Overseas or From All

Overseas Locations FROM: Shipping Activity To: Domestic Customer or Transshipping Activity Clearance Authority (Ocean) or Customer Service

Branch (CSB) (Air) or CONUS Sea Terminal

INFO: GACP TRANSPORTATION, HILL AFB UT - (AFLCMC / EBHMB)

email: ooalc.gacp.transportation@us.af.mil or FAX (801) 777-1089.

INFO: Sponsoring Service Accountable Supply Activity Ultimate Consignee/ Final Destination

SUBJ: Report of Shipment (REPSHIP)

1. Shipment Date written as a three-digit day of the year (Julian)

2. Estimated Time of Arrival (ETA) written as a three-digit day of the year (Julian) (Observe Standard Transit Time (STT), if CONUS Truck Shipment and no Required Delivery Date (RDD) identified)

3. Required Delivery Date (RDD) or Delivery Date (DD), if specified

4. Carrier

5. Bill of Lading (BL) Number (Notes 1, 2, 3, 4)

6. Military Traffic Expediting-Greater Security (MTX-GS) Service Number (Notes 1, 2, 3)

7. Air Release Number (Notes 1, 2, 3) or for Surface Shipments, Export Traffic Release (ETR) Number and Vessel Name and/or Voyage Document Number

8. Shipment (Cargo) Name (Example: Bombs)

9. Container and Seal Number (if applicable):

a. Container Transportation Control Number (TCN)

b. Total Weight of Contents

c. Rounds, Pieces, Weight, Cube, Condition code, and Lot Numbers (Note 4)

10. Security Risk Category (SRC), (E.G., Security Risk Category I, II, III, IV, Unclassified, Confidential, Secret, None)

11. Controlled Item Inventory Code (CIIC)

12. Total Net Explosive Weight (NEW)

13. Hazard Classification (s)

14. Department of Defense Identification Code / Navy Ammunition Logistic Code (DODIC/NALC). (Note 4).

15. Name, address, and phone number of person responsible for information contained in REPSHIP

NOTES:

1. When the conveyance contains more than one shipment unit, repeat the data elements in separately lettered paragraphs for each shipment unit.

2. Cargo for more than one vessel or flight, but shipped to Port of Embarkation (POE) in a single conveyance, is included in a single REPSHIP. When cargo for a single vessel is moved to the Seaport of Embarkation (SPOE) in more than one conveyance, repeat all the data elements as above in separate numbered paragraphs for each conveyance or REPSHIP.

3. A separate REPSHIP is used for each mode of shipment to the POE.

4. Lot number, DODIC and NALC are not mandatory fields. If available, they may be provided in the electronic

RESHIP or in the template above. If a CBL is used, the lot number and ammunition condition code should be included in the remarks section. Weapons must be identified on the CBL by each serial number contained within the shipment.

5. DODIC and NALC are codes used specifically for logistic administration and control of ammunition.

Attachment 1

Statement of Work June 2020

PRESERVATION, PACKAGING & MARKING REQUIREMENTS

The contractor shall develop, implement and maintain the preservation, packaging and packing of all items to be delivered under the terms of this contract. Packaging procedures will be established in accordance with AFMCI 24- 201, specifically Paragraph 3.7 and MIL-STD-2073-1, Standard Practice for Military Packaging, Packaging requirements are identified in the AFMC Form 158, Packaging Requirements submitted by the responsible packaging specialist. All “markings and labeling” of shipments shall conform to MIL-STD-129, DoD Standard Practice, Military Marking for Shipment and Storage. The contractor shall affix a completed DD Form 1574, Serviceable Tag-Materiel or DD Form 1574-1, Serviceable Label- Materiel to each unit pack or intermediate container and prime outer container(s). The tag or label will indicate the condition(s) of the materiel and to identify the individual article or contents, bundle, container to which they are securely attached.

INTERNATIONAL STANDARDS FOR PHYTOSANITARY MEASURES

(ISPM 15) REQUIREMENTS

The contractor shall use the wood packaging material regulation for international trade which describes Phytosanitary (including treatments) that have been approved for wood packaging material and provides for the approval of new or revised treatments. Use the latest revision of (ISPM 15), and the following statement complies with the United Nations-implemented restrictions on wood packaging material (WPM).

“This requirement is specifically concerned with invasive species such as pinewood nematode. WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. The statement below cites the requirements in detail and covers lumber for building containers and pallets used for deliveries resulting in worldwide shipments (direct vendor deliveries, Air Logistics complex (ALC), Container Consolidation Points (CCP), Aerial Ports, Water Ports, or other DoD installations).

ELECTROSTATIC MATERIAL (When Applicable) The Contractor shall apply provisions of MIL-STD-2073-1, when identifying all solid state devices and modules containing diodes, translators, integrated circuits and/or other microelectronic components sensitive to electrostatic forces. All such items shall be packaged IAW MIL- STD-2073-1 using electrostatic free barrier materials and shall clearly bear “Electrostatic Sensitive Device” labels IAW MIL-STD-129, Department of Defense Standard Practice Military Marking for Shipment and Storage.

PALLETIZED UNIT LOADS

The Contractor shall apply provisions and methods of MIL-STD-147, Palletized Unit Loads to contracts requiring the preparation and shipment of bonded palletized unit loads for DoD facilities when applicable.

SPECIALIZED SHIPPING CONTAINERS

The contractor shall apply provisions of MIL-STD-648, Department of Defense Design Criteria Standard, Specialized Shipping Containers. This standard establishes general design guidelines and associated tests for specialized shipping containers used by the Department of Defense. Definitive requirements for specific containers will be defined by the individual specification, acquisition, or task order. This standard is intended to be used as the basic reference document in all specifications and standards prescribing performance requirements to be applied to a specialized shipping container. Compliance with this intent is expected through normal application of the specification or standard preparation and revision processes.

Statement of Work (Cont)

HAZARDOUS MATERIALS (When Applicable) The contractor shall ensure Hazardous shipments comply with International Civil Aviation Organization (ICAO), U.S. Code of Federal Regulations (CFR) Title 49, International Air Transport Association (IATA) Dangerous Goods Regulation, International Maritime Dangerous Goods Code (IMDG, Annex 1), and AFMAN 24-204, Preparing Hazardous Materials for Military Air Shipments. Packaging shall meet “DOT specification or a United Nation (UN) specification ” manufactured in accordance with 49 CFR, Part 178 and the final packages assembled IAW 49 CFR, Parts 100-185 as applicable. A Competent Authority Approval (CAA) shall be acquired from the responsible Associate Administrator or other designated Department official to perform a function requiring prior consent under the Hazardous Material Regulation (HMR). Package(s) shall be marked IAW MIL-STD-129, DoD Standard Practice, Military Marking for Shipment and Storage.

The contractor shall affix a completed DD Form 1574, Serviceable Tag-Materiel or DD Form 1574-1, Serviceable Label- Materiel to each unit pack or intermediate container and prime outer container(s). The tag or label will indicate the condition(s) of the materiel and to identify the individual article or contents, bundle, container to which they are securely attached. If a symbol is used to represent the manufacturer or the approval agency certifying compliance with 49 CFR 178, subparts L and M, the symbol must be registered with the U.S. Department of Transportation. A copy of the Contractor’s Test Report and signed certification that the package configuration meets both CFR and UN requirements shall be made available to the procuring contract office, as required, prior to acceptance or shipment of any portion of the product IAW Contract Data Requirements List (CDRL DI-PACK-81059A) (Reference AFMC Form 158). Safety Data Sheets (SDS) are required for known hazardous items and applicable items shown in FED-STD-313, Tables I and II. The SDS shall have any applicable identification number, such as National Stock Number or Special Item Number. A copy of the SDS shall be mailed or e-mailed no later than five (5) days prior to contractual delivery of items:

FAR clause 52.223-3, Hazardous Material Identification and Material Safety Data

SPECIAL PACKAGING INSTRUCTIONS RETRIEVAL & EXCHANGE SYSTEM

(SPIRES)

Contractors may request the use of SPIRES website to view item packaging requirements or search for Special Packaging Instruction drawings via the following website: https://spires.wpafb.af.mil/

REUSABLE CONTAINERS

The contractor shall safeguard all received reusable shipping containers that meet the requirements of the AFMC Form 158 and are suitable for return shipment of serviceable assets. The contractor shall dispose of and replace unserviceable containers with new containers that meet requirements of the AFMC Form 158.

Contact the Product Support Manager and Administering Contracting Office (ACO) for disposition instructions and replacement when Long Life Reusable Container(s) are received in an unserviceable condition.

https://spires.wpafb.af.mil/

REPORTING DISCREPANCIES

The contractor shall use Web Supply Discrepancy Report (WebSDR) to submit/reply to a Supply Discrepancy Report (SDR), when improperly packed assets are received/shipped in other than the contracted packaging requirements (coded data or Special Packaging Instructions (SPI) drawings) from Department of Defense (DoD) components or contractor activities. The contractor shall request a WebSDR account via the following website: https://www.transactionservices.dla.mil/daashome/homepage.asp

(See Defense Logistics Management (DLM) 4000.25-M, Volume 2, Supply Standard and Procedures, Chapter 17, Supply Discrepancy Reporting) http://www.dla.mil/HQ/InformationOperations/DLMS/

Exceptions when no damage has occurred are as follows:

- Items packaged before the current SPI date.

- An alternate pack may be used, provided the prime Air Force Sustainment Complex, Packaging Office at the Air Logistics Complex (ALC) approves and issues a waiver, deviation number, which would be annotated on the exterior container on the lower right hand portion of the identification side of the container.

- In accordance with Technical Order (TO) 00-85B-3, How to Package Air Force Spares, the contractor may substitute the next larger size fast pack, of the type I or type II to ship transportation priorities 1 and 2 shipments as long as there is no decrease in any of the container dimensions without the requirement of a waiver deviation. TO 00- 85B-3, para 4.2 can be accessed via the website:

- https://www.tinker.af.mil/Portals/106/Documents/Technical%20Orders/AFD-082416-00-85B-3.pdf

ASSIST Documents for Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions The contractor shall use the ASSIST website to access specification, standards, data item descriptions documents listed in this contract solicitation:

FAR 52-211-2 Availability of Specifications, Standards, and Data Item Descriptions listed in the Acquisition Streamlining and Standardization Information System https://quicksearch.dla.mil/

AFSC

406 SCMS/GULAA

Attn:

DSN:

COMM:

E-mail:

Jenifer Burleigh 7778835

8017778835 jenifer.burleigh@us.af.mil https://www.transactionservices.dla.mil/daashome/homepage.asp http://www.dla.mil/HQ/InformationOperations/DLMS/ https://www.tinker.af.mil/Portals/106/Documents/Technical%20Orders/AFD-082416-00-85B-3.pdf https://quicksearch.dla.mil/%23/

APPLICABLE GOVERNMENT PACKAGING DOCUMENTS

NOTE: UTILIZE THE MOST RECENT REVISION

AFI 24-602V2_AFGM2018-01, Preparation and Movement of Air Force Cargo

AFMAN 24-204, Preparing Hazardous Materials for Military Air Shipments

DLMS 4000.25, Defense Logistics Management Systems, Volume 2, Change 10, Supply Standards and Procedures, Chapter 17, Supply Discrepancy Reporting

DOT Title 29, Occupational Safety and Health Administration, Labor

DOT Title 49, Code of Federal Regulations (49 CFR), Transportation

International Civil Aviation Organization (ICAO) Technical Instructions

International Air Transport Association (IATA) Dangerous Goods Regulation

International Maritime Dangerous Goods (IMDG) Code

ISPM 15, International Standard Phytosanitary Measure Note: Marking Requirements may be found in the American Lumber Standards Committee, Incorporated Wood Packaging Material Enforcement Regulations dated November 07, 2014 and ISPM 15.

MIL-STD-2073-1E, Change 3, Standard Practice, for Military Packaging

MIL-STD-129R, Change 1, Department of Defense Standard Practice Military Marking for Shipment and Storage

MIL-STD-648E, Department of Defense Design Criteria Standard, Specialized Shipping Containers

MIL-STD-147E, Change 1, Palletized Unit Loads

MIL-STD-1686C, Electrostatic Discharge Control Program for Protection of Electrical and Electronic Parts, Assemblies and Equipment (Excluding Electrically Initiated Explosive Devices) TO 00-85B-3, How to Package Air Force Spares

FED-STD-313E, Federal Standard: Material Safety Data, Transportation Data and Disposal Data for Hazardous Materials Furnished to Government Activities

MIL-STD-1686C, Electrostatic Discharge Control Program for Protection of Electrical and Electronic Parts, Assemblies and Equipment (Excluding Electrically Initiated Explosive Devices).

PRESERVATION, PACKAGING & MARKING REQUIREMENTS

INTERNATIONAL STANDARDS FOR PHYTOSANITARY MEASURES

(ISPM 15) REQUIREMENTS

ELECTROSTATIC MATERIAL (When Applicable)

PALLETIZED UNIT LOADS

SPECIALIZED SHIPPING CONTAINERS

Statement of Work (Cont)

HAZARDOUS MATERIALS (When Applicable)

SPECIAL PACKAGING INSTRUCTIONS RETRIEVAL & EXCHANGE SYSTEM (SPIRES)

REUSABLE CONTAINERS

Statement of Work (Cont)

REPORTING DISCREPANCIES

Exceptions when no damage has occurred are as follows:

ASSIST Documents for Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions

Statement of Work (Cont)

ATTACHMENT 2

USAF & USN CAD/PAD STATEMENT OF WORK - AMMUNITION DATA CARDS

January, 2018

1. Ammunition Data Cards (ADC) shall be prepared in accordance with MIL-STD-1168 (current revision) and shall follow the format required by the application identified as Worldwide Ammunition-data Repository Program (WARP). All of the requirements of MIL-STD-1168 apply but some are tailored in accordance with MIL-STD-962 to meet CAD/PAD program requirements as listed below.

2. The criteria and procedures for the assignment of lot numbers for energetic materials

(pyrotechnics, propellants, explosives) including their constituents shall be in accordance with

MIL-STD-1168.

3. All energetic materials (pyrotechnics, propellants, explosives) used in assemblies and sub-assemblies/components (i.e., igniter cartridges, delay elements, primer assemblies, explosive cord, etc.) shall be entered in the ADC using the common name, actual/original manufacturer’s part number & revision, lot number, and date of manufacture. Traceability shall be ensured by the original manufacturer’s documentation such as Certificate of Conformance (COC), Certificate of Analysis (COA), Quality Assurance Record (QAR) Quality Inspection Record (QIR), Quality Assurance Documents (QAD), Batch Record, or other equivalent documentation that would provide positive traceability in the event of a future product recall.

4. The contractor may list their own internal part number for energetic material that they re-designate or re-characterize but must also list the actual manufacturer’s part number, lot number, and date of manufacture in parentheses in a format that is searchable in WARP. Any GFM/GFP provided under contract to the vendor should retain government provided part/lot numbers and nomenclature to retain traceability. Ingredients which are used to synthesize or that are blended in a process to make the end item energetic material are not required to be listed. Examples of blended or synthesized energetic materials that shall be listed are HNS, Lead Azide, BKNO3, ZPP, HES 8028, etc. If the ages of energetic materials are older than the ages specified on the Airmunitions Specification or as specified elsewhere in the contract at the time the CAD/PAD devices become hermetically sealed, the date of energetic material recertification or any associated approved Request for Variance (RFV) shall be notated in the waivers and deviation description section.

5. Hardware components shall be fully traceable and identified by the original manufacturer’s lot identification information/documentation or qualified distributor’s documentation such as Certificate of Conformance (COC), Certificate of Analysis (COA), Quality Assurance Record (QAR), Batch Record, or other equivalent documentation that would provide positive traceability in the event of a future product recall. The actual date of manufacture is not required for any non-age degradable materials such as metal housings, tubes, sleeves, firing pins, nuts, bolts, washers, etc. The COC, COA, QAR, or Batch Record date(s) may be used for the DOM. Epoxies, sealants, curative, O-rings, and other organic materials shall be fully traceable to OEM with DOM and traceable via the original manufacturer’s lot identification documentation such as Certificate of Conformance (COC), Certificate of Analysis (COA), Quality Assurance Record (QAR) Batch Record, or other equivalent documentation that would provide positive traceability in the event of a future product recall. Materials or components that do not affect the reliability or safety of the end item (i.e., solvents, paints, lacquers, labels, dust caps, etc.) do not need to be listed on the ADC.

6. The ADC data and information entered in WARP for all materials and components ideally shall stand alone for traceability to the actual manufacture’s information (i.e. Mfg P/N, Mfg date (as applicable), Mfg lot number etc.). If contractor uses their own P/N, reference date for acceptance or other “trace”/traceability identification used internally for the non-critical piece parts/materials, it shall be noted in the remarks section, i.e. “trace ID, or PO used for the

ATTACHMENT 2 (continued) following piece parts: (parts shall identified/listed)”, provided the field/entry method is searchable in WARP. If traceability documentation is “questionable” or in conflict and needs clarification, the applicable engineer or equipment specialist shall be contacted to resolve any issues.

7. A “sample” ADC is generated in WARP the first time an ADC is submitted by the contractor for applicable government reviews and approvals. Upon approval of the sample ADC, a final version for each production lot shall be completed in WARP and uploaded for Invoicing, Receipt, Acceptance, and Property Transfer (iRAPT - formerly WAWF) for review and acceptance prior to shipment of product by the applicable government authority. The WARP ADC program will not allow the submission of additional ADCs until such time as the sample ADC has been approved in the system. The sample ADC does not require the use of a “Z” interfix number used to identify it as a sample.

8. If any unique situations exist that may conflict with compliance, a resolution should be proposed by the contractor prior to contract award to determine possible work-around.

9. A hard copy of the applicable ADC(s) shall also be included with each shipment per applicable

ADC CDRL.

WARP will reside within the Munitions History Program (MHP). Additional details on these WARP applications are provided below.

MHP-WARP Access Procedures

Government or Contractor employee with CAC and AKO account:

(a) Click on the MHP hyperlink which is https://mhp.redstone.army.mil/

(b) Enter CAC PIN when prompted

(c) Click on WARP (ADC)

(d) Click on Help

(e) Click on WARP Request Access and follow instructions

Contractor or Government employee without CAC and AKO account: MHP-WARP uses PKI authentication requiring a DoD approved digital certificate as a security measure to protect the integrity of stored data. There are three vendors that have been approved to issue DoD approved certificates per an External Certification Authority (ECA) program. You are required to use one of the approved vendors listed on the following DISA website:

http://iase.disa.mil/pki/eca/index.html A nominal fee is charged for each certificate. The Contractor, including any subcontractors, shall assume the responsibility for all costs of obtaining each digital certificate needed.

After the required certificate is obtained:

(a) Click on the MHP-WARP hyperlink: https://mhpwarp.redstone.army.mil/

(b) Enter ECA password

(c) Click on Help and follow the instructions for obtaining the necessary access

HELP Numbers are as follows:

MHP Access – (256)313-2143; DSN 897-2143 JMC Quality Administrators for WARP issues – (309)782-2697 or (309)782-7107

ATTACHMENT 2 (continued)

Worldwide Ammunition-data Repository Program (WARP)

An online user’s manual will provide additional help and criteria in the development of an ammunition data card. It is recommended that you download and read the user’s manual prior to creating and filling out your initial ammo data card. The user's manual also contains screen shots, which depict what the data entry person will see during the ADC input process.

Ammunition Data Card Input

ADC input allows current contractors and government facilities the capability to create, and submit for approval, both sample ADCs and production lot ADCs which meet the format requirements of MIL-STD-1168 and as specified in this SOW for ADCs. ADCs are automatically forwarded to the respective Government Agency Responsible for Acceptance (GARA). The GARA in most cases is the Defense Contract Management Agency (DCMA) Quality Assurance Representative (QAR), who reviews contractor input for accuracy and completeness, and after updating the disposition code for the specific lot, submits the ADC to the database. The contractor’s data entry person is granted access only to ADCs identified with its specific manufacturing code, as identified in MIL-HDBK-1461, Manufacturer's Symbols. The use of previously inputted ADCs through the TEMPLATE option significantly reduces input effort, while increasing accuracy and consistency of data.

Email Notification WARP provides immediate, automated notification to process participants when actions are required. When the producer has completed an ADC submission, an email message is routed to the GARA advising that an ADC awaits review and approval. If the GARA approves the ADC as submitted, the ADC is released to the WARP database and an email, with approved data card, is routed back to the originator. If the ADC requires modification or correction to conform with MIL- STD-1168 and/or the approved format and technical content as approved by the government, an email is provided to the ADC originator advising that corrective action is required prior to approval.

Information Updates It is important that the System Administrators are apprised when a producer receives a new contract. The producer shall notify usarmy.RIA.jmc.mbx.warp@mail.mil within 30 days after receipt of a new contract. Information to be included shall be the contract number, item, GARA, Manufacturer's identification symbol and the names of the individuals who will be inputting ADCs into the system. If you are a new producer and do not have a Manufacturer's identification symbol, you can obtain one by sending an email to usarmy.RIA.jmc.mbx.warp@mail.mil. The email must contain manufacturer's name, address where performance of the contract will take place, and a point of contact.

(End of statement of work)

AIRMUNITION SPECIFICATION

8 Dec 2020

FD2020-21-50071

NSN: 1377012853109ES

1. The contractor shall provide an advanced Report of Shipment (REPSHIP) to the consignee no later than 24 hours prior to the shipment arrival, and for ammunition shipments no later than two hours after shipment departure. A REPSHIP shall include all the following data in accordance with Attachment 1.

2. Department of Defense Identification Code (DODIC): MT51

3. Ammunition Data Cards (ADC) shall be filled out; input in accordance with Attachment 2, Statement of Work – Ammunition Data Cards; and state quantity/serial number of lot acceptance test Units in the remarks block. One hard copy of the ADC shall accompany shipments to each shipping location.

CDRL (DI-MISC-80043B).

4. Items shall be marked in accordance with CAD/PAD Item Marking Instruction Version 1.5, 1 May 2019, attached.

5. Shelf Life Code marking NOT required per MIL-STD-129R.

6. Items are Inert.

7. All Engineering Change Proposals (ECP’s), Notice of Revisions (NORs), and Requests for Variances (RFVs formerly RFD/RFW) affecting the approved product baseline configuration, acceptance test procedures, or manufacturing process of any time(s) on this contract shall be in accordance with EIA- 649-B. Major ECPs with NORs and Critical/Major RFV’s shall be submitted to the responsible Government Engineering Authority for review/disposition by CCB. Minor/Administrative ECP’s with NORs and Minor RFVs shall be processed by the Cognizant Government Engineer.

ECPs-CDRL (DI-SESS-80639E) NORs-CDRL (DI-SESS-80642E) RFVs-CDRL (DI-SES-80640E) Distribution Statement: B, Reason: Administrative or Operational (REF. DoD 5230.24)

8. Item(s) must pass both gross and fine checks. MIL-STD-883K, Method 1014.15 may be used as guidance. The existing leak rate limit established for this item(s) will remain the same.

Contractor shall generate a Lot Acceptance Test Plan (LATP/ATP) with an analysis or test results showing compliance for Hill AFB engineering approval at least 90 days prior to commencement of Lot Acceptance Testing allowing for 30 days approval time after submission.

CDRL (DI-QCIC-80553A).

9. Lot Acceptance Test requirements are: In accordance with latest government approved ATP.

Contractor

10. The contractor shall furnish a Lot Acceptance Test/Inspection Report in WAWF, CDRL (DI-NDTI- 80809B).

11. LOT ACCEPTANCE TEST: In the event of an end item failure, the contractor shall notify the PCO/ACO and Air Force Engineering Organization within 1 business day Air Force Engineering Organization AFLCMC/EBHJ, devin.swanson@us.af.mil.

12. In the event of test failure(s), a Failure analysis and Corrective Action Report with proposed corrective actions/recommendations is required. CDRL (DI-SESS-80255B).

13. If Hexanitrostilbene (HNS) explosive material is used in the manufacture of this item, the HNS shall meet the requirements of Government Document WS5003F (or latest revision), Purchase Description of HNS Explosive; and maximum particle size shall not exceed 250 microns.

14. The age of energetic materials and components (i.e. ALL explosive, propellants, pyrotechnics, cartridges, and/or initiators) used in the manufacture of these items or sub-components shall not exceed 24 months based on the original manufacturing date. All energetic materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and 121 (http:/www.pmddtc.state.gov/regulation_laws/itar_official.html).

15. Raw (non-blended) ingredients and materials are used in blended/mixed energetic materials such as, but not limited to: fuels, oxidizers, binders, curatives, sensitizers, plasticizers, stabilizers etc., shall not exceed 24 months since date of manufacture and comply with original manufacture’s MIL-STD. The Government may waive the energetic and constituent material requirements listed above or portions thereof, on a case-by-case basis (when acceptable to the government) provided the contractor furnishes all details of the reason for the variance and the age, lot numbers, traceability, and other pertinent information/test data and Certificate of analysis/Conformance (COA/COC) of the subject materials or components. The variance shall be submitted as a RFV and may be subject to, but not limited to, conditions such as sensitivity testing, stabilizer and analysis and/or dehumidification at vendor’s cost;

therefore, vendor must plan accordingly. RFV not required provided vendor has approved energetic material and constituent management and recertification plan approved by HAFB technical authority for this specific contract and contract is executed with materials in compliance with said plan.

Recertification test data for materials shall be provided by vendor upon request at no additional charge to the government. All ray ingredients, materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and 121

16. Percussion primers shall have been certified/recertified by performing sensitivity (all-fire/no fire) and dud testing per applicable specification within the past 24 months unless they are Navy certified and have a 2 year certification. Primers shall be stored in a temperature and humidity controlled environment and in a sealed container with desiccant from time of primer manufacturing, shipping, storage and through final installation in end item. All primers shall be X-rayed in top and side views for critical defects prior to use.

17. This item is designated as a Critical Safety Item (CSI). Documentation for critical characteristics may be found in the contract, TDP, assembly/inspection procedures or QALI. MRB approval authority shall be retained by government engineer. Other characteristics requiring inspection or special oversight from DCMA:

18. Approval from government engineer is required prior to rework and repair of nonconforming material (see Attached ES7034)

DEPARTMENT OF THE AIR FORCE

448 SUPPY CHAIN MANAGEMENT WING (AFMC)

HILL AIR FORCE BASE, UTAH

17 AUGUST 2020

MEMORANDUM FOR CONTRACTING AND AFLCMC/LZPEF

FROM: 429 SCMS/GUMAC

6038 Aspen Ave. Bldg 1289SW

Hill Air Force Base, Utah 84056-5825

SUBJECT: Data Package (Bid Sets)

NSN PR IMAGE COUNT BETA.SAM

1377-01-285-3109ES 21-50071 52

ABSS

1. In an effort to reduce costs and improve proficiency, the Engineering Data Services Center will no longer attach a copy of the Data Package to the Purchase Request (PR) Official File. The Solicitation Office will distribute copies of the Bid Set and a master set of the PR Data Package will be kept with the latest revision and PR number referenced.

2. When questions arise from the contractor concerning the data package, the buyer will perform one of the following:

a. Initiate a Procurement Technical Assistance Request for Spares (PTARS) for data changes. Forward to cognizant engineering group referencing current engineer as found on current Screening Analysis Worksheet (SAW) in Purchase Requirement Process System (PRPS).

The PR number, National Stock Number (NSN), phone number and mailing address must be included.

b. Web based solicitation data packages can be obtained at https://beta.sam.gov/. To register contact the help desk at, 1-866-606-8220 toll free or DSN : 94-606-8220

3. If copies of the CD are required, contact AFLCMC/LZPEF, Vickie Inlow, at AFLCMC.LZPEF.CDRoom@us.af.mil, DSN 777-6228, Com (801) 777-6228.

a. They will respond to the request within 2 working days whenever possible. If you have any questions or need further information please contact AFLCMC/LZPEF.

Vincent M. Villagomez Chief, Material Integrity Section

DSN 586-0460, Com (801) 586-0460

CAD/PAD Item Marking Instruction, V 1.5

CAD/PAD Item Marking Instruction

Prepared By CAD/PAD Joint Program Office

NSWC IHEODTD and AFLCMC/EBHJ

Version 1.5 Dated 01 May 2019

1.

Purpose

Table of Contents

2. Scope Page 5

3. Marking Requirements Page 6

4. Placement of UID Markings Page 8

5. Items delivered in kit format Page 9

6. Waivers Page 9

References

NOTE: Use latest revision of all reference documents.

1. MIL-STD-130 Department of Defense Standard Practice Identification Marking of U.S.

Military Property

2. MIL- STD-1168 (current revision) Ammunition Lot Numbering and Ammunition Data Card

(Note section 3.1 for new lot assignment for “remanufactured CAD/PAD Components”)

3. ISO/IEC 16022 Information technology - Automatic identification and data capture techniques - Data Matrix bar code symbology specification

4. ISO/IEC 15434 Information technology - Automatic identification and data capture techniques - Syntax for high capacity ADC media

5. ISO/IEC 15418 Information technology - Automatic identification and data capture techniques - GS1 Application Identifiers and ASC MH10 Data Identifiers and maintenance

6. UNDER SECRETARY OF DEFENSE FOR ACQUISITION POLICY AND

TECHNOLOGY Department of Defense Guide to Uniquely Identifying Items version 1.6 (this document is available on line at http://www.acq.osd.mil/dpap/pdi/uid/index.html or from Defense Procurement & Acquisition Policy, 3060 Defense Pentagon, Room 3E1044, Washington, DC 20301-3060)

7. DEFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENT 252.211-7003

Item Identification and Valuation (Copies of this document are available on line at http://farsite.hill.af.mil/ or from the Superintendent of Documents, P.O. Box 371954, Pittsburgh, PA 15250-7954)

8. AFSCM 21-556 Vol. 2 Julian Date format

9. ANS MH10.8.2 - 2006 Data Application Identifier Standard

10. –ISO 28219 Labeling and Direct Product Marking with Linear Bar Code and Two- Dimensional Symbols http://www.acq.osd.mil/dpap/pdi/uid/index.html http://farsite.hill.af.mil/ http://farsite.hill.af.mil/

Figures

1. Determining IUID requirement

2. Sample UID Data Stream

3. Sample CAD/PAD Data Plate/Label

4. Sample of Etched Data

5. Sample CAD/PAD Small Item Data Plate/Label

1. Purpose.

The Under Secretary of Defense has implemented policy requiring DoD components meeting the requirements identified in Figure 1 to be marked with Item Unique Identifiers (IUID). Cartridge Actuated Devices and Propellant Actuated Devices (CAD/PAD) items, regardless of dollar value, are typically serially managed in aircraft maintenance data systems and therefore are applicable to the IUID requirement.

Additionally, the Air Force Aircrew Escape System Executive Working Group (AESEWG) and the egress system maintenance community has requested that CAD/PAD items be marked with Data Matrix ECC 200 on item data plates or items to enhance accuracy of aircraft maintenance data.

In accordance with MIL-STD-130, this marking instruction identifies marking requirements that meet the above objectives by tailoring Unique Identification (UID) requirements to include aircraft maintenance data requirements for both free text Human Readable Information (HRI) and Machine Readable Information (MRI), which are both mandated requirements for CAD/PAD items.

Figure 1. Determining UID Requirement

2. SCOPE.

This instruction identifies marking requirements applicable to suppliers/manufacturers of CAD/PAD components. It is applicable to both production of new CAD/PAD components and remanufacture of service returned, over-aged components. It identifies marking methods applicable to the various sizes and shapes of CAD/PAD components.

As of this writing, guidance regarding mandated transfer of data to the IUID registry can be found at “http://www.acq.osd.mil/dpap/pdi/uid/index.html”. Go to Training and Communication link, select IUID Toolkit (www.IUIDtoolkit.com), and select “Defense Suppliers”, then under “Submit”, select subsection “Registration of IUID Data11”, under Support Tools select “Data Submission”.

http://www.iuidtoolkit.com/

3. Marking Requirements.

Both Human Readable Information (HRI) and Machine Readable Information (MRI) are required (see section 4). In accordance with the Defense Federal Acquisition Regulation Supplement (DFARS), DoD has mandated the use of Data Matrix ECC 200 as the standard format for UID MRI markings. Guidance for the construct and application of Data Matrix markings is contained in MIL-STD-130 and the DoD UID Guide located at http://www.acq.osd.mil/dpap/pdi/uid/index.html, select Guides link.

3. 1. HRI Marking Requirements. The following HRI data is required (as a minimum):

- Item Nomenclature; Per applicable manufacturer drawing

- Manufacturer’s Commercial and Government Entity (CAGE); Five (5) alpha/numeric characters.

- Item Lot Number; Lot numbers shall be assigned IAW MIL-STD-1168 (current revision), unless otherwise directed. A new lot number and serial number shall also be assigned for “remanufactured” CAD/PAD components as opposed to adding a suffix to the original lot number for a “rework, overhaul or renovation” effort.

NOTE: The requirement for unique lot number has been deleted.

DOM is NOT required if the lot number contains the DOM as identified in MIL-STD-1168

- Item Serial Number; Serial number shall be up to eight (8) numeric characters.

The serial numbers shall be sequentially assigned and shall not be repeated until serial number 99,999,999 has been reached.

- Item manufacturer’s Part Number

NOTE: The weapon system Specification Number does not meet this requirement

- Optional markings: Additional markings (such as manufacturer’s name, logo, contract number) are acceptable, provided that space is available on the item/data label. Date of Manufacture (DOM); DOM shall be MM/YYYY and be the same date that is coded into the lot number.

NOTE: Markings and/or attachments shall make no reference to item installation requirements/procedures or shelf/service lives

S S S S S o

3.2. MRI Data Construct.

Data Matrix ECC200 markings shall be developed based on UID Data Construct #2 using Data Identifiers (DIs) in accordance with MIL-STD-130 and the DoD UID Guide (see Figure 2). To facilitate durability throughout the scanning life cycle, the largest symbol size, including quiet zone, shall be fitted within the available marking real estate. The symbol’s internal module (cell) sizes shall be no smaller than 0.0075 inch (0.19 mm) and no larger than 0.025 inch (0.64 mm). Marks shall contain only the data elements identified below:

NOTE: The actual UII will be comprised of CAGE, Part Number, and Serial Number data. The parenthesis surrounding the Data Identifiers are NOT encoded in the 2D symbol

(17V) Manufacturer’s Commercial and Government Entity (CAGE) code, 5 alpha/numeric characters

- (1P) Manufacturer’s Item Part Number, 18 alpha/numeric characters maximum

NOTE: The weapon system specification numbers do not meet this

- (S) Item Serial Number, IAW HRI requirement, up to eight (8) numeric characters

- (30T) Item production Lot Number, IAW HRI requirement, 15 alpha/numeric characters maximum

NOTE: The data identifier for Lot Number has been changed from 1T to 30T

- (4D) Date of Manufacture (DOM), in Julian Date format, five (5) numeric characters:

Example: 08151 = 31 May 2008

The first two positions are the last two digits of the year, the last three positions are the Julian Date (001 through 366)

[)> R 06 G 17V 12345 G 1P 123456789-ABCDEFGH G S 12345678 G 30T ABC06D123-001 G 4D 08151 R E

Figure 2. Sample UID Data Stream

S S T

4. Placement of UID Marking. CAD/PAD items vary considerably in size and shape. A large percentage of these items are currently marked with HRI printed on data plates or labels permanently affixed to the item. The preferred method for incorporating the UID required MRI is to include it on the current data plate/label and, wherever possible, the supplier is to incorporate this concept. The following identifies known variations in marking and preferred MRI incorporation methods.

Note: Unless specifically identified as a requirement in the procurement contract, subcomponents of the End Item Assembly shall not be UID marked.

4.1. CAD/PAD Items Currently Marked with Data Plates, Labels, or Flag-Tags. The data plates/labels for these items shall be modified/arranged to allow space for the MRI per paragraph 3.2. Marking shall comply with MIL-STD-130 and the DoD UID Guide (see figure 3).

Figure 3. Sample Data Plate/Label

4.2. CAD/PAD Items Currently Marked With Ink or Laser Etching Directly on the Item.

Item marking shall be modified/arranged to allow space for the incorporation of ink or laser etched MRI per paragraph 3.2. Marking shall comply with MIL-STD-130 and the DoD UID Guide (see figure 4).

CAD/PAD Builder Inc.

Acft Explosive Component Noun

CAGE: 12345

P/N: 123456789-1234

Ser No: 0001 Lot No: ABC08D001-001

DOM: 04/2008

Figure 4. Sample of Etched Data

CAD/PAD Builder Inc.

Acft Explosive Component Noun

CAGE: 12345

P/N: 123456789-1234 Ser No: 0001

4.3. CAD/PAD Items Considered to be Too Small for HRI and MRI. These items shall be physically marked using currently approved methods for HRI. A self-adhesive label shall be supplied in the item inner packaging that includes the minimum HRI (per paragraph 3.1) and the MRI Data Matrix marking (per paragraph 3.2). The label shall be as small as possible (meeting MIL-STD-130 requirements for HRI) and will include only the minimum required data (see figure 5).

Figure 5. Sample Small Item Data Plate/Label

Note: This will allow the maintainer to scan the MRI from the label and the ability to affix it to the next higher assembly.

5. Kit Marking Requirements. Individual components procured and delivered in a “kit” or “ship-set” format shall each be marked with HRI and MRI as identified in sections 3 and 4.

The kit containers shall also be marked with HRI and MRI per sections 3 and 4.

Note: Individual components supplied in kits or ship-sets require unique item identifiers. Their markings shall not reflect those identifying the kit or ship-set.

5.1 Only the “kit “or “ship-set” will require data submission into the UID Registry. Data submission for individual components in a kit is not required, as these components were not individually priced as line items when placed on contract.

Note: To meet UID requirements, each kit will be assigned an individual serial number. Kits that are comprised of multiple containers will all be marked with the same serial number.

5.2 “Kits” or “ship sets” will typically be assigned lot numbers coinciding with the oldest individual component in the kit.

6. JSF F-35 Instructions. The marking instructions for F-35 components, labels, and packaging, shall be as outlined in this document. Additionally, contractors are required to submit an Electronic Equipment Logbook (EEL) for all serial numbers delivered to the Government. When submitting EELs, the lot number is limited to 10 characters and shall only include the year of production, month of production, interfix number, and sequence number with no dashes. Use of these nine characters will allow for an optional lot suffix as

Acft Explosive Item Noun

CAGE: 12345

P/N: 123456789-1234 Ser No: 0001 deemed necessary by procuring agency. The lot number identified on the Ammo Data Card (ADC) shall match the lot number used on the components and shall be generated

IAW MIL-STD-1168.

7. Waivers. Waivers to the UID requirement are not allowed. Requests for waivers to marking methods outlined in this instruction may be considered. Submit requests through appropriate contracting channels.

CAD/PAD Item

Dated 01 May 2019

Figures

1. Purpose.

2. SCOPE.

3. Marking Requirements.

Example: 08151 = 31 May 2008

Figure 2. Sample UID Data Stream

Figure 3. Sample Data Plate/Label

Figure 4. Sample of Etched Data

Figure 5. Sample Small Item Data Plate/Label

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM

1377012853109ES

E. CONTRACT/PR NO.

F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

Ammunition Data Card (ADC)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.)

DI-MISC-80043B

5. CONTRACT REFERENCE

Airmunitions Specification

6. REQUIRING OFFICE

AFLCMC/EBHJ

7. DD 250 REQ

SD

9. DIST STATEMENT

REQUIRED

B

10. FREQUENCY

ASREQ

12. DATE OF FIRST SUBMISSION

BLK 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION

Draft

Final

Reg Repro

16. REMARKS

BLK 7: The electronic receiving report shall be annotated with the Lot Number, National Stock Number and Nomenclature. The electronic receiving report shall also be annotated to reflect if additional submittals are to be furnished or if this is the final submittal of data. The electronic receiving report shall be used only for this data item; do not combine other data item submittals with this requirement. Electronic receiving report required via internet Wide Area Work Flow (WAWF) at: https://wawf.eb.mil.

BLK 9: DISTRIBUTION STATEMENT B. Distribution authorized to U.S.

Government agencies only, (Administrative/Operational Use) (Date of Contract Award). Other requests for this document shall be referred to AFLCMC/EBHJ.

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C, App. 2401 et seq.), as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.

DESTRUCTION NOTICE - Destroy by any method that will prevent disclosure of contents or reconstruction of the document.

BLK 10,12,13: Submit after successful Lot Acceptance Test and prior to delivery of each production lot.

BLK 14: A sample ADC or "draft" will be generated and submitted for each part number/NSN produced under this contract using the Worldwide Ammunition-data Repository Program (WARP) system to ensure general format and content is acceptable prior to final ADC submittals.

Sufficient hard copies of final version ADCs shall be generated for each individual production lot from the Worldwide Ammunition-data Repository Program (WARP) such that at least one hard copy per production lot shall be provided with each individual CLIN shipment/destination. An electronic copy for each production lot shall be submitted/uploaded with the electronic receiving report through WAWF to AFLCMC/EBHJ using DoDAAC FA8213.

FOB DESTINATION

EBH 20-169-004

Terry McCurdy, AFLCMC/EBHTC, 586-0535

WAWF 0 1 0

DoDAAC, FA8213

Included with item(s) shipped

Sample ADC via

WARP sys only

15. TOTAL 0 1 0

G. PREPARED BY

mccurdy.terry.d.1075978215

H. DATE

2020/06/17

I. APPROVED BY

hargrove.er…