Attachments.pdf
PDF 983 KB Posted
- Solicitation number
- W912WJ25Q0041
About this file
This is a set of maps and schedules showing the locations and work assignments for Park Attendants at the Cape Cod Canal recreation areas. The document details eight park attendant positions (No. 3-8) divided into three paired locations: Herring Run/Sagamore Recreation Areas (Attendants 3 & 4), Sandwich/Sandcatcher Recreation Areas (Attendants 5 & 6), and Bourne/Tidal Flats Recreation Areas (Attendants 7 & 8).
The maps illustrate specific areas of responsibility including comfort stations, camp sites, and trash removal routes along the canal's North and South Service Roads. The document includes detailed work schedules for 2025 (base year) and 2026 (option year), with Schedule A and Schedule B alternating work days between paired attendants. The base year 2025 consists of 95 days for Schedule A and 93 days for Schedule B, while the option year 2026 has 92 days for both schedules, running from April through October. Each location includes designated camp sites for the park attendants, marked on satellite imagery with specific boundaries and comfort station locations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ25Q0041-0001.pdf | ||
| Solicitation W912WJ25Q0041.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PARK ATTENDANTS
CAPE COD CANAL
Figure 1: Park Attendant Camp Site Locations
PARK ATTENDANTS NO 3 & NO 4
CAPE COD CANAL HERRING RUN AND SAGAMORE RECREATION AREAS
Figure 1: Area of Responsibility at the Herring Run Recreation Area
For Herring Run/Sagamore Park Attendants 3 & 4
Figure 3: Area of Responsibility at the Sagamore Recreation Area
For Herring Run/Sagamore Park Attendants 3 & 4
Figure 4: Area of Responsibility for Trash Removal Services Along the Canal’s North
Service Road (Station #230 – 15) for Herring Run/Sagamore Park Attendants 3 & 4.
Figure 5: Park Attendant Camp Sites for Herring Run/Sagamore
Park Attendants 3 & 4.
PARK ATTENDANTS NO. 5&6
CAPE COD CANAL SANDWICH AND SANDCATCHER RECREATION AREAS
Figure 6: Area of Responsibility for Sandwich and Sandcatcher Recreation Areas
Figure 7: Area of trash removal services along the South Service Road from station# 35 - #230
Figure 8: Park Attendant Campsites for Sandwich/Sandcatcher
Park Attendants # 5 & 6
PARK ATTENDANTS NO 7 & NO 8
CAPE COD CANAL BOURNE AND TIDAL FLATS RECREATION AREAS
Figure 9: Area of Responsibility at Bourne Recreation Area
Figure 10: Area of responsibility at Tidal Flats Recreation Area
Figure 11: Area of trash removal services along the South Service Road from station# 230 - #37
PARK ATTENDANTS NO. 3 – NO. 8
Base Year 2025
Park Attendant A & B Base Year Schedule 2025
Both contractors work
Park Attendant 3,5, & 7
SCHEDULE A
Park Attendant 4,6, & 8
SCHEDULE B
Year 2025 = 95 days = 93 days
April 16,17,18,19, 20,21,22,27,28,29,30 16,17,18,19, 23,24,25,26
May 5,6,7,8,13,14,15,16,21,22,23,24,29,30,31 1,2,3,4,9,10,11,12,17,18,19,20,25,26,27,28
June 1,6,7,8,9,14,15,16,17,22,23,24,25,30 2,3,4,5,10,11,12,13,18,19,20,2126,27,28,29
July 1,2,3,4,8,9,10,11,16,17,18,19,24,25,26,27 4,5,6,7,12,13,14,15,20,21,22,23,28,29,30,31
Aug 1,2,3,4,9,10,11,12,17,18,19,20,25,26,27,28 5,6,7,8,13,14,15,16,21,22,23,24,29,30,31
Sept 2,3,4,5,10,11,12,13,18,19,20,21,26,27,28,29 1,6,7,8,9,14,15,16,17,22,23,24,25,30
Oct 4,5,6,7,12,13,14 1,2,3,8,9,10,11,14
PARK ATTENDANTS NO. 3 – NO. 8
Option Year 2026 Park Attendant A & B Option Year Schedule 2026
Both contractor s work
Park Attendant 3,5, & 7
SCHEDULE A
Park Attendant 4,6, & 8
SCHEDULE B
Year 2026 = 92 days = 92 days
April 16,17,18,19,20,21,26,27,28,29 16,17,18, 22,23,24,25,30
May 4,5,6,7,12,13,14,15,20,21,22,23,28,29, 30,31
1,2,3,4,8,9,10,11,16,17,18,19,24,25,26,2
June 5,6,7,8, 13,14,15,1621,22,23,24,29,30 1,2,3,4,9,10,11,12,17,18,19,20,25,26,27, July 1,2,7,8,9,10,15,16,17,18,23,24,25,26,3
3,4,5,6,11,12,13,14,19,20,21,22,27,28,29
,30
Aug 1,2,3,8,9,10,11,16,17,18,19,24,25,26,2
4,5,6,7,12,13,14,15,20,21,22,23,28,29,30
,31
Sept 1,2,3,4,9,10,11,12,17,18,19,20,25,26,2
7,28
5,6,7,8,13,14,15,16,21,22,23,24,29,30
Oct 3,4,5,6,11,12,13 1,2,7,8,9,10,13
File details come from the government source that posted it. Updated .