Attachments.pdf
PDF 4 MB Posted
- Solicitation number
- W912WJ23Q0133
About this file
This document package includes photos and a statement of work for the renovation of a maintenance garage at the Barre Falls Dam in Barre, Massachusetts. The U.S. Army Corps of Engineers is soliciting proposals under solicitation number W912WJ23Q0133 to complete repairs and upgrades to the 40' x 80' garage structure including weatherproofing exterior siding, insulating interior walls, installing a new furnace and 275 gallon fuel tank in bays 2 and 3, and upgrading the electrical panel. Work must be completed by December 31, 2023. Proposals are due by April 15, 2023 and the contract is to be awarded by May 15, 2023. The statement of work and twelve photos provide additional details on the scope of renovations needed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ23Q0133-0002.pdf | ||
| Amendment W912WJ23Q0133-0001.pdf | ||
| Solicitation W912WJ23Q0133.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maintenance Garage Renovation
U.S. Army Corps of Engineers
Barre Falls Dam
Barre, Massachusetts
Statement of Work
Informational Photo #1: Aerial view of the 40’x80’ garage at the bottom left of the image and the access to it from the main road at 200 Coldbrook Rd, Barre, MA
Barre Falls Dam
Barre, Massachusetts
Statement of Work
Informational Photo #2: View from the North of the front of the garage.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #3: View of the single bay (Bay 1) from the overhead door opening.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #4: View of bays 2, 3, and 4 from the NW corner of bay 4.
Barre Falls Dam
Barre, Massachusetts
Statement of Work
Informational Photo #5: Back walls of bays 2 & 3, where furnace and fuel tank are to be installed.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #6: Interior views of garage ceiling.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #7: Exterior view of Eastern wall.
Barre Falls Dam
Barre, Massachusetts
Statement of Work
Informational Photo #8: Photo of holes in metal siding that must be weatherproofed prior to insulating interior walls.
Barre Falls Dam
Barre, Massachusetts
Statement of Work
Informational Photo #9: Example of protective bollards required for the 275 gallon fuel tank installation.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #10: Electrical panel exterior.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #12: Electrical panel breakers.
Barre Falls Dam
Barre, Massachusetts
Informational Photo #12: Electrical panel interior labels.
| Attachments.pdf |
| Attachments 2.pdf |
File details come from the government source that posted it. Updated .