Attachment3_Form 66.pdf
PDF 752 KB Posted
- Attached to
- Repair Fuel Pumphouse 2 Containment Federal contract opportunity
- Solicitation number
- FA500021R0035
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA500021R00350003 SF 30_3.pdf | ||
| Solicitation Amendment FA500021R00350002 SF 30.pdf | ||
| Attachment8_QandA.pdf | ||
| Attachment1_Specs and SOW Revision 2.pdf | ||
| Attachment1_specs and SOW Revision 1.pdf | ||
| Solicitation Amendment FA500021R00350001 SF 30.pdf | ||
| Attachment1_Specs_SOW.pdf | ||
| Solicitation_FA500021R0035.pdf | ||
| Attachment4_Price Schedule.pdf | ||
| Attachment6_Wage Determination.pdf | ||
| Attachment2_Drawings.pdf | ||
| Attachment5_Contractors Fire Safety Guide.pdf | ||
| Attachment 7_Open Market General Specifications.pdf | ||
| Attachment8_DD1354.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF FORM 66, OCT 99 Previous Edition Will Be Used
LI
N
E N
U M
B ER Note: 3 copies required per submittal.
Government will retain all submittals.
Provide an electronic copy for each submittal.
C
ER
TI
F.
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
TU
R
U R
'S R
EC
O
M M
EN
D
AT
IO
C
AT
AL
O
G D
AT
A
O &M
R
EC
O M
M
EN
D
AT
IO
N
S
C
AL
C U
LA
TI
O N
S
W
AR
R
AN
TY
D R
AW
IN
G S
O
TH
ER
TE
ST
R
ES
U
LT
S
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E
TO
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
AP
PR
O
VE
D
D
IS
AP
PR
O
VE
D
C O
N
TR
AC
TO
R S
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
NOTES
GENERAL
1 Project Specific Form 66 X NTP + 10 2 Construction Schedule X NTP + 10 3 Contractor's QA/QC Plan X NTP + 10 4 673 ABW Form 3 X Prior to Start 5 Material Safety Data Sheet (MSDS) X See Notes MSDSs must be submitted and approved by the Government prior to procurement of all potential hazardous materials.
6 Notice of Start of Work X NPT +10 Request Letter 7 Notice of Utility Outages X 14 Days Prior Request Letter 8 Fence Plan X NTP + 10 9 Quality Control Plan X NTP + 10
10 Record of Proper Disposal X Completion of Disposal
11 Operation of On-Base Gravel Extraction Pit X Prior to Extraction 12 Hazzard Communication Plan See Notes Minimum 20 working days prior to start of work
CIVIL
13 Fusion joint records X Completion +5 14 Shear gate X
15 FML X X
16 Blind flange X 17 Post indicator valve X 18 Heat trace channel X 19 Pipe X 20 Pipe Insulation X X 21 Pipe Jacket X 22 Sieve Analysis X 23 Density Tests X 3 Days After Test 24 Compaction Test Plan and Data X NTP + 10 25 Demolition Plan X Prior to Start 26 Concrete Admixtures X NTP + 10 27 Concrete Mix Design Data X NTP + 10 28 Concrete Strength X 3 Days After Test 29 Concrete Curing Materials and Methods X NTP + 10
HAZMAT
30 Environmental Pre-Construction Checklist X NTP + 10 31 JBER HAZMAT Usage Tracking Form X See Notes NLT 10 working days prior to material being brought onto installation 32 JBER HAZMAT Usage Tracking Form X See Notes NLT 7 working days after final acceptance 33 Fuel Spill Clean Up Plan X NTP + 10 34 Enviornmental Protection Plan X See Notes Within 15 working days after award and 10 days prior to preconstruction meeting
SOLICITATION /CONTRACT NUMBERPROJECT NAME
Repair Fuel Pumphouse 2 Contaiment
SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
PROJECT NUMBER
FXSB 19-4700
FA500021F0035
FXSB 19-4700 Repair Fuel Pumphouse 2 Containment
Attachment#3_Form 66
AF FORM 66, OCT 99 Previous Edition Will Be Used
LI
N
E N
U M
B ER Note: 3 copies required per submittal.
Government will retain all submittals.
Provide an electronic copy for each submittal.
C
ER
TI
F.
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
TU
R
U R
'S R
EC
O
M M
EN
D
AT
IO
C
AT
AL
O
G D
AT
A
O &M
R
EC
O M
M
EN
D
AT
IO
N
S
C
AL
C U
LA
TI
O N
S
W
AR
R
AN
TY
D R
AW
IN
G S
O
TH
ER
TE
ST
R
ES
U
LT
S
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E
TO
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
AP
PR
O
VE
D
D
IS
AP
PR
O
VE
D
C O
N
TR
AC
TO
R S
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
NOTES
SOLICITATION /CONTRACT NUMBERPROJECT NAME
Repair Fuel Pumphouse 2 Contaiment
SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
PROJECT NUMBER
FXSB 19-4700
35 Erosion and Sediment Control Plan X NTP + 10 36 Spill Prevention and Clean-Up Plan X NTP + 10
CLOSEOUT
O&M maint. data and maint manuals & Manufacturer's Warranty for All Equipment Installed X X X Install + 5
Factory and Field Test Certificates, Logs and Test Results X Before Acceptance
39 Completion of DD 1354 X Final + 7 40 As Builts X Final + 7
FA500021F0035
FXSB 19-4700 Repair Fuel Pumphouse 2 Containment
Attachment#3_Form 66
Submittal 1