This Quality Assurance Surveillance Plan (QASP) is for the USS DEWEY (DDG-105) FY26 contract under the Chief of Naval Operations (CNO) 6C1, with solicitation number N6264926RA003. The document outlines the government's methodology for monitoring and evaluating contractor performance, with key roles including the Administrative Contracting Officer (ACO) and Project Manager/Contracting Officer Representative (PM/COR). The surveillance methods include direct observation, verification of documentation/deliverables, and inspections.
Performance standards cover multiple assessment areas, including schedule and associated reports, corrective action requests, condition found reports, letters of concern/direction, and cure/show cause notices. The government will continuously monitor the contractor's performance and evaluate deliverables using acceptable quality level standards. Contractors are required to submit various reports according to specified schedules, respond to requests within designated timeframes, and ensure the completeness and accuracy of their submissions. Performance will be documented and may be included in the Contractor Performance Assessment Report System (CPARS) for future reference.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001 Attachment (I).pdf | ||
| Solicitation - N6264926RA003.pdf | ||
| Attachment IV Government Furnished Property.xlsx | XLSX spreadsheet | |
| Attachment VI Warranty Tracking Information.pdf | ||
| Attachment VIII Contract Data Sheet 26RA003.pdf | ||
| Attachment I POP List.xlsx | XLSX spreadsheet | |
| Attachment II Proposal Breakdown Form.xlsx | XLSX spreadsheet | |
| Att III Request for Information Form.pdf | ||
| Attachment V Source of Repair Instruction.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
DEPARTMENT OF THE NAVY
Quality Assurance Surveillance Plan (QASP)
For
USS DEWEY (DDG-105) FY26
Chief of Naval Operations (CNO) 6C1
Solicitation: N6264926RA003
Attachment VII
1. Purpose
This QASP provides the performance criteria, standards, and procedures for the Government’s surveillance and oversight of the Contractor’s performance to assure deliverables are timely, adequate, and complete and to assure performance is meeting the requirements specified in the contract.
2. Government Roles and Responsibilities
The following personnel shall oversee and coordinate surveillance activities:
a. Administrative Contracting Officer (ACO) – The ACO shall assure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The
ACO shall also assure the contractor receives impartial, fair, and equitable treatment under this contract. The ACO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
b. Project Manager (PM) / Contracting Officer Representative (COR) – The PM/COR is responsible for technical administration of the contract and shall assure proper
Government surveillance of the contractor’s performance. The PM/COR shall keep a quality assurance file. The PM/COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
3. Performance Standards
The performance and acceptable quality level standards are listed in Enclosure (1). The
Government shall use these standards to assess contractor performance.
4. Methods of Surveillance
Various methods exist to monitor performance. The Government may use, and is not limited to, the surveillance methods listed below in the administration of this QASP:
a. Direct Observation: The ACO and/or PM/COR will provide on-site oversight to assure the Contractor is adequately performing to the contract specifications.
b. Verification of documentation/deliverables provided by Contractor: Government review and assessment of deliverables (timely submission, accuracy, and completeness) and performance will be accomplished in accordance with the contract/order.
c. Inspections: Other inspections may be made in cases such as accident investigations, etc.
Inspections shall be divided and scheduled as required.
5. Evaluation Ratings
The Government will evaluate the Contractor’s performance of the contract/order and the
PM/COR will assign a rating of either acceptable or unacceptable. The acceptable quality levels are outlined in Enclosure (1).
6. Documenting Performance
The Government will document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing past performance information using the Contractor Performance Assessment Report System (CPARS).
7. Frequency of Measurement
Frequency of Measurement. The frequency of measurement for deliverables is defined in the contract/order. The contractor’s performance will be continuously monitored. The Government will periodically analyze whether the frequency of surveillance is appropriate for the work being performed.
Enclosure (1): Performance Standards & Acceptable Quality Levels
A) Deliverable/
Assessment Area B) Performance / Acceptable Quality Level Requirement
1. Schedule and
Associated Reports per
NAVSEA Standard
Item (NSI) 009-60
a) The Contractor is required to submit the following reports (hereinafter referred to as deliverables), in accordance with the schedule requirements stated in NSI 009-60 Tables 2 and 3 to support the milestones identified in Section F of the Contract:
1. Initial Integrated Production Schedule (IPS)
2. Schedule of Record
3. Weekly IPS
4. 25 Percent Conference Support
5. 50 Percent Conference Support
6. 75 Percent Conference Support
b) Deliverables shall be provided in accordance with the content and format requirements stated in NSI 009-60.
Notes:
i. If the Government does not provide schedules/information for Alteration Installation Team, Government-Contracted Third Party
Maintenance Providers, Ship’s Force, Commercial Industrial Services, Fleet Maintenance Activity, or other schedules/information not known to the contractor, the contractor shall provide the schedule and associated reports (including the IPS) in the required timeframes to include all information known to the contractor up to 7 days prior to the date of required submission.
ii. Should the supervisor and the contractor disagree as to whether an element within NSI 009-60 is objectively required or discretionary, the supervisor will provide direction and/or clarification, which will take effect on the next required submission of the NSI 009-60 deliverable.
iii. Rejection or acceptance of a NSI 009-60 deliverable will be determined on whether:
a. The deliverable provided conforms to the schedule, content and format requirements in NSI 009-60; and
b. The deliverable provided conforms to the Supervisor’s direction and/or clarification of any disputed objective/discretionary elements.
Enclosure (1): Performance Standards & Acceptable Quality Levels
2. Corrective Action
Requests (CARs)
a) The Contractor shall respond to Method C and Method D CARs by the required response date in each respective CAR.
b) The Contractor’s response/resolution to a Method C or Method D CAR is complete and adequate.
3. Accuracy of
Condition Found
Reports (CFRs)
a) CFRs shall be submitted via hard copy or approved electronic media to SRF-JRMC after discovery of the condition and at a minimum, contain the information required by Section C Paragraph C-3.1 of the contract/order and NSI 009-01.
4. Letters of Concern
(LOCs) and Letters of
Direction (LODs)
a) The Contractor shall respond to LOCs and LODs issued by the ACO for failure to meet a requirement of the contract/order by the required response date identified in each respective LOC or LOD.
b) The Contractor’s response/resolution to a LOC or LOD issued by the ACO for failure to meet a requirement of the contract/order is complete and adequate.
5. Cure Notices and
Show Cause Notices
a) In accordance with FAR 49.402-3Procedure for default, the Contractor shall respond to cure notices and show cause notices by the required response date identified in each respective notice.
b) The Contractor’s response/resolution to a cure notice or show cause notice is complete and adequate.