ACADIA NATIONAL PARK
Hancock County, Maine
ACAD-318547
BIKE PATH SURFACE
PROJECT MANUAL
SPECIFICATIONS
NATIONAL PARK SERVICE
ACADIA NATIONAL PARK
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01010 Summary of Work 01270 Definition of Bid Items 01310 Project Meetings 01320 Schedules and Monthly Inspections 01330 Submittals 01360 Accident Prevention 01430 Contractor Quality Control 01510 Temporary Services 015713 Temporary Erosion Controls 01600 Material and Equipment 01770 Project Closeout
DIVISION 2 - SITE WORK
DIVISION 31 EARTH WORK
312000 Earth Moving (Aggregate Emplacement)
TABLES AND DRAWINGS
Table 1 Bike Path Data
Bike Path Map Typical Bike Path Sections
July 1, 2021 TOC-1
July 1, 2021
01010-1
SUMMARY OF WORK
SECTION 01010
PART I - GENERAL
1. DESCRIPTION:
A. The contractor is to provide and install aggregate surface course meeting the attached specifications on Acadia National Park’s broken stone bike paths on Schoodic Peninsula.
B. The Contractor shall spread and compact surface course material in such a manner that the combination of existing surface course and emplaced surface course shall be a uniform 2 inch compacted thickness, while maintaining the existing road geometry (sample profiles furnished in the attached drawings).
C. On site work will be a period of performance of 40 days.
D. The Contractor shall furnish all labor, materials, equipment, tools, transportation services and supplies required to complete the work in accordance with the Contract Documents.
E. All work will be performed under a single contract.
2. LOCATION:
A. The site is located at Schoodic Peninsula, in Acadia National Park in the town of Winter Harbor, Maine.
3. CONTRACTOR'S USE OF PREMISES AND SPECIAL REQUIREMENTS
A. Construction camp: Establishment of a camp within the park will not be permitted.
B. Site limits: Confine all operations to the bike path surface.
C. Site access: Access roads will be open to the public during construction. Sections being worked will be closed. Contractor employees may not bring personal vehicles on the bike path system. Only marked company vehicles approved by the government will be permitted access.
D. On site storage: Equipment necessary for the work and material storage will be allowed in an approved area by COR.
E. Preservation of natural features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
01010-2
F. Park Service personnel will not accept nor handle, store or otherwise take receipt of any materials or correspondence destined, addressed for delivery to the contractor directly or in the care of any party.
G. Existing utilities: None within the confines of the work site.
4. ARCHAEOLOGICAL FEATURES:
A. None.
5. FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before performing work at the site.
6. PUBLICATIONS CITED
A. All publications, references, codes, or standards cited in this specification, regardless if dated or not, shall be the latest published edition. Those that are superseded shall be governed by the superseding document.
END OF SECTION
01310-1
PROJECT MEETINGS
SECTION 01310
PART 1 GENERAL
1 .1 I. PRECONSTRUCTION CONFERENCE
A. Before start of construction, Contracting Officer will hold a meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Correspondence procedures
2. Designation of responsible personnel
3. Labor standards provisions
4. Payroll reports
5. Changes
6. Payments to Contractor
7. Subcontractors
8. National Park Service regulations
9. Accident prevention program (including name of responsible supervisor)
10. Accident reporting
11. Contractor’s Quality Control Program
12. Documents required under the contract
13. Park rules and regulations
14. Recycling Program
15. Saturday, Sunday, holiday and night work
16. Safety program (compliance with the "Accident Prevention" clause of the contract)
17. Cultural Survey and Natural Resource Compliance requirements
18. Tentative construction schedule
19. Submittal of shop drawings, project data, samples, and approved equals
20. Project closeout requirements
21. Relationship of Division 1 to other divisions
01310-2
1 .2 II. PROGRESS MEETINGS
A. The Contracting Officer will schedule weekly meetings with the Contractor and subcontractors.
B. The meeting agenda will include the following as a minimum:
1. Review of work progress
2. Field observations, problems, and decisions
3. Identification of problems which impede planned progress
4. Review of Contractor’s Quality Control Program and activities
5. Review of submittals schedule and status of submittals
6. Review of off-site fabrication and delivery schedules
7. Status of project record drawings (monthly)
8. Status of operation and maintenance data manuals (monthly)
9. Maintenance of progress schedule
10. Corrective measures to regain projected schedules
11. Planned progress during succeeding work period
12. Coordination of projected progress
13. Maintenance of quality and work standards
14. Effect of proposed changes on progress schedule and coordination
15. Other business relating to work
PART 2 – PRODUCTS
Not used.
PART 3- EXECUTION
01320-1
SCHEDULES
SECTION 01320
SCHEDULES
1 .1 DESCRIPTION
A. The work of this section consists of schedule requirements before and during construction.
1 .2 SCHEDULES
A. In accordance with Section M submit a Progress Schedule with the proposal. Within seven (7) calendar days after issuance of subsequent modification/task order and before beginning any work, submit a revised Progress Schedule. Contracting Officer will review the Progress Schedule for format and content.
1. Progress Schedule: Submit with proposal three copies of the Progress Schedule in bar chart or computer program format. Show each area of work.
2. No progress payments will be made until and updated progress schedule is provided.
PART 2 PRODUCTS NOT USED.
PART 3 EXECUTION NOT USED.
01330-1
SUBMITTALS
SECTION 01330
PART 1 - GENERAL
I. DESCRIPTION
A. The work of this section consists of submittal requirements before and during construction.
II. RELATED REQUIREMENTS
A. Closeout submittals - Section 01770.
III. SUBMITTAL AND APPROVAL PROCEDURES
A. All submittals shall be transmitted using National Park Service form CM 16, unless otherwise directed. A Microsoft Word copy is available at:
http://workflow.den.nps.gov/staging/10_PublicForms/Construction/Forms/CM16_02_23_
07.DOC
No action will be taken on a submittal item unless accompanied by the transmittal form.
B. As specified in the individual sections, forward submittals to Contracting Officer (through COR) at least 30 days before need for approval. Unless a different number is specified or it is submitted electronically, submit one reproducible original and two copies of each shop drawing, three copies of manufacturer's catalog sheets (cut sheets), three specimens of each sample, and three copies of all other submittals requested.
1. Shop Drawings: Not Used
2. Samples: Samples shall be large enough to illustrate clearly the functional characteristics and full range of color, texture, or pattern.
3. Manufacturers' Catalog Sheets: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use. MSDS sheets must accompany catalog sheets.
4. Manufacturer's Installation Instructions: When contract documents require compliance with manufacturer's printed instructions, provide one complete set of instructions for Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
C. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
D. Substitutions of alternative items:
1. For each item proposed as substitutions, submit supporting data, including:
a) Drawings and samples as appropriate.
01330-2
b) Comparison of the characteristics of the proposed item with that specified.
c) Changes required in other elements of the work because of the substitution.
d) Name, address, and telephone number of vendor.
e) Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a) Has investigated the proposed item and determined that it is equivalent or superior in all respects to that specified.
b) Will provide the same warranties for the proposed item as for the item specified.
c) Has determined that the proposed item is compatible with interfacing items.
d) Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e) Waives all claims for additional expenses that may be incurred as a result of the substitution.
3. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
E. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.
F. Submittal Identification:
1. Identification shall include the park name, project title, contract number, and transmittal number.
2. All sets of shop drawings, manufacturer's catalog sheets, samples, and other documents submitted to the Contracting Officer must have the identification information on the submittal.
3. Identification information shall be applied to the bottom right margin on each page.
Identification information on samples shall be applied to the most readily visible area on the sample or on tags attached to sample.
G. Submittal Numbering:
1. Number each submittal consecutively.
2. For re-submittals use the original submittal number, plus a letter suffix beginning with A.
3. Additional re-submittals of the same item shall contain the original number with the next consecutive letter.
H. Contracting Officer's Review:
1. Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show
01330-3 evidence of Contractor's approval.
2. Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.
3. After reviewing submittals, the Contracting Officer will return one copy of form CM- 16 and one copy of applicable (marked up) submittal sheets to the Contractor. Shop drawing review notations will be returned on the reproducible original shop drawing.
All other submitted items will be retained. The Contractor is responsible for producing additional copies for his/her own use.
4. The returned submittal will be marked in one of three ways as defined below:
a) APPROVED: Acceptable with no corrections.
b) APPROVED WITH NOTATIONS: Minor corrections or clarifications required.
All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
c) DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
PART 2 – PRODUCTS
PART 3- EXECUTION
01360-1
ACCIDENT PREVENTION
SECTION 01360
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
II. SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with Occupational Safety and Health Administration regulations and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
7. Fire Protection: Section 01510.
B. Certificates: When requested, provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
III. QUALITY ASSURANCE
01360-2
A. In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
IV. ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 3 days of a reportable accident, fill out and forward to the Contracting Officer the attached offline accident reporting worksheet.
B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2 PRODUCTS
I. FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
II. PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA.
III. BARRIERS
A. As per accepted Proposal.
01360-3
PART 3 EXECUTION
I. EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
II. EGRESS
A. Provide and maintain adequate egress at all times in accordance with the Life Safety Code (NFPA 101-94). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with egress.
III. PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
IV. SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the work site.
B. Conduct monthly safety meetings for all levels of supervision. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program.
The Contracting Officer will attend the meeting and enter the results of the meetings into the daily log.
V. HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times.
VI. TRAINING
01360-4
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF
SECTION
01360-5
01430-1
CONTRACTOR QUALITY CONTROL
SECTION 01430
A. The work of this section consists of preparing and executing a quality control program.
II. SUBMITTALS
A. Quality Control Plan: With the Proposal, submit for evaluation a written Contractor Quality Control (CQC) plan. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence by the Contracting Officer. The plan shall include:
1. See Section M.
B. Daily Submittals: See Section M
C. Tests: See Section M
D. Off Site Inspection Reports: See Section M.
E. Progress Payments: If the CQC plan and Daily Quality Control Reports are not submitted in a timely manner, the Contracting Officer may retain an appropriate amount of the applicable progress payment.
III. QUALITY ASSURANCE
A. General: Except for tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
B. Quality Control Staff: The Contractor's job supervisory staff may be used for quality control, supplemented as necessary by additional technicians. The Contractor's designated Quality Control Supervisor shall be employed full time at the project site whenever contract work is in progress.
C. Testing Laboratory and Equipment: Employ certified independent laboratory to perform sampling and testing.
1. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NBS requirements.
Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.
2. The testing laboratory organization shall be experienced in the type of testing work to be done.
PART 2 PRODUCTS Not used.
01430-2
I. OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
II. ON-SITE CONTROL
A. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
B. Preparatory: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for the quality control work.
2. Ensure that provisions have been made for field control testing.
3. Examine the work area to ensure that all preliminary work has been completed.
4. Verify all field dimensions and advise the Contracting Officer of discrepancies.
5. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.
C. Initial: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship. Review control testing procedures to ensure compliance with contract requirements.
D. Follow-Up: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
III. DOCUMENTATION
A. Maintain Daily Quality Control Reports (sample attached) of quality control activities and tests. Daily Quality Control Reports may not be substituted for other written reports required under the General Provisions, such as Disputes, Differing Site Conditions, or Changes.
IV. ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer. Construction shall not proceed on any feature of work containing uncorrected work.
CONTRACTOR'S Q.C. DAILY REPORT REPORT NO.
SHEET 1 OF
PROJECT CONTRACT NO. DATE
PARK CONTRACTOR'S REPRESENTATIVE ON THE JOB
WEATHER (Rain, Snow Cloudy, Windy, etc.)
RAINFALL
Inches
TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)
MAX. MIN.
PRIME CONTRACTOR
NO. EMPLOYEES BY JOB
CATEGORIES
Ho urs
HEAVY EQUIPMENT
ON JOB
NO.
UNIT
S
HRS. WORKING
YE
S
N O
Comme nts
WORK PERFORMED BY PRIME CONTRACTOR:
MATERIALS DELIVERED OFFICIAL VISITORS TO SITE
2A. SUBCONTRACTOR, : (If more than one subcontractor use copies of following page.)
NO. EMPLOYEES BY JOB
CATEGORIES
H o ur s
HEAVY EQUIPMENT ON
JOB
NO.
UNITS
HRS. WORKING
YE
S
N O
WORK PERFORMED BY SUBCONTRACTOR:
SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)
TESTING: Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)
Type and Location of Testing:
VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING
REQUIRED:
REMARKS:
CERTIFICATION:
I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above.
Contractor's Designated Quality Control Representative
SUBCONTRACTOR WORK CONTINUED: CONTRACT NO. REPORT NO.
SHEET OF
SUBCONTRACTOR,
NO. EMPLOYEES BY JOB
CATEGORIES
H o u r s
HEAVY EQUIPMENT ON
JOB
NO.
UNIT
S
HRS. WORKING
YE
S
NO Comments
SUBCONTRACTOR,
NO. EMPLOYEES BY JOB
CATEGORIES
H o u r s
HEAVY EQUIPMENT
ON JOB
NO.
UNIT
S
HRS. WORKING
YE
S
N O
Comments
NO. EMPLOYEES BY JOB CATEGORIES H
o u r s
HEAVY EQUIPMENT
ON JOB
NO.
UNIT
S
HRS. WORKING
Y E S
N O
NO. EMPLOYEES BY JOB CATEGORIES H
o u r s
HEAVY EQUIPMENT
ON JOB
NO.
UNIT
S
HRS. WORKING
Y E S
N O
COMME
NTS
TEST REPORT INFORMATION SHEET
CONTRACT NO. REPORT NO.
SHEET OF
1. Individual Making Inspection or Test:
Testing Laboratory; Name: Phone #:
Address:
Description of Work and Test Method:
Location of Samples and Tests or Inspections:
Specification Section:
Inspection or Test Data:
Test Results and Interpretations of Test Results:
Comments or Professional Opinion About Compliance of Inspected Work or Tested Work with contract Document Requirements:
Recommendations:
Corrective Actions Taken:
CERTIFICATION:
I certify that the above testing report is complete and correct and that all testing performed this day for this contract is in strict compliance with the plans and specifications except as noted above.
Signature of Inspector
01510-1
TEMPORARY SERVICES
SECTION 01510
A. The work of this section consists of providing temporary services required for Contractor's performance of the work of this contract.
B. RELATED REQUIREMENTS
1. Section 01571 3 - Temporary Erosion and Pollution Controls.
I. GENERAL
A. Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
II. SANITARY FACILITIES
A. Provide a portable toilet at the work site.
III. FIRE PROTECTION EQUIPMENT
A. Extinguisher shall have a minimum UL rating of 2-A:10-B:C.
I. ELECTRICITY AND LIGHTING
A. There is no electrical service available.
II. TELEPHONE
A. No telephone service is available on site for Contractor's use.
01510-2
III. WATER
A. Furnish cool, potable water for construction personnel in locations convenient to work stations.
B. No water for compaction will be drawn from lakes within the Park.
IV. SANITARY FACILITIES
A. Clean portable toilet to be moved and kept near the site. Personnel are not to void into the woods.
V. FIRE PREVENTION AND PROTECTION
A. Responsible person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
B. Hazard Control: Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Spark Arresters:
1. Written determinations of periods and areas of potential fire hazard will be issued by Contracting Officer.
2. Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the U.
S. Forest Service.
D. Service and Refueling Areas: Fuel all vehicles and mobile equipment off site. Fuel cans stored on site will be in secondary containment tubs.
E. Smoking: Smoking within buildings or temporary storage sheds is prohibited.
F. Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided.
VI. FIRE PROTECTION EQUIPMENT REQUIRED
A. Vehicles and Equipment:
1. Provide one extinguisher on each vehicle or piece of equipment.
01 57 13 - 1
TEMPORARY EROSION & POLLUTION CONTROL
SECTION 01 57 13 - TEMPORARY EROSION and POLLUTION CONTROL
1.1 SECTION REQUIREMENTS
A. Provide all labor, equipment, materials and maintain temporary erosion control devices as specified herein.
B. Standards:
1. Maine Department of Environmental Protection (MDEP), “Maine Erosion and Sediment Control BMPs”, March 2003 or as later revised.
2. Maine Department of Transportation Standard Specifications (MDOTSS), latest revision.
C. Submittals: Contractor shall furnish to the Contracting Officer, in writing, his Erosion and Sediment Control Plan including proposed locations for transfer of aggregate material. The plan shall also include an erosion control sequence and description of measures to be used to mitigate temporary erosion and shall meet the requirements of the MDEP standard noted above.
A schedule of work shall accompany the work plan. Acceptance of this plan will not relieve the Contractor of the responsibility of completion of the work as specified.
D. Provide such erosion control measures as may be necessary to correct conditions that develop prior to the completion of permanent erosion control devices or as required to control erosion that occurs during normal construction operations.
E. Construction operations shall comply with all federal, state and local regulations pertaining to erosion control.
F. After awarded the Contract, prior to commencement of construction activities, meet with the Contracting Officer to discuss erosion control requirements and develop a mutual understanding relative to details of the Erosion and Sediment Control Plan.
G. Erosion control devices include, but are not limited to, silt fences, filter barriers, rock check dams, straw bales, sand bags, landscaping, and similar items. The extent of erosion control is only partially shown on the Drawings. The Contractor shall also furnish and install all erosion control measures, which are required by other related authorities, such as DEP, local boards, and all other similar entities.
H. The Contractor shall follow the conditions of any State permitting with regard to sedimentation and erosion control. A log of erosion control device inspections and measures taken to improve such shall be maintained by the Contractor for the duration of the project. This maintenance log shall be produced by the Contractor upon request by the Government or MDEP.
I. Design Criteria
1. Conduct all construction in a manner and sequence that causes the least practical disturbance of the physical environment.
01 57 13 - 2
2. Stabilize disturbed earth surfaces in the shortest time and employ such temporary erosion control devices as may be necessary until such time as adequate soil stabilization has been achieved.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Not Used.
PART 3 - EXECUTION
3.1 NARRATIVE
A. When necessary control and catch sediment from newly placed surface which may become suspended in the run-off. This shall be done through the use of stone check dams, silt fence and sedimentation collection areas.
3.2 INSTALLATION
A. Temporary Erosion Checks: Construct temporary erosion checks in ditches and other locations as indicated in the approved plan or as directed by the Contracting Officer.
B. Every week and after precipitation producing the equivalent of one half inch of rainfall, the contractor shall inspect and maintain all erosion control measures. Maintenance shall include, but not be limited to removal of sediment from silt fence or berms if soil accumulates to a depth of one-half the fabric height: repair of stone check dams if runoff channelizes under or around the stone: removal of excess accumulated sediment from dewatering and inlet protection devices: and washing of temporary construction entrances.
C. Reuse: Materials and devices of suitable type and condition may be reused at other on-site locations when approved by the Contracting Officer. Materials and devices, determined by the Contracting Officer to be unsuitable for reuse, shall become the Contractor's property and shall be disposed of in a manner and location outside the park.
3.3 MULCHING
A. Not Used
3.4 AIR POLLUTION CONTROL
A. Take all necessary reasonable measures to minimize air pollution by any material or equipment used during construction.
01 57 13 - 3
3.5 EQUIPMENT FUELING AND SERVICING
A. All construction equipment that frequently travels the Park roads (such as trucks) and other equipment that can reasonably travel from the work area, shall be fueled and serviced outside the Park limits.
B. Fuel and service equipment that cannot reasonably travel from the work area to outside the Park at designated sites within, or accessible from, the work zones.
C. Fuel and service vehicles shall carry tools and materials needed for the clean-up of any accidental spills. Clean up all spills immediately and remove and dispose of contaminated materials outside of the park.
D. Contain, then notify the Contracting Officer of any spillage immediately, regardless of the amount of fuel, oil or other contaminant spilled.
E. Equipment that is found to be leaking fuel, oil, lubricant, or other contaminant shall be immediately removed from the park
F. Minimum equipment/vehicle fueling and maintenance practices that will be implemented to control pollutants to storm water (e.g., secondary containment, drip pans, spill kits, etc.)
G. Fueling equipment is to be maintained according to OSHA regulations. Cleanup materials are to be present near the fueling area and clearly labeled.
H. Equipment Repair and Maintenance - Unless vehicle cannot be moved without incurring further damage, no repairs are to occur on site. If a machine is creating a pollution problem, it must be removed from the site. No equipment will be permitted on site that is leaking any fuels, fluids or lubricants. Any and all routine maintenance is to occur offsite.
I. Maintenance and Inspections shall occur daily
3.6 SPILL PREVENTION AND CONTROL
A. All chemical agents are to be stored in OSHA and DOT approved containers, if applicable. All chemicals are to be stored in a safe manner, and stored in a secondary containment unit whenever possible (i.e. fuel cabinet, concrete spill containment tank, etc.). Containers without secondary containment will not be allowed to sit on the ground. Cleanup materials are to be present near the chemical storage area or equipment that may accidentally leak (eg. Hydraulics, or overturning) and clearly labeled. Spill cleanup materials are to be provided by contractor.
B. In the event of a spill, contractor to contain and notify Government immediately. Once government personnel are on site they will direct cleanup.
END OF SECTION 01 57 13
01600-1 of 1
MATERIAL AND EQUIPMENT
SECTION 01600
MATERIAL AND EQUIPMENT
A. The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.
II. TRANSPORTATION AND HANDLING
A. Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition.
III. STORAGE AND PROTECTION Not Used
IV. STORAGE AND PROTECTION OF EQUIPMENT
A. Store equipment remaining at job site over-night and on weekends in such a way that emergency vehicles and a minimum of one lane of vehicular traffic can pass. The contractor is responsible for any vandalism that might occur to equipment.
PART 2 PRODUCTS Not used.
I. TRANSPORTATION RESTRICTIONS
A. The weight of a fully loaded truck used to haul materials shall observe all State load restrictions. Maximum speed limits in the Park shall always be observed, maximum speed limit on the Bike Paths is 15 MPH, and they will be aggressively enforced.
01770-1
PROJECT CLOSEOUT
SECTION 01770
A. The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.
I. CLEANING
Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish.
Restore or refinish surfaces that are damaged due to work of this contract to original condition.
Pick up all construction debris from the site.
II. PROJECT RECORDS
A. Collect and maintain for inspection on site all quality control records and load tickets.
Deliver copies to the government weekly.
B.
III. CLOSEOUT SUBMITTALS
A. Submit before final inspection request.
1. Project Records: As specified above.
2. Post Construction Guarantees and Bonds: Not used.
3. Spare Parts and Materials: None
4. Operation and Maintenance Data: None
5. Keys: Return all issued keys and locks. Final payment will be withheld until keys are returned or until a contract modification equal to the cost of replacing all like keys and locks is processed.
01770-2
IV. SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. Notify that the project, or designated portion of project, is substantially complete, and request a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.
1. When work is determined to be substantially complete, Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may replace, repair, or remedy the work with an appropriate reduction in the contract price.
2. If work is not determined to be substantially complete, Contracting Officer will notify Contractor in writing. After completing work, Contractor shall resubmit certification and request a new final inspection.
V. ACCEPTANCE OF THE WORK
A. After all deficiencies have been corrected, a Letter of Acceptance will be issued, and a Release of Claims will be forwarded to the contractor for signature.
31 20 00 - 1
EARTH MOVING
SECTION 31 20 00 – EARTH MOVING (Aggregate Emplacement)
1.1 DESCRIPTION OF WORK
A. Placement of carriage road surface course.
1.2 GENERAL REQUIREMENTS
A. Provisions of the General Conditions apply to this section.
B. All work shall be performed and completed in conformance with all applicable local, State & Federal requirements. Specifically, permits obtained by the Government and including requirements for construction are incorporated into these specifications and shall be implemented by the Contractor.
1.3 SURVEYING AND LAYOUT
A. The Contractor shall establish a temporary stationing system for quality control purposes.
B. Markings shall not be permanent and must be removed after government verification.
1.4 QUALITY ASSURANCE
A. Regulatory agencies, codes & standards
All work shall be performed in accordance with all applicable Local, State or Federal regulations and requirements, including Occupational Safety standards. The Contractor shall be responsible for verifying that required permits are secured and approved prior to starting any work affected by such requirements.
B. Soil testing and inspection
Contractor shall provide soil testing and quality control testing during earthwork operations from an independent testing entity acceptable to both the Government and the Contractor. The cost of all testing shall be borne by the Contractor. Contractor shall obtain and submit to the Contracting Officer the test results for every soil proposed to meet specified material or to be used within the project, prior to such material being used on the project. These tests shall include:
a. Optimum moisture-density curve as determined by ASTM D 1557 (modified proctor)
b. Sieve analysis as determined by ASTM C-117 & C-136
c. In addition to initial testing, Contractor shall perform additional gradation tests and furnish results as materials are processed and/or delivered. Frequency of
31 20 00 - 2 additional testing shall be 1 test per 500 cubic yards. If source of materials should change after completion of original test, a complete set of tests, as required above, shall be performed again.
d. The Government reserves the right to conduct quality control inspection and testing to determine the reliability of the test results.
e. Materials delivered that do not comply with the specifications and/or certifications shall be removed from the site at no cost to the Government.
1.5 SUBMITTALS
A. Comply with Section 01330 (Submittals) with regard to process and quantity of submittals.
B. Submittals shall be prepared for items including, but not limited to:
1. Soil gradations
2. Soil density tests (modified proctors)
1.6 PROTECTION OF PERSONS AND PROPERTY
A. The Contractor shall be responsible to ensure that all persons and property are adequately protected. The public, structures, utilities, traffic, sidewalks, pavements and other facilities shall be protected from damage caused by settlement, lateral movement, undermining, washout and any other hazard created by the earthwork operations. Protect all existing trees, shrubs and plantings.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Crushed Stone Aggregate Surface Course Material (Half Inch Minus)
1. Aggregate shall consist of hard, durable particles or fragments of crushed stone or gravel conforming to the following requirements and gradations:
Los Angles abrasion, ASTM C 131 and C 535 ................ 50% max.* Fractured faces (one face) ................................................ 95% min.* Fracture faces (two faces) ................................................ 75% min.* Soundness loss, 5 cycles, ASTM C 88 (magnesium) ....... 18% max.* Flat/Elongated (length to width >5 ASTM D4791 .......... 15% max.*
* Based on the portion retained on the 3/8" sieve
2. Materials shall be free from organic material and lumps or balls of clay.
3. Material passing the No. 4 sieve shall consist of natural or crushed sand and fine mineral particles. The material including any blended filler, shall have a plasticity index of not
31 20 00 - 3 more than 6 and a liquid limit of not more than 25 when tested in accordance with ASTM D4318.
4. Aggregate shall contain a minimum of 5% clay particles by no more than 50% of that portion of material passing the No. 200 sieve size shall be clay. Inorganic clay to be used as binder shall conform to the following:
Passing No. 200 ......................... 75% Liquid Limit ........................... 30 min.
Plastic Index ............................. 8 min.
5. The fraction of material passing the No. 200 sieve size shall be determined by washing as indicated in ASTM D1140, "Amount of Material in Soils Finer Than the No. 200 Sieve."
The fractured faces for the coarse aggregate portion (retained on the No. 4 Sieve) shall have an area of each face equal to at least 75% of the smallest midsectional area of the piece. When two fractured faces are contiguous, the angle between the planes of fractures shall be at least 30 degrees to count as two fractured faces. Fractured faces shall be obtained by mechanical crushing.
6. Gradation shall be obtained by crushing, screening, and blending processes as may be necessary. Material shall meet following screen analysis requirements by weight.
Sieve Designation Percent Passing 1/2" 100% 3/8” 90-100% No. 4 60-81% No. 8 44-60% No. 40 20-33% No. 200 10-16%
PART 3 - EXECUTION
3.1 AGGREGATE EMPLACEMENT
A. Emplace with a paver modified to integrate the crown such that a full width uniform surface is achieved with the crown.
B. The contractor will be responsible for measuring existing surface course in advance of the placement, determining emplacement thickness, assuring that a uniform thickness has been emplaced and compacted to specifications, that the road profile has been maintained.
C. The standard for depth shall be to approach 2 inches of surface course depth without going under.
D. Sections over 100’ long that consistently have depths under 2 inches or over 2.5 inches, or do not have an evenly graded surface, or do not have sufficient compaction, will be required to be reworked.
E. Placement will be in accordance with the approved quality control plan.
31 20 00 - 4
F. Compaction
1. Field density tests shall be provided in accordance with ASTM 1556 or ASTM D2922 methods. They shall be provided, as a minimum, at the following locations, frequency and meeting the following requirements:
a. 95% of maximum dry density.
b. Water shall be added to the material required to optimum moisture content and to control dust.
G. Allow testing agency to inspect and test in accordance with the approved quality control plan.
Contractor shall be responsible for the cost of compaction testing.
3.2 EQUIPMENT
A. Limit equipment and access per Section 01600 and accepted proposal
END OF SECTION 31 20 00