Attachment K.2 API 653 Repair Report - Fac 400.pdf
PDF 1 MB Posted
- Attached to
- POL Tank Inspection, Grissom ARB, IN
- Solicitation number
- W9128F22Q0105
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment C - Tank Data Sheet.xlsx | XLSX spreadsheet | |
| Attachment K - Fac 400 Inspection Report.pdf | ||
| Attachment D - Monthly Contractors Progress Management and Status Report.xlsx | XLSX spreadsheet | |
| Attachment J - API External Inspection Template (002).pdf | ||
| Solicitation W9128F22Q0105.pdf | ||
| Attachment B - Fuel Tank Storage List - CTG.xlsx | XLSX spreadsheet | |
| Attachment A - General Installation Security Requirements.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA
MATERIAL SAMPLES, OR MANUFACTURER'S
CERTIFICATES OF COMPLIANCE
DATE TRANSMITTAL NO.
CONTRACT NO.
PAGEPROJECT TITLE
LOCATION
33 56 13.13-19 11/4/2021
CMP - Grissom ARB Tanks 400, 402, 403
W9128F-16-D-0028 W9128F18F0190
Item Description Variation QA Code
62 API 653 Inspection Report - Tank 400 No A
SECTION III - GOVERNMENT REVIEW REMARKS
No remarks
Attachment to ENG FORM 4025-R Page 1 of 1
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR
MANUFACTURER'S CERTIFICATES OF COMPLIANCE
For use of this form, see ER 415-1-0; the proponent agency is CECW-CE
SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)
TO: FROM: CONTRACT NO. THIS IS A:
PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal) THIS TRANSMITTAL IS FOR: (Check one)
DATE TRANSMITTAL NO.
NEW TRANSMITTAL
9/28/2021 33 56 13.13-19
CMP - Grissom ARB Tanks 400, 402, 403,33 56 13.13-Steel Tanks with Fixed Roofs
W9128F-16-D-0028 W9128F18F0190
Defense Fuels Resident Office PO Box 13287 Offutt AFB, NE 68113
Reliable Contracting Group, LLC 13035 Middletown Industrial Blvd.
Louisville KY40223-4762
USA
FIO GA DA CR DA/CR DA/GA S
ITEM NO.
(See Note
3) a.
DESCRIPTION OF SUBMITTAL ITEM
(Type size, model number/etc) b.
SUBMITTAL TYPE CODE
(See Note 8) c.
NO. OF
COPIES
d.
CONTRACT REFERENCE
DOCUMENT
SPEC. PARA
NO.
e.
DRAWING
SHEET NO.
f.
FOR
CONTRACTOR
USE
g.
VARIATION
(See
Instruction No.
6) h.
FOR CE USE
CODE
(Note 9) i.
62 API 653 Inspection Report - Tank 400 11 - CLOSEOUT SUBMITTALS 14 A No
Contractor Reviewer: Chris Bertz, Project Manager, PH: (502) 244-2596, Ext. 4474
Remarks from Contractor
ENCLOSURES RETURNED (List by item No.) DATE
SECTION II - APPROVAL ACTION
NAME, TITLE AND SIGNATURE OF APPROVING AUTHORITY
I certify that the above submitted items have been reviewed in detail and are correct and in the strict conformance with the contract drawings and specifications except as otherwise stated.
NAME AND SIGNATURE OF CONTRACTOR
ENG FORM 4025-R, JUL 2015 REPLACES EDITION OF MAR 2012, WHICH IS OBSOLETEPage 1 of 1 thurt Typewriter Chris Bertz, Project Manager
Reliable Contracting Group
13035 Middletown Industrial Blvd.
Louisville, KY 40223
33 56 13.13-19
_X_ Approved
__ Approved with corrections as noted on submittal data and/or attached sheet(s).
Signature:______________________________________________________________
Title: Chris Bertz, Project Manager, PH: 502-244-2596, Ext. 4474
Date: 9/28/2021
Item # 62 – API 653 Inspection Report – Tank 400
US Army Corps of Engineers
Omaha District
API 653 Repair Inspection Report - Final
Grissom Joint ARB
Tank Number 400
US Army Corps of Engineers Center of Expertise for Petroleum, Oils and Lubricants
(USACE POL-MCX)
29 July 2021
Table of Contents
ACRONYMS AND ABBREVIATIONS
SUITABILITY FOR SERVICE MEMORANDUM
GENERAL TANK INFORMATION
TANK REPAIRS
1. Remove and Replace Tank Bottom
2. Provide Concrete Ringwall Foundation
3. Remove and Replace External Tank Roof
4. Repair Tank Coatings
5. Repair Tank Level Alarms
6. Repair Shell Overflows
7. Repair Tank Stairs
8. Repair Manways
9. Provide Low Suction Piping
10. Provide Thermal Relief Piping
11. Provide Water Draw-Off Tank
12. Repair Stilling Wells
13. Repair Issue/Receipt Piping
14. Provide Anti-Rotation Cables
15. Replace Internal Floating Roof
16. Replace Mechanical Tape Gauge
17. Remove AFFF System and Supports
18. Provide Tank Identifiers
19. Provide Tank Strapping Chart
20. Perform Hydrostatic Test
21. Perform Non-Destructive Examination in Accordance with API 653
22. Provide Final API 653 Report
23. Replace AST Containment Systems
APPENDIX A: ENGINEERING DRAWINGS
APPENDIX B: VERTICALITY REPORT
ACRONYMS AND ABBREVIATIONS
API
ASME
ASNT
ATG
American Petroleum Institute
American Society of Mechanical Engineers
American Society of Non-Destructive Testing
Automatic Tank Gauge
BBL Barrel
CFR Code of Federal Regulations
CP Cathodic Protection
DFT Dry Film Thickness
HLA High Level Alarm
HLCS High Level Control Shutoff
HHLA High-High Level Alarm
LLA Low Level Alarm
LLLA Low-Low Level Alarm
MFL Magnetic Flux Leakage
MT Magnetic Particle Testing
NACE National Association of Corrosion Engineers
NDT Non-Destructive Testing
NFPA National Fire Protection Association
PSI Pounds per Square Inch
PT Penetrant Testing
P/V Pressure/Vacuum
RP Recommended Practice
PST Product Saver Tank
RT Radiography Testing
TML Thickness Measurement Location
TRV Thermal Relief Valve
UFC Unified Facilities Criteria
UFGS Unified Facilities Guide Specifications
ULS Ultra-Low Sulfur
UT Ultrasonic Testing
VT Visual Testing
SUITABILITY FOR SERVICE
MEMORANDUM
STORAGE TANK NO. 400
Out-of-Service API 653 Tank Inspection and Repair
Contract No. W9128F-16-D-0028, Delivery Order No. W9128F18F0190
Grissom ARB, IN
Tank 400 was inspected 1 April 2021 to 29 July 2021. An API 653 Repair Inspection was performed by Darrin
Laughlin. This tank report is an Appendix to the original API 653 tank report.
On this date 29 July 2021, the tank is in suitable condition for return to service.
Mandatory Repairs
No mandatory repairs were required.
Other Repairs and Maintenance
1. Remove and Replace Tank Bottom
2. Provide Concrete Ringwall Foundation
3. Remove and Replace External Tank Roof
4. Repair Tank Coatings
5. Repair Tank Level Alarms
6. Repair Shell Overflows
7. Repair Tank Stairs
8. Repair Manways
9. Provide Low Suction Piping
10. Provide Thermal Relief Piping
11. Provide Water Draw-Off Tank
12. Repair Stilling Wells
13. Repair Issue/Receipt Piping
14. Provide Anti-Rotation Cables
15. Replace Internal Floating Roof
16. Replace Mechanical Tape Gauge
17. Remove AFFF System and Supports
18. Provide Tank Identifiers
19. Perform NDE Examination
20. Replace AST Containment Systems
Inspection Intervals
The next In-Service Inspection should occur in 5 years (July 2026) and the next UT thickness measurements should occur in 9 years (June 2030) in accordance with API 653.
The next Out-of-Service inspection should occur in 10 years (July 2031).
This storage tank suitability for service evaluation has been completed in accordance with the requirements of API Standard 653, 5th Edition, Addendum 2, May 2020.
Prepared by:
Darrin A Laughlin
US Tank Inspection Manager
AmSpec
API 653 Certified Inspector No. 29230
GENERAL TANK INFORMATION
ITEM DESCRIPTION
Owner Grissom Joint Air Reserve Base
Location Grissom ARB, Indiana
Tank Number 400
State / Country Indiana, USA
City Cass and Miami Counties
Inspection Date 4/1/21 – 7/29/21
Tank Manufacturer Chicago Bridge & Iron
Design Standard API 12C
Date of Construction Assumed 1955
Tank Contents JP-8
Tank Diameter 60.0000 Feet
Shell Height 30.3333 Feet
Product Height 25.00 Feet
Tank Capacity 577,475 Gallons
Foundation Concrete Ringwall
Construction
Bottom Lap-Welded
Shell Butt-Welded
Floating Roof Petrex Aluminum Honeycomb
Fixed Roof Lap-Welded
Material
Bottom 0.3125” A36
Shell Assumed A36
Floating Roof Aluminum
Fixed Roof 0.250” A36
Cathodic Protection Impressed Current
Interior Coating System Thin Film Epoxy
Exterior Coating System Thin Film Epoxy
Level Gauging Varec 2500 Tape Gauge
Overfill Protection High and High-High Level Alarms
Piping Receipt 8” Carbon Steel
Issue 10” Carbon Steel
Low Suction 4” Carbon Steel
Water Draw-Off 2” Carbon Steel
Level Alarms Low-Low Level Alarm: 2’-6.5”
Low Level Alarm: 2’-10”
High Level Alarm: 25’-5.75”
High-High Level Alarm: 26’-3.25”
Type of Internal Floating Roof Petrex Aluminum Honeycomb
TANK REPAIRS
1. Remove and Replace Tank Bottom
OBSERVATION: Tank bottom was replaced with new cone down, lap-welded bottom.
2. Provide Concrete Ringwall Foundation
OBSERVATION: New concrete ringwall foundation.
3. Remove and Replace External Tank Roof
OBSERVATION: New cone-up, lap-welded fixed roof installed
4. Repair Tank Coatings
OBSERVATION: New interior tank coatings on shell, bottom, fixed roof, and all interior appurtenances.
5. Repair Tank Level Alarms
OBSERVATION: New level alarms installed
6. Repair Shell Overflows
OBSERVATION: New shell overflows installed at new overflow elevations
7. Repair Tank Stairs
OBSERVATION: Existing stairs were replaced with a new galvanized stair system.
8. Repair Manways
OBSERVATION: New 36” manways installed
9. Provide Low Suction Piping
OBSERVATION: New 4” low suction line installed
10. Provide Thermal Relief Piping
OBSERVATION: New thermal relief piping systems installed on the issue, receipt, and new 4” low suction line
11. Provide Water Draw-Off Tank
OBSERVATION: New stainless steel 55-gallon water draw-off tank installed
12. Repair Stilling Wells
OBSERVATION: New 8” and 6” aluminum stilling wells installed
13. Repair Issue/Receipt Piping
OBSERVATION: External issue/receipt piping system was modified
14. Provide Anti-Rotation Cables
OBSERVATION: Anti-rotation cables installed
15. Replace Internal Floating Roof
OBSERVATION: NEW ALUMINUM HONEYCOMB FLOATING ROOF INSTALLED
16. Replace Mechanical Tape Gauge
OBSERVATION: New mechanical tape gauge installed
17. Remove AFFF System and Supports
OBSERVATION: All materials related to the AFFF system were removed
18. Provide Tank Identifiers
OBSERVATION: Data plate was installed
19. Provide Tank Strapping Chart
OBSERVATION: New strapping charts in 1/16” increments were provided.
20. Perform Hydrostatic Test
OBSERVATION: Tank hydrostatic test was performed.
21. Perform Non-Destructive Examination in Accordance with API 653
OBSERVATION: MT examination was performed at the tank tape gauge supports, stairway platform supports, and AFFF piping supports.
22. Provide Final API 653 Report
OBSERVATION: A final API 653 report for UT floor scan was provided.
23. Replace AST Containment Systems
OBSERVATION: New FML containment system with drain inlet was provided.
APPENDIX A: ENGINEERING DRAWINGS
APPENDIX B: VERTICALITY REPORT
April 1, 2021
VERTICALITY REPORT
FOR
GRISSOM AFB
GRISSOM AFB, IN.
This report documents the findings of the examinations performed on April 1, 2021.
Amspec personnel:
Darrin Laughlin
Nick Guilliam
INTRODUCTION
1 DESCRIPTION……………………………………………………………………………..
2 SUMMARY…………………………………………………………………………………..
3 VERTICALITY SURVEY…………………………………………………………………
TABLE OF CONTENTS
Owner: GRISSOM AFB Date: 4/1/2021
Location: INDIANA
Tank: 400
SUMMARY
The following is a summary of the significant findings of the inspection.
A verticality survey was performed to measure the radial deviations of the shell. The maximum out‐of‐plumbness was found to be at Station No. 4 which deviated outwards by 1.344 inches.
The maximum calculated internal diameter was found to be 60.101 feet at Station
2 (diametrically opposite Station 6) at an elevation of 16.2 feet. The minimum calculated internal diameter was found to be 59.841 feet at Station 1
(diametrically opposite Station 5) at an elevation of 1 foot.
Client #:
Tank: 400
VERTICALITY SURVEY
METHODOLOGY
The verticality survey was conducted at eight (8) vertical stations, evenly spaced around the tank starting at the Gauge Point. Using the bottom course as a reference circle, ( 3.5 foot elevation), the shell deviations were measured with three (3) readings per course, one foot above the lower horizontal weld, at the middle of the course, and one foot below the upper horizontal weld.
The analysis involves calculating the internal tank diameter at various elevations.
The internal diameter is calculated by using two methods. A two (2) point analysis, whereby shell deviations diametrically opposed to each other are used to calculate an internal diameter thus giving the verticality, and a three (3) point analysis where by the shell deviations at three (3) triangulated stations are used to calculate an internal diameter thus giving the roundness.
Tank: 400
VERTICALITY SURVEY
2 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
OFFSET DELTA OFFSET DELTA CAL. TANK
REFERENCE inch 359.778 RADIUS in. 359.778 RADIUS in. INSIDE DIA ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 358.818 ‐0.96 359.274 ‐0.504 59.841
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 0 359.778 0 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 359.73 ‐0.048 359.706 ‐0.072 59.953
COURSE 2 ‐ 8.75 FT. ELEVATION 359.61 ‐0.168 359.562 ‐0.216 59.931
COURSE 2 ‐ 11.3 FT. ELEVATION 359.418 ‐0.36 359.37 ‐0.408 59.899
COURSE 2 ‐ 14.2 FT. ELEVATION 359.322 ‐0.456 359.154 ‐0.624 59.873
COURSE 3 ‐ 16.2 FT. ELEVATION 359.49 ‐0.288 359.178 ‐0.6 59.889
COURSE 3 ‐ 18.9 FT. ELEVATION 359.658 ‐0.12 359.274 ‐0.504 59.911
COURSE 3 ‐ 21.8 FT. ELEVATION 359.754 ‐0.024 359.274 ‐0.504 59.919
COURSE 4 ‐ 23.8 FT. ELEVATION 359.802 0.024 359.586 ‐0.192 59.949
COURSE 4 ‐ 26.75 FT. ELEVATION 359.778 0 359.658 ‐0.12 59.953
COURSE 4 ‐ 29.5 FT. ELEVATION 359.538 ‐0.24 359.778 0 59.943
MAXIMUM CALCULATED INTERNAL DIAMETER 59.963
MINIMUM CALCULATED INTERNAL DIAMETER 59.841
RADIAL DEVIATION (POSITIVE) 0.024 0
RADIAL DEVIATION (NEGATIVE) ‐0.96 ‐0.504
STATION 1 STATION 5
Tank: 400
COURSE 6
COURSE 5
COURSE 4
COURSE 3
COURSE 2
COURSE 1
Client #:
‐0.960
0.000
‐0.048
‐0.168
‐0.360
‐0.456
‐0.288
‐0.120
‐0.024
0.024
0.000
‐0.240
‐2.5002.500
Station 1
‐0.504
0.000
‐0.072
‐0.216
‐0.408
‐0.624
‐0.600
‐0.504
‐0.504
‐0.192
‐0.120
0.000
‐2.500 2.500
Station 5
Tank: 400
VERTICALITY SURVEY
2 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
OFFSET DELTA OFFSET DELTA CAL. TANK
REFERENCE inch 359.778 RADIUS in. 359.778 RADIUS in. INSIDE DIA ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 360.786 1.008 360.378 0.6 60.097
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 0 359.778 0 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 360.234 0.456 359.754 ‐0.024 59.999
COURSE 2 ‐ 8.75 FT. ELEVATION 360.714 0.936 360.138 0.36 60.071
COURSE 2 ‐ 11.3 FT. ELEVATION 360.882 1.104 360.162 0.384 60.087
COURSE 2 ‐ 14.2 FT. ELEVATION 361.05 1.272 360.162 0.384 60.101
COURSE 3 ‐ 16.2 FT. ELEVATION 361.122 1.344 360.09 0.312 60.101
COURSE 3 ‐ 18.9 FT. ELEVATION 361.05 1.272 359.826 0.048 60.073
COURSE 3 ‐ 21.8 FT. ELEVATION 361.074 1.296 359.658 ‐0.12 60.061
COURSE 4 ‐ 23.8 FT. ELEVATION 361.098 1.32 359.586 ‐0.192 60.057
COURSE 4 ‐ 26.75 FT. ELEVATION 360.93 1.152 359.418 ‐0.36 60.029
COURSE 4 ‐ 29.5 FT. ELEVATION 361.002 1.224 359.322 ‐0.456 60.027
MAXIMUM CALCULATED INTERNAL DIAMETER 60.101
MINIMUM CALCULATED INTERNAL DIAMETER 59.963
RADIAL DEVIATION (POSITIVE) 1.344 0.6
RADIAL DEVIATION (NEGATIVE) 0 ‐0.192
STATION 2 STATION 6
Tank: 400
COURSE 6
COURSE 5
COURSE 4
COURSE 3
COURSE 2
COURSE 1
Client #:
1.008
0.000
0.456
0.936
1.104
1.272
1.344
1.272
1.296
1.320
1.152
1.224
‐2.5002.500
Station 2
0.600
0.000
‐0.024
0.360
0.384
0.384
0.312
0.048
‐0.120
‐0.192
‐0.360
‐0.456
Station 6
Tank: 400
VERTICALITY SURVEY
2 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
OFFSET DELTA OFFSET DELTA CAL. TANK
REFERENCE inch 359.778 RADIUS in. 359.778 RADIUS in. INSIDE DIA ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 359.4168 ‐0.3612 359.61 ‐0.168 59.9189
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 0 359.778 0 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 359.658 ‐0.12 359.73 ‐0.048 59.949
COURSE 2 ‐ 8.75 FT. ELEVATION 359.706 ‐0.072 359.826 0.048 59.961
COURSE 2 ‐ 11.3 FT. ELEVATION 359.634 ‐0.144 359.73 ‐0.048 59.947
COURSE 2 ‐ 14.2 FT. ELEVATION 359.682 ‐0.096 359.634 ‐0.144 59.943
COURSE 3 ‐ 16.2 FT. ELEVATION 359.586 ‐0.192 359.562 ‐0.216 59.929
COURSE 3 ‐ 18.9 FT. ELEVATION 359.418 ‐0.36 359.634 ‐0.144 59.921
COURSE 3 ‐ 21.8 FT. ELEVATION 359.418 ‐0.36 359.658 ‐0.12 59.923
COURSE 4 ‐ 23.8 FT. ELEVATION 359.418 ‐0.36 359.97 0.192 59.949
COURSE 4 ‐ 26.75 FT. ELEVATION 359.514 ‐0.264 360.138 0.36 59.971
COURSE 4 ‐ 29.5 FT. ELEVATION 359.826 0.048 360.234 0.456 60.005
MAXIMUM CALCULATED INTERNAL DIAMETER 60.005
MINIMUM CALCULATED INTERNAL DIAMETER 59.9189
RADIAL DEVIATION (POSITIVE) 0 0.456
RADIAL DEVIATION (NEGATIVE) ‐0.3612 ‐0.216
STATION 3 STATION 7
Tank: 400
COURSE 6
COURSE 5
COURSE 4
COURSE 3
COURSE 2
COURSE 1
Client #:
‐0.361
0.000
‐0.120
‐0.072
‐0.144
‐0.096
‐0.192
‐0.360
‐0.360
‐0.360
‐0.264
0.048
‐2.5002.500
Station 3
‐0.168
0.000
‐0.048
0.048
‐0.048
‐0.144
‐0.216
‐0.144
‐0.120
0.192
0.360
0.456
Station 7
Tank: 400
VERTICALITY SURVEY
2 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
OFFSET DELTA OFFSET DELTA CAL. TANK
REFERENCE inch 359.778 RADIUS in. 359.778 RADIUS in. INSIDE DIA ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 359.61 ‐0.168 359.826 0.048 59.953
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 0 359.778 0 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 360.114 0.336 359.85 0.072 59.997
COURSE 2 ‐ 8.75 FT. ELEVATION 360.234 0.456 359.874 0.096 60.009
COURSE 2 ‐ 11.3 FT. ELEVATION 360.258 0.48 359.922 0.144 60.015
COURSE 2 ‐ 14.2 FT. ELEVATION 360.354 0.576 360.114 0.336 60.039
COURSE 3 ‐ 16.2 FT. ELEVATION 360.522 0.744 360.09 0.312 60.051
COURSE 3 ‐ 18.9 FT. ELEVATION 360.546 0.768 360.09 0.312 60.053
COURSE 3 ‐ 21.8 FT. ELEVATION 360.618 0.84 360.21 0.432 60.069
COURSE 4 ‐ 23.8 FT. ELEVATION 360.426 0.648 360.234 0.456 60.055
COURSE 4 ‐ 26.75 FT. ELEVATION 360.426 0.648 360.186 0.408 60.051
COURSE 4 ‐ 29.5 FT. ELEVATION 360.498 0.72 360.21 0.432 60.059
MAXIMUM CALCULATED INTERNAL DIAMETER 60.069
MINIMUM CALCULATED INTERNAL DIAMETER 59.953
RADIAL DEVIATION (POSITIVE) 0.84 0.456
RADIAL DEVIATION (NEGATIVE) ‐0.168 0
STATION 4 STATION 8
Tank: 400
COURSE 5
COURSE 4
COURSE 3
COURSE 2
COURSE 1
Client #:
‐0.168
0.000
0.336
0.456
0.480
0.576
0.744
0.768
0.840
0.648
0.648
0.720
‐5.0000.0005.000
Station 4
0.048
0.000
0.072
0.096
0.144
0.336
0.312
0.312
0.432
0.456
0.408
0.432
‐5.000 5.000
Station 8
Tank: 400
VERTICALITY SURVEY
3 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
1 3 6 3 POINT 3 POINT
0 degrees 90 degrees 225 degrees INSIDE INSIDE
REFERENCE inch RADIUS in. RADIUS in. RADIUS in. RADIUS in. DIAMETER ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 358.818 359.417 360.378 359.538 59.923
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 359.778 359.778 359.778 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 359.730 359.658 359.754 359.714 59.952
COURSE 2 ‐ 8.75 FT. ELEVATION 359.610 359.706 360.138 359.818 59.970
COURSE 2 ‐ 11.3 FT. ELEVATION 359.418 359.634 360.162 359.738 59.956
COURSE 2 ‐ 14.2 FT. ELEVATION 359.322 359.682 360.162 359.722 59.954
COURSE 3 ‐ 16.2 FT. ELEVATION 359.490 359.586 360.090 359.722 59.954
COURSE 3 ‐ 18.9 FT. ELEVATION 359.658 359.418 359.826 359.634 59.939
COURSE 3 ‐ 21.8 FT. ELEVATION 359.754 359.418 359.658 359.610 59.935
COURSE 4 ‐ 23.8 FT. ELEVATION 359.802 359.418 359.586 359.602 59.934
COURSE 4 ‐ 26.75 FT. ELEVATION 359.778 359.514 359.418 359.570 59.928
COURSE 4 ‐ 29.5 FT. ELEVATION 359.538 359.826 359.322 359.562 59.927
MAXIMUM CALCULATED INTERNAL DIAMETER 59.970
MINIMUM CALCULATED INTERNAL DIAMETER 59.923
Tank: 400
VERTICALITY SURVEY
3 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
2 4 7 3 POINT 3 POINT
45 degrees 135 degrees 270 degrees INSIDE INSIDE
REFERENCE inch RADIUS in. RADIUS in. RADIUS in. RADIUS in. DIAMETER ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 360.786 359.610 359.610 360.002 60.000
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 359.778 359.778 359.778 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 360.234 360.114 359.730 360.026 60.004
COURSE 2 ‐ 8.75 FT. ELEVATION 360.714 360.234 359.826 360.258 60.043
COURSE 2 ‐ 11.3 FT. ELEVATION 360.882 360.258 359.730 360.290 60.048
COURSE 2 ‐ 14.2 FT. ELEVATION 361.050 360.354 359.634 360.346 60.058
COURSE 3 ‐ 16.2 FT. ELEVATION 361.122 360.522 359.562 360.402 60.067
COURSE 3 ‐ 18.9 FT. ELEVATION 361.050 360.546 359.634 360.410 60.068
COURSE 3 ‐ 21.8 FT. ELEVATION 361.074 360.618 359.658 360.450 60.075
COURSE 4 ‐ 23.8 FT. ELEVATION 361.098 360.426 359.970 360.498 60.083
COURSE 4 ‐ 26.75 FT. ELEVATION 360.930 360.426 360.138 360.498 60.083
COURSE 4 ‐ 29.5 FT. ELEVATION 361.002 360.498 360.234 360.578 60.096
MAXIMUM CALCULATED INTERNAL DIAMETER 60.096
MINIMUM CALCULATED INTERNAL DIAMETER 59.963
Tank: 400
VERTICALITY SURVEY
3 POINT DIAMETER CALCULATION AT DIFFERENT ELEVATION
RADIAL POINT ELEVATION
3 5 8 3 POINT 3 POINT
90 degrees 180 degrees 315 degrees INSIDE INSIDE
REFERENCE inch RADIUS in. RADIUS in. RADIUS in. RADIUS in. DIAMETER ft.
REF. OFFSET COURSE 1 ‐ 1 FT. 359.417 359.274 359.826 359.506 59.918
COURSE 1 ‐ 3.75 FT. ELEVATION 359.778 359.778 359.778 359.778 59.963
COURSE 1 ‐ 6.75 FT. ELEVATION 359.658 359.706 359.850 359.738 59.956
COURSE 2 ‐ 8.75 FT. ELEVATION 359.706 359.562 359.874 359.714 59.952
COURSE 2 ‐ 11.3 FT. ELEVATION 359.634 359.370 359.922 359.642 59.940
COURSE 2 ‐ 14.2 FT. ELEVATION 359.682 359.154 360.114 359.650 59.942
COURSE 3 ‐ 16.2 FT. ELEVATION 359.586 359.178 360.090 359.618 59.936
COURSE 3 ‐ 18.9 FT. ELEVATION 359.418 359.274 360.090 359.594 59.932
COURSE 3 ‐ 21.8 FT. ELEVATION 359.418 359.274 360.210 359.634 59.939
COURSE 4 ‐ 23.8 FT. ELEVATION 359.418 359.586 360.234 359.746 59.958
COURSE 4 ‐ 26.75 FT. ELEVATION 359.514 359.658 360.186 359.786 59.964
COURSE 4 ‐ 29.5 FT. ELEVATION 359.826 359.778 360.210 359.938 59.990
MAXIMUM CALCULATED INTERNAL DIAMETER 59.990
MINIMUM CALCULATED INTERNAL DIAMETER 59.918
| 33 56 13.13-19 API 653 Inspection Report - Tank 400.pdf |
| Grissom Tank 400 Final API 653 Report.pdf |
| Grissom ARB Tank 400.pdf (p.1-18) |
| 400 Verticality & Roundness Report.pdf (p.19-34) |
| Drawing1 Layout1 (1).pdf (p.35) |
| Drawing1 Layout2 (1).pdf (p.36) |
| Drawing1 Layout2 (2) (1).pdf (p.37) |
File details come from the government source that posted it. Updated .