Attachment J7 - TO 3 FireiOS SOW.docx
DOCX document 18 KB Posted
- Attached to
- BARD Mobile Development Services IDIQ
- Solicitation number
- 030ADV24R0004
- Issued by
-
Library of Congress
About this file
This statement of work outlines agile software development services for the BARD Mobile application on the Amazon Fire OS platform. The contractor shall provide 12 four-week or 24 two-week sprints of development work to rebuild, enhance, and maintain the BARD Mobile application according to requirements. Development shall follow the NLS agile methodology, with the contractor responsible for baseline and target artifacts such as backlog, test, and release plans. The government will provide application code, API documentation, credentials for source code repositories and systems access. Quality control requirements adhere to the NLS agile methodology. Example sprints cover single sign-on implementation, migration to the BARD 2.0 API, upgrades for iOS 17 and iPadOS 17, user interface improvements, and release and bug fixing. The related federal contract opportunity is the Library of Congress' BARD Mobile Development Services IDIQ solicitation number 030ADV24R0004.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment J5-TO 1 iOS SOW rev.docx | DOCX document | |
| Attachment J6-TO 2 Android SOW rev.docx | DOCX document | |
| Amendment 0001_030ADV24R0004 0001.pdf | ||
| Attachment J4 - Question and Answers.pdf | ||
| Attachment J6 - TO 2 Android SOW.docx | DOCX document | |
| Attachment J4 - Questions_Template.xlsx | XLSX spreadsheet | |
| 030ADV24R0004.pdf | ||
| Attachment J1 - NLS Agile Methodology Guide.docx | DOCX document | |
| Attachment J5 - TO 1 iOS SOW.docx | DOCX document | |
| Attachment J2 - QASP.xlsx | XLSX spreadsheet | |
| Attachment J3 - Pricing Schedule 12.18.2023.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C.1. Background Contract number TBD provides software maintenance, bug fixes and development of new features for BARD Mobile for Amazon Fire OS platform in Performance Area C3.4. These services will be performed using an agile development methodology.
C.2. Scope The contractor shall perform software development activities involving the maintenance, enhancement, and development of Fire OS applications. Perform all software development work using the “SCRUM” based agile development methodology.
C.3. Requirements C.3.1. The contractor shall provide Agile software development services for 12 (twelve) four -week sprints or 24 (twenty four) two week sprints.
C.3.2. The contractor shall rebuild BARD Mobile for Fire OS.
C.3.3. The contractor shall implement features and enhancements defined in attachment A BARD Mobile Fire OS Requirements.
C.3.4. The contractor shall review and maintain issues logged in the NLS Bugzilla system for BARD Mobile Fire OS.
C.3.5. The software development lifecycle used by the contractor shall be governed by the Agile Development methodology as described in the statement of work and IDIQ ATTACHMENT J2 - “NLS Agile Methodology Guide".
C.3.6. The contractor shall develop the baseline artifacts (BSRS, BPBL, and BTM - see IDIQ ATTACHMENT J2 - “ NLS Agile Methodology Guide", section 2.5).
C.3.7. The contractor shall develop and release target artifacts (SRS, SRP, PBL, TM, ITTM, ATM -see IDIQ, ATTACHMENT J2 - “NLS Agile Methodology Guide", sections 2.5 and 2.8).
C.3.8. The contractor shall develop and test the software per the sprint release plan (SRP). The SRP is one of the release target artifacts created per IDIQ Attachment J2 in section 4.2.
C.3.9. The contractor shall develop and test of the software in accordance with the procedures defined in IDIQ, ATTACHMENT J2 - “NLS Agile Methodology Guide", sections 2.5 and 2.8 and sections 3, 4, 5 and 6.
C.4. Government Furnished Information.
NLS will provide the contractor the following:
C.4.1. The BARD Mobile additions and enhancement list defined in this Task Order Section J, ATTACHMENT J -“BARD Mobile Fire OS Requirements” C.4.2. User Accounts and related credentials to access the NLS BARD system.
C.4.3. NLS staff will provide an introduction to the BARD system. This will provide background information as to the functionality of the BARD system and how it can be used to debug BARD mobile.
C.4.4. Credentials of a GIT repository for software deliveries.
C.4.5. Existing source code for BARD Mobile Fire OS app.
C.4.6. Documentation for the BARD API.
C.5. Quality Control The contractor shall comply with the quality control requirements as specified in IDIQ Attachment J2, NLS Agile Software Development Methodology”, sections 3 and 6, and sprint defect remediation procedures as specified in section 7.
Example Sprint Plan (Submit proposed sprint plan with proposal)
1. Sprint 1: AAA/SSO Implementation – Part 1 (3/2024 – 4/2024) Implementation of Single-sign-on and AAA feature to the BARD Mobile application. Developer documentation for SSO and AAA will be provided.
2. Sprint 2: AAA/SSO implementation – Part 2 (4/2024– 5/2024) Continuation of AAA/SSO implementation.
3. Sprint 3: BARD 2.0 Migration – Part 1 (5/2024 – 6/2024) Migration to BARD 2.0 API and endpoints. BARD 2.0 API documentation will be provided.
4. Sprint 4: BARD 2.0 Migration - Part 2 (6/2024 – 7/2024) Continuation of migration work to transition into BARD 2.0.
5. Sprint 5: BARD 2.0 Migration - Part 3 (7/2024 – 8/2024) Additional sprint to finish BARD 2.0 migration and beta release.
6. Sprint 6: Bug fixes and overflow sprint (8/2024 – 9/2024) Fix bugs associated with AAA/SSO and BARD 2.0 API migration and perform overflow work.
7. Sprint 7: iOS 17 and iPadOS17 upgrade – Part 1 (9/2024 – 10/2024) Upgrade to support iOS17 and iPadOS17.
8. Sprint 8: iOS 17 and iPadOS17 upgrade – Part 2 (10/2024 – 11/2024) Continuation of iOS17 and iPadOS17 upgrade sprint.
9. Sprint 9: iOS 17 and iPadOS17 upgrade – Part 3 (11/2024 – 12/2024) Continuation of iOS17 and iPadOS17 upgrade sprint and beta release.
10. Sprint 10: Bug fixes and overflow sprint (12/2024- 1/2025) Fix bugs after upgrade to iOS17 and iPadOS17 and overflow sprint.
11. Sprint 11: UI Improvement (1/2025 - 2/2025) Improvement of UI features as listed in backlogged UI tasks, such as dark mode, contrast settings etc.
12. Sprint 12: Release and Bug Fixes (2/2025 - 3/2025) Final beta release with bug fixes.
File details come from the government source that posted it. Updated .