About this file

This is a Contractor Performance Self-Assessment form used to evaluate contractor performance on federal contracts. The form requires contractors to provide detailed narratives and ratings across ten evaluation areas, with the first six being mandatory and four being optional for additional areas.

The six primary evaluation categories are: Quality, Schedule, Cost Control, Management, Small Business Subcontracting, and Regulatory Compliance. Each category uses a standardized five-point rating scale consisting of Exceptional, Very Good, Satisfactory, Marginal, and Unsatisfactory, with an N/A option when not applicable. The form requires contractors to complete identifying information including contract number, order number, contractor address, period of performance being assessed, and contracting officer details. Contractors must provide substantive comments for each rating that explain the basis for their selection. The document includes detailed evaluation rating definitions that specify what constitutes each rating level and the supporting evidence required. For example, an Exceptional rating requires identifying multiple significant events benefiting the Government with no significant weaknesses, while a Satisfactory rating requires only minor problems with no significant weaknesses. Marginal and Unsatisfactory ratings must reference management tools such as deficiency reports that notified the contractor of contractual problems. The form concludes with signature blocks for the contractor representative completing the assessment, including name, title, phone, email, and date. Contractors are directed to use the Contractor Performance Assessment Reporting System (CPARS) guidance for additional assistance and to contact their Contracting Officer for submission instructions.

View the file

Other files for this federal contract opportunity

Other files attached to Training & TA Contract for State Councils on Developmental Disabilities, newest first.
File Type Posted
TTA for State Councils QA.docx DOCX document
Attachment J.2 Past Perf Questionnaire.pdf PDF
Solicitation 7571MN26R00028.pdf PDF
DDC TA Contract Logic Model_FY27-31.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR PERFORMANCE SELF-ASSESSMENT

INSTRUCTIONS: Provide a detailed narrative and rating for each of the relevant evaluation areas. Narratives must substantiate your rating selection. The contractor should use the Guidance for the Contractor Performance Assessment Reporting System (CPARS) to assist in preparation of the self-assessment. If further direction is required on how to complete this self-assessment or where to submit it, please contact your Contracting Officer.

CONTRACTOR CONTRACT

NUMBER

ADDRESS

ORDER

NUMBER

CITY / STATE/ ZIP

PERIOD OF

PERFORMANCE

BEING

ASSESSED

FROM TO

CONTRACTING

OFFICER’S REP

CONTRACTING

OFFICER

1. Quality N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

COMMENTS:

2. Schedule N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

3. Cost Control N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

4. Management N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory https://cpars.gov/documents/CPARS-Guidance.pdf

5. Small Business Subcontracting N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

6. Regulatory Compliance N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

7. Other Area:

N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

8. Other Area:

N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

9. Other Area:

N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

10. Other Area:

N/A Exceptional Very Good Satisfactory Marginal Unsatisfactory

Additional comments to support your response to any item above.

Completed by:

Name:

Title:

Phone Number:

Email Address:

Signature:

Date:

EVALUATION RATING DEFINITIONS

RATING

DEFINITION

NOTE

Exceptional Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

To justify an Exceptional rating, identify multiple significant events and state how they were of benefit to the Government. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

Very Good

Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

To justify a Very Good rating, identify a significant event and state how it was a benefit to the Government. There should have been no significant weaknesses identified.

Satisfactory Performance meets contractual requirements.

The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract/order.

There should have been NO significant weaknesses identified. A fundamental principle of assigning ratings is that contractors will not be evaluated with a rating lower than Satisfactory solely for not performing beyond the requirements of the contract/order.

Marginal Performance does not meet some contractual requirements. The contractual performance of the element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions. The Contractor's proposed actions appear only marginally effective or were not fully implemented.

To justify Marginal performance, identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the Government.

A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g., management, quality, safety, or environmental deficiency report or letter).

Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

To justify an Unsatisfactory rating, identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the Government. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g., management, quality, safety, or environmental deficiency reports, or letters).