This document outlines requirements for a Design-Build Consultant Team to assist the Federal Aviation Administration in developing a Request for Proposal and selecting a Design-Builder for a new Airport Traffic Control Tower at David Wayne Hooks Airport. Key details include:

  • The Design-Build Consultant Team will aid in developing the technical scope of work, performance criteria, and evaluation factors to be included in the Request for Proposal. They will also advise FAA during the source selection process and facilitate partnering meetings between FAA and the selected Design-Builder.

  • Deliverables include an initial, draft, and final Request for Proposal. The schedule allocates 183 calendar days from notice to proceed to complete the work, and allows for travel to meetings in Fort Worth, Texas and site visits.

  • Qualifications for Consultant Team members include a minimum of seven years' design-build experience, with at least one member holding the Design-Build Institute of America's certification and two having federal government project leadership experience. One must have an active professional license.

  • An optional scope of work involves evaluating performance of the Design-Builder and FAA's implementation of design-build best practices during construction of the air traffic control tower.

View the file

Other files

File Type Posted
SIR 697DCK-24-R-00018.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
KEY PERSONNEL EXPERIENCE.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace ATCT Design Build Consultant– Professional Services in Development of Performance and Selection of Design-Builder.

The Federal Aviation Administration (FAA) has a requirement for a Design-Build (DB) Consultant Team to assist the FAA with the Technical Scope of Work and Source Selection for the for new Airport Traffic Control Tower (ATCT) at David Wayne Hooks Airport (DWH). The delivery method is Design Build (DB) utilizing Best Value. This contract supports FAA’s goal to establish multiple ATCTs.

Siting for the new ATCT has been completed. The approved siting report establishes the finish floor elevation for the cab floor for optimum visibility to aircraft movement areas. Currently, we are waiting on the approved requirements document, before we can hire a Design Builder.

The Design Build (DB) Consultant Team has the responsibility of assisting the FAA in the development of the Technical Scope of Work and establishing performance criteria that meets the current Design Build Institute of America (DBIA) best practices or the DWH ATCT project.

FAA is open to “stipulated sum”, “award fee” etc.

The Design Build Consultant Team will help in the development of the Request for Proposal, the Evaluation Criteria, and the Source Selection Process. Source Selection must follow DBIA best practices. One bid option is included to document performance of both the Design-Builder and FAA implementation of Design Build Best Practices for the DWH Project.

DB Request for Proposal (RFP)

One (1) Request for Proposal is required as final deliverables. The FAA will provide a 10% Standard Design for the DWH ATCT.

1. DWH ATCT cab floor will be below 119 FT AGL. The 10% design is available, but we are waiting on the Requirements Document. The Requirements Document is under development and is anticipated ready for distribution in January 2024. Elements specific to the site: foundations, sitework, HVAC loads, access, utilities, site layout, fire protection, etc. require site adaptation. Certain aspects of Architecture, Mechanical, Electrical, and Structure will be more mature and have less flexibility in options. ATCTs at or below 119 FT AGL will have the following characteristics:

• 440 SF Tower Cab

• Occupied Shaft

• Single Elevator and Single Exit Stair

• Space Programming is provided with the standard

• Must be site specific for Tomball, Tx (DWH)

2. The duration is estimated to be 2yrs, with the option to extend the duration as needed. It is assumed that it will take 1 year for procurement, and 1 year for design.

Award of a construction project is prohibited until the Environmental Assessment is complete. FAA anticipates the DWH ATCT will fall in the programmatic Environmental Assessment (EA). Coordination with the FAA Environmental Specialist will be required to determine timeline to complete the EA. Construction costs must be separated from design costs.

Performance Criteria

The DB Consultant Team will aid the FAA in development of the Technical Scope of Work and performance criteria and provide consultation to the FAA during the Design Builder competition. The DB Consultant Team must accommodate FAA’s schedule to attend meetings, review documents, and provide feedback in a timely manner. The DB Consultant Team is responsible for incorporating the following items below into the Design Build (DB) Request for Proposal (RFP):

1. Available space programming information (space adjacencies, size, configuration and site-specific data such as but not limited to seismic, wind loading, geotechnical, etc for DWH.

2. Consistent with the Department of Transportation (DOT) sustainability goals, the FAA requires all ATO new construction, major renovation, or repair and alteration of Agency buildings to comply with the Guiding Principles for Sustainable Federal Buildings and Associated Instructions, dated December 2020 (located at https://ksn2.faa.gov/AJW/AJW244C/references/SitePages/Home.aspx)

3. FAA Security requirements individually identified by project

4. Identifying and mitigating risks inherent in the Design Build best practices

5. FAA Terminal Facilities Design Standard, Version 2.1.1. Some prescriptive requirements may include, but are not limited to the following:

a. FAA Order 002F Drawing Standards

b. Minimum FAA Building Information Modeling (BIM) Requirements

c. FAA Order JO 1053.3, Implementation Date 03/12/2015, “Air Traffic Organization

Energy Efficient and Sustainable New Construction and Major Renovation”

d. New Facility Security Requirements per FAA Order 1600.69 latest version

e. Design criteria and guidelines for HVAC systems and redundancies for critical spaces per FAA A/E Project Manual

f. The ATCT requires a single stair as the primary means of egress for the ATCT’s with cab floor elevations less than 120 FT AGL

g. Single elevator is required for ATCT cab below 119 FT AGL

h. FAA-STD-019, Lightning and Surge Protection, Grounding, Bonding and Shielding

i. FAA-C-1217, Interior Electrical Work Specification

j. FAA-C-1391, Installation, Termination, Splicing, and Transient/Surge Protection of

Underground Electrical Distribution System Power Cables

k. IBC high rise requirements apply for all ATCTs over 55FT AGL in overall height

l. Class A Fire Alarm System as defined in NFPA 72

m. Airport Traffic Control Towers shall be designed in accordance with the requirements of the International Building Code (2021 edition or latest at time of design start). A single exit may be permitted for ATCTs with Control Cabs less than 1,500 sq ft in area, and occupant loads on each floor less than 15 persons.

ATCTs shall be constructed in accordance with Section 412 of the IBC. ATCTs in excess of 75 height shall incorporate portions of IBC Section 403 for High Rise Structures as referenced by Section 412. ATCTs with occupied floors in excess of 35 feet in height shall be provided with automatic fire suppression. ATCTs with occupied floors in excess of 30 feet shall be provided with Class I standpipe system with design coordinated with local responding Fire Department or approved by AHJ for non-federal properties. Unless modified by Section 412, ATCTs in excess of 75 feet in height shall comply with other requirements for high rise structures. ATCT facilities shall comply with all other IBC and IFC requirements not specified here for primarily Group B (Business) occupancy with other incidental use occupancies as classified in the code. Paths of egress shall conform to NFPA 101 requirements. Other fire protection features including doors, barriers, suppression, detection and alarm systems shall comply with applicable NFPA standards.”

Source Selection Criteria and Competition

The DB Consultant Team will assist the FAA in the development of the Request for Proposal (RFP), Evaluation Criteria and the Source Selection Process. The DB Consultant Team may be required to attend meetings and presentations during the competition as advisors. The DB Consultant Team will advise the FAA on, but is not limited to the items listed below:

1. DBIA concepts and practices;

2. Evaluation criteria in regards to design, technical approach, project management, schedule, cost and life cycle cost analysis;

3. Develop questions for Offerors down selected to interviews (if necessary); and

4. Review of Offerors’ proposals.

After award the DB Consultant Team must facilitate a formal partnering meeting between FAA, stakeholders, and awarded Design-Builder along with an owner risk workshop to assist in identifying and assigning risk to awarded Design-Builder and owner.

Deliverables

The following deliverables are required:

1. Initial RFP – Developed based on available data, and suggested performance requirements.

2. Draft RFP – Incorporates FAA input.

3. Final RFP – Incorporates the delivery of the 10% Standard Design by the FAA

Terminal Program Office for ATCTs with cab floors below 119 FT AGL.

Schedule – DWH ATCT

Activity Calendar

Days

NTP 1

Initial Scope 60 FAA Review 15 Draft Scope 45 FAA Review 15 Final Scope 30 FAA Review 10 Complete 7 Total Calendar 183

Travel

1. Request for Proposal – Assumes one 2-day meeting in Fort Worth, Tx to discuss the Initial

RFP.

2. Source Selection - Assumes up to six 2-day meetings in Fort Worth to review bidders, answer bid questions, and assist in meeting with bidders.

3. Bid Option 1 - Assumes six trips to DWH site.

Qualifications:

The Design Build Consultant Team must include at minimum of two (2) engineers and no more than four (4) engineers with the minimum qualifications:

1. All Key Personnel must clearly demonstrate a minimum of seven (7) years in Design Build experience in establishing scopes of work and assisting Owners in selection of the Design Build Teams.

2. At least one (1) Key Personnel must be Design Build Institute of America, DBIA, certified.

3. At least two (2) Key Personnel must have leadership experience in the Design Build Selection Process with Federal or Government projects.

4. At least one (1) Key Personnel must have an active professional architectural or engineering license.

Option 1: Construction Services

Work will include, but is not limited to the following:

1. Evaluate and document performance of both the Design-Builder and FAA for implementing Design Build Best Practices for the DWH Project

2. Attend site visits and meetings with the FAA Team and DB Contractor.

3. Coach FAA Team for DBIA Best Practices

4. Evaluate Project Performance both FAA and DB Contractor

5. Trend analysis and reporting for changes and project issues.

6. Review Request for Proposal against project progress for lessons learned and recommend revisions.

DB Request for Proposal (RFP)
Performance Criteria
Source Selection Criteria and Competition
Deliverables
Schedule – DWH ATCT
Travel