Statement of Work
The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required service shall be in accordance with the requirements as described herein and on attached contract documents.
3.1 Background:
The USDA-ARS Wenatchee branch located at 1104 N Western Ave, Wenatchee WA requires installation of HVAC, electrical, and lighting improvements for the conversion of the two office spaces (rooms 105 and 107 in the shop building) into a clean room for tissues culture.
3.2 Contractor shall provide the installation of a high efficiency minisplit heat pump on the north side of the shop building, two highwall minisplit heads/assemblies located on the north wall of each room, and associated copper lines and fittings between them
3.2.1 Contractor shall add new electrical circuits, rerouting ~60A to a new panel outside these rooms to a. reduce likelihood of power issues from the existing wiring and allow for sufficient power and outlets (including a 240V for larger equipment) to run refrigeration and clean room equipment and b. have a circuit with sufficient amperage for the new minisplit installation
3.2.2 Contractor shall convert the outlets in the room, as many don’t have space for grounded plugs
3.2.3 Contractor shall replace lighting fixtures in both office rooms, removing and disposing of the 4’ vaportite fixtures, and installing low profile LED fixtures.
3.2.4 Work shall be conducted during normal daily working hours between 9 am and 5:30 pm.
3.3 Contractor will provide materials, labor, equipment, and all associated services necessary to complete project.