These are Preliminary Specifications for the USS CURTIS WILBUR (DDG 54) detailing multiple specific maintenance and repair work items for the ship. The documents cover five distinct work items:
- Antenna Platform Perforated Under Plate Installation (Item 179-11-001): Involves removing and installing a 6 SF perforated aluminum plate, 10 nuts, washers, and studs at the 07 Level, with requirements for containment, visual inspection, and surface restoration. 2. Lagging and Insulation Replacement (Item 256-11-001): Requires removing and replacing damaged insulation throughout the ship, with specific guidelines for installation, marking, and documentation. 3. Cosmetic Polymeric Covering System Repair (Item 634-10-001): Involves repairing a 100 SF deck covering section in a passage area, including removal of existing coating, joint inspection, and non-skid strip installation. 4. Trunk Safety Net Weight Testing (Item 612-21-001): Covers static load testing of safety nets in multiple ship locations, including installation of new label tags and documentation. 5. Gas Turbine Generator Seawater Cooling Pump Rigging Services (Item 980-11-001): Provides crane and rigging services for removing and installing a seawater circulation cooling pump in the Generator Room.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment IV Warranty Tracking Information.pdf | ||
| Att III Request for Information Form.pdf | ||
| N6264925RA067.pdf | ||
| Attachment V Source of Repair Instruction.pdf | ||
| Attachment II Price Proposal Form N6264925RA067.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRELIMINARY SPECIFICATION
SHIP: USS CURTIS WILBUR (DDG 54) ITEM NO
COAR: PCN
CMP:
PLANNER
179-11-001
CEO3 -L032
NONE
LOFTIS, OLEN
ANCHETA, FREDDIE
1. SCOPE:
1.1 Title: Antenna Platform Perforated Under Plate; install
1.2 Location of Work:
1.2.1 TBD Platform, 07 Level, Frames ### - ###, Underside
1.3 Identification:
1.3.1 Quantity (6 SF), Perforated Plate, 16 Gauge, Aluminum, QQ- -A-
250/8F, Grade 5052, H32, Sheet 6E-2-3C, Item Number 8000 (Page 49) of 2.2
1.3.2 Quantity (10 EA), Nut, Self locking, 5/8 -llUNJC-3B, Steel Carbon, MIL-N-25027, Part Number 00050 of 2.3
1.3.3 Quantity (10 EA), Washer, Flat Round, 5/8 by 0.063 Inch Thick, Steel Carbon, FF-W-92B, Type A, Grade 2, Part Number 00051 of 2.3
1.3.4 Quantity (10 EA), Stud, Welded, 5/8 Inch Diameter by 1-1/2 Inch Long, Steel Carbon, MIL-S -24149/lB, Type One, Class One, Part Number 00054 of 2.3
2. REFERENCES:
2.1 Standard Items, FY25 (OH-i)
2.2 171-6218960 Rev AA, Unit Strl Arr Dwg Assy Unit 4260
2.3 150-622ll38PL Rev 157, Procurement Material List Title
3. REQUIREMENTS:
3.1 Install and maintain steel tube and clamp type staging at location listed in 1.2 in accordance with 2.2 as directed by the
SUPERVISOR, with each sufficient level and projection to safely reach and perform requirements of this Work Item.
3.1.1 Contractor must install Containment to fully enclose the equipment listed in 1.3.2 to ensure no harmful contaminants are allowed into the area which would cause damage to Ship during replacement.
(V) (G) "JOINT INSPECTION"
3.2 Accomplish a visual inspection of each perforated under plate for the antenna platform located in 1.2, for structural integrity, deterioration, pitting, each crack, and area of damage or distortion, and to determine required repairs, using 2.2 for guidance.
Report: VISUAL INSPECTION RESULTS (MC) - WORK ,' ,''l2'' COMPLETE + 0j days
SSP: YOKO-006-25 1 of 2 ITEM NO: 179-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
SHIP: USS CURTIS WILBUR (DDG 54)
3.2.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.1 to the SUPERVISOR.
3.3 Remove existing and install new perforated plate, each nut, washer, and stud listed in 1.3 and located in 1.2, using 2.2 and 2.3 for guidance, as designated by the SUPERVISER.
3.3.1 Restore each mating surface exposed by removal. Repair by removing each high spot, burr, abrasion, and foreign matter, where removal can be accomplished by a hand tool.
3.3.2 Chip and grind each surface flush in way of each repair.
3.3.3 Template exact size, configuration, and location from each existing shipboard condition.
3.4 Accomplish the requirements of 009-32 of 2.1, for each new and disturbed surface.
4. NOTES:
4.1 Ship's Force has tentatively offered to provide material if Contractor unable to obtain.
5. GOVERNMENT FURNISHED MATERIAL(GFM)
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: YOKO-006-25 2 of 2 ITEM NO: 179-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, SHIP: USS CURTIS WILBUR )DDG 54) ITEM NO: 256-11-001
COAR: 26 PCN: ES01 -L048
:1 CMP: NONE
PLANNER: LOFTIS, OLEN
1. SCOPE:
1.1 Title: Lagging and Insulation; replace
1.2 Location of Work:
1.2.1 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY25 CH-l)
2.2 508-6218533 Rev V, Mchry Piping & Eqpt Insulation and Lagging Schedule
2.3 59086 -RK-STM-010/CH-505 Rev 5, Piping Systems
2.4 Lagging Priority List, Ship Force provided
3. REQUIREMENTS:
3.1 Remove existing damaged and deteriorated insulation and lagging identified in 2.4, using 2.2 and 2.3 for guidance, as designated by the
SUPERVISOR.
3.2 Accomplish the requirements of 009-11 of 2.1 for installation of new insulation and lagging to accomplish work identified in 2.4, as directed by the SUPERVISOR.
3.2.1 Accomplish the requirements of 009-32 of 2.1 for new
insulation, lagging, and reusable covers to match surrounding areas.
3.2.2 Accomplish the requirements of 009-32 of 2.1 for each surface to be insulated with the exception of non-ferrous and corrosion resistant steel (CRES) piping, plating, and vent ducting.
3.3 Template exact size, configuration, and location from each existing shipboard condition.
3.3.1 Apply designatidh, markings and color coding on new and disturbed lagging and insulation in accordance with Paragraph 505-7.8 of 2.3.
3.4 Submit one legible copy, in hard copy or approved transferable media, of a weekly report to document labor and material expenditures to the SUPERVISOR.
3.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 Ship's Force has provided prioritized lagging list for bidding purposes. Additional Lagging may be required and must be provided via the
SSP: YOKO-006-25 1 of 2 ITEM NO: 256-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, SUPERVISOR.
5. GOVERNMENT FURNISHED MATERIAL(GFM)
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: YOKO-006-25 2 of 2 ITEM NO: 256-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, SHIP: USS CURTIS WILBUR (DDG 54) ITEM NO: 612-21-001
COAR: 26 PCN: See Attachment A
I CMP : NONE
PLANNER: LOFTIS, OLEN
ANCHETA, FREDDIE
1. SCOPE:
1.1 Title: Access Trunk Safety Net Weight Test; accomplish
1.2 Location of Work:
1.2.1 Access Trunk (3-42-1-T)
1.2.2 Escape Trunk (3 -97 -l -T)
1.2.3 Escape Trunk (2 -322 -l -T)
1.2.4 Access Trunk (3 -322 -l -T)
1.2.5 Escape Trunk (2-334-2-T)
1.2.6 Engine Room No 2 (4-254-0-E)
1 .3 Identification:
1.3.1 Quantity (3 EA), Trunk Safety Net Assembly, DHLSD/AFOO4, DHLSD/AFOO5, Plan 9B -A, Sheet 9A and 9B of 2.2
1.3.2 Quantity (3 EA), Trunk Safety Net Assembly, DHLSD/AF015, DHLSD/AF016, DHLSD/AF017, Sheets llA through 11C of 2.2
1.3.3 Quantity (2 BA), Trunk Safety Net Assembly, DHLSD/AF019, Plan 13A-A, Sheet 13A of 2.2
1.3.4 Quantity (3 EA), Trunk Safety Net Assembly, DHLSD/AFOO1, Plan l2A-A, Sheet 12A of 2.2
1.3.5 Quantity (2 EA), Trunk Safety Net Assembly, DHLSD/AF014, Plan l4A-A, Sheet l4A of 2.2
1.3.6 Quantity (One BA), Trunk Safety Net Assembly, Between GTM 2A and 2B, DHLSD/AFOO1, Plan 12A-A, Sheet l2A and Sheet l2B of 2.2
2. REFERENCES:
2.1 Standard Items, FY25 (CH-l)
2.2 612-6566603 Rev AA, Fab & Instl of Safety Nets (Trunks)
2.3 2C6l2Cl03 Rev G/3, Lifeline, Liferail and Safety Net 2C6l2C103 Strength and Load Test
2.4 8100-1312-0254 Rev E, Access Trunk Safety
2.5 804-5184163 Rev B, Nets, Safety, Trunk
3. REQUIREMENTS:
(I) (G) "STATIC LOAD TEST"
3.1 Accomplish the requirements of 2.3, for each trunk safety net listed in 1.3, and located in 1.2, using 2.2, 2.4, and 2.5 for guidance.
3.1.1 Install new each label tag on each safety net in accordance
SSP: YOKO-006-25 1 of 3 ITEM NO: 612-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, with 2.2.
3.1.2 Submit one legible copy, in hard copy or approved
transferrable media, of each completed data sheet of 2.2 to the
SUPERVISOR.
3.2 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None
5. GOVERNMENT FURNISHED MATERIAL(GFM)
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: YOKO-006-25 2 of 3 ITEM NO: 612-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, Attachment A
PCN Identification
CGO1 -2003 SAFETY NET WEIGHT TEST
EA01 -7805 SAFETY NET WEIGHT TEST
CFO3 -2637 SAFETY NET WEIGHT TEST
CEO3 -4773 SAFETY NET WEIGHT TEST
CEO1 -4835 SAFETY NET WEIGHT TEST
EMO2 -5124 SAFETY NET WEIGHT TEST
SSP: YOKO-006-25 3 of 3 ITEM NO: 612-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, SHIP: USS CURTIS WILBUR (DDG 54) ITEM NO: 634-10-001
COAR: 26 PCN: SSO2 -2307
CMP: NONE
_____________________________ PLANNER: LOFTIS, OLEN
ANCHETA, FREDDIE
1. SCOPE:
1.1 Title: Cosmetic Polymeric Covering System; repair
1.2 Location of Work:
1.2.1 Passage (02-154-2-L)
1.3 Identification:
1.3.1 Quantity (100 SF), Cosmetic Polymeric )PRC) Deck Covering, 10' x 10' Section of Deck Covering in Front of Wardroom
2. REFERENCES:
2.1 Standard Items, FY25 )CH -1)
2.2 634-6219440 Rev N, Deck Covering Details
2.3 631-6219391 Rev T, Paint Schedule
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-26 of 2.1, including Attachment C, for the removal of existing and installation of new cosmetic polymeric deck covering system (PRC), for deck located in 1.2 as identified in 1.3.
(V) )G) "JOINT INSPECTION"
3.1.1 Accomplish joint inspection with SUPERVISOR following the removal of existing PRC coating once substrate surface is accessible.
3.1.2 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 6, Columns A and B for surface preparation.
3.1.3 Accomplish the requirements of 009-26 of 2.1, including Attachment G for the installation of peel and stick non-skid strip.
3.2 Accomplish the requirement of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM)
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
SSP: YOKO-006-25 1 of 2 ITEMNO: 634-10-001
EXPORT CONTROLLED DATA: This document Contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,
1. None.
SSP: YOKO-006-25 2 of 2 ITEM NO: 634-10-001
EXPORT CONTROLLED DATA: This document Contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, SHIP: USS CURTIS WILBUR (DDG 54) ITEM NO: 980-11-001
COAR: 26 PCN: EMO4 -5029
BWST FILE NO: 000-001 CMP: NONE
REVISED: 05 APR 2019 PLANNER: ANCHETA, FREDDIE
1. SCOPE:
1.1 Title: Number 3 Gas Turbine Generator Seawater Cooling Pump Rigging Services; provide
1.2 Location of Work:
1.2.1 Generator Room (3-370-0-E)
1.3 Identification:
1.3.1 Quantity (One EA), Pump Assembly, SSGTG No 3 Seawater
Circulation Cooling Pump, PMPCTFGL, l80GPM, 35P51, 3577RPM MCC VLT, APL: 017030718, Mfr: Carver Pump Company Inc, MFR ID: 9N-3500-10, MIL-P-17840
2. REFERENCES:
2.1 Standard Items, (FY25 CH-l)
3. REQUIREMENTS:
3.1 Provide crane and rigging services when directed by the SUPERVISOR, to support removal of existing equipment identified in 1.3 and located in
1.2 as designated by the SUPERVISOR.
3.1.1 Receive new equipment via the SUPERVISOR and accomplish a visual inspection for general condition and completeness.
3.1.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.1.1 to the SUPERVISOR.
3.2 Provide crane and rigging services to transport and support installation of equipment received in 3.1.1 as designated by the
SUPERVISOR.
3.3 Accomplish the requirements of 009-32 of 2.1 for each disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM)
5.1 LLTM:
TOTAL NATIONAL
QUANTITY PIECE REF STOCK REQ
PROVIDED NAME Of PART NO. NO. NO. PARA NO.
Pump Assembly, APL: 017030718, 9N-3500-
1. 1 AY MIL-P-17840 10
3.1.1
5.2 PUSH MATERIAL: pa
SSP: YOKO-006-25 1 of 2 ITEM NO: 980-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: YOKO-006-25 2 of 2 ITEM NO: 980-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR) . This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,
File details come from the government source that posted it. Updated .