This is a WebAIM Short Form Task Group Instruction (TGI) document for naval ship maintenance work on USS JOHN FINN (DDG-113). The document, dated 30-MAY-2026, contains instructions for installing 12 foundations for the MK59 Decoy Launcher system on the vessel's 02 Level Weather deck area, spanning frames 200-218 (both port and starboard sides) and frames 278-292 (port side), with additional work locations in the Fan Room Pressure Zone, Deck Gear Locker, Replenishment Gear Locker, and Director Equipment Room.
The work scope requires installation of each new foundation in accordance with referenced technical drawings and standards, submission of alignment data reports to the supervisor, and accomplishment of surface treatment requirements per naval specifications. Work involves structural fabrication (handled separately by TGI No. 38BC147405F03), with SRF-JRMC providing government-furnished materials and service work including crane and rigging services, electrical utilities, low-pressure air/water/steam supply, safety inspections, gas-free inspections, and quality assurance inspections. The task involves multiple skilled trades including structural fabrication, welding, electrical work, installation, painting, and repair work. Material requirements include adhesive (12 per page, stock number 8040 014175562) ordered for the contractor. Work start and completion dates are referenced in the 6J1 POP List_Bundle #3. The document notes a potential asbestos hazard during initial conditions and contains references to 11 technical drawings, manuals, and specifications for alignment verification and installation control procedures.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
30-MAY-2026 1034
20.15.6.0.9333 (July 2025) ICN: 38BC147405 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA 30088K MK59 FDN AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - (RE) S/A 30088K, INSTALL FOUNDATION FOR MK59 DECOY LAUNCHER
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 5
EXSAZCF3
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
WATANABE, KAZUMI 231A 3152434518 27-MAY-2026
APPROVED BY: CODE: PHONE: DATE:
NAKAMURA, YUUJI 231A 3152436041 28-MAY-2026
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZCF3
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
474G1105 0
1. SCOPE/PURPOSE:
1.1 Title: S/A 30088K, Foundation for MK59 Decoy Launcher; install
1.2 Location of Work:
1.2.1 02 Level Weather, Frames between 200 and 218, Starboard (Stbd)
1.2.2 02 Level Weather, Frames between 200 and 218, Port
1.2.3 02 Level Weather, Frames between 278 and 292, Port
1.2.4 Fan Room Pressure Zone No. 2 (01-200-2-Q)
1.2.5 Deck Gear Locker (01-276-2-A)
1.2.6 Replenishment Gear Locker (01-201-1-A)
JRMC ONLY - Combat Systems Alignment Required, TGI Short Form
30-MAY-2026 1034
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC147405 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA 30088K MK59 FDN AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - (RE) S/A 30088K, INSTALL FOUNDATION FOR MK59 DECOY LAUNCHER
FOUO Pg 2 of 5
CU PHASE DESCRIPTION (Cont.)
1.2.7 06 Level Weather, Frame 150, Center
1.2.8 Director Equipment Room No. One (05-131-0-Q)
1.3 Identification:
1.3.1 Quantity (12 EA), Foundation for MK59 Decoy Launcher on Platform, 02 Level Weather, Port and Stbd
Remarks: See Plan 16-5A, Plan 23-5A, and Plan 30-5A of Ref. No. 3 for material and detail
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard
1.6 Contractor work start date: **See 6J1 POP List_Bundle #3
1.7 Contractor work completion date: **See 6J1 POP List_Bundle #3
2. PROCEDURE:
2.1 Install each new foundation listed in 1.3.1 in accordance with Ref. No. 3 through Ref. No. 6, using Ref. No. 7 through Ref.
No. 11 for guidance.
2.1.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of alignment data of each foundation to the SUPERVISOR.
2.1.2 Accomplish the requirements of 009-012 of Ref. No. One, including Table 2, Column(s) A and D, Lines One through 7.
2.2 Accomplish the requirements of 009-032 of Ref. No. One for each new and disturbed surface.
2.3 Notes:
2.3.1 Planner: Code 231A K. Watanabe, 243-4518
Planner: Code 233 S. Sato, 080-9350-1452
2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
2.3.3 Fabrication of new foundation listed in 1.3.1 will be accomplished by TGI No. 38BC147405F03 (SRF-JRMC TGI).
2.3.4 JCN EXSA-ZCF3 is related to this TGI.
2.4 Government Furnished Material (GFM):
2.4.1 SRF-JRMC will provide GFM listed in the Material List.
2.5 SRF-JRMC will provide the following service work: (TGI No. 38BC147405S03).
30-MAY-2026 1034
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC147405 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA 30088K MK59 FDN AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - (RE) S/A 30088K, INSTALL FOUNDATION FOR MK59 DECOY LAUNCHER
FOUO Pg 3 of 5
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
2.5.1 [C740] Crane and crane rigging service.
2.5.2 [X99E] Utility service, electrical.
2.5.3 [X99M] Utilities service, including low pressure air supply, water supply, and steam supply.
2.5.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.5.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.5.6 [C133] QA Inspection for (G) symbol(s).
30-MAY-2026 1034
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC147405 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA 30088K MK59 FDN AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - (RE) S/A 30088K, INSTALL FOUNDATION FOR MK59 DECOY LAUNCHER
FOUO Pg 4 of 5
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
3 DWG 100-8991124 LAUNCHING SYS DECOY
MK59 MOD1 STRUC & MODS
& ML
A Y ALL
4 LAR
30088/DDG113/1236
DDG 113 LAUNCHER
FOUNDATION
- Y ALL
5 LAR
30088/DDG113/1234
DDG 113 LAR DRAWING
8991124
- Y ALL
6 LAR
30088/DDG113/1237
SPECIAL NOTES AND
LAUNCHER MAINT
ENVELOPES RECTIFY RLAR
1234508 & 1234988
- Y ALL
7 DWG 150-7060433 UNIT STRL ARR DWG ASSY
UNIT 4410
D Y 3-
8 DWG 150-7060437 UNIT STRUCTURAL ARR
ASSY UNIT 4610
H Y 3-
9 DWG 8730437 INSTALLATION CONTROL
DRAWING FOR MK 59 MOD 1
DECOY LAUNCHING SYSTEM
- Y ALL
10 TM SW225-CH-CSA-
CSAM FOR DDG51 CLASS;
ALIGNMENT VERIFICATION &
CORRECTIVE ALIGNMENT
PROCEDURES
08 N
11 TM SW225-A0-MMA-
COMBAT SYSTEM
ALIGNMENT THEORY
5 N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 SFTR HRs, WELD HRs, ELEX HRs, INSL HRs, PNTR HRs, RGRS
HRs, QA HRs
22/KE PC 0 0 N
2.2 PNTR HRs, QA HRs 22/KE PC 0 0 N
Structure Work CFM: for all paints, thinner, insulation, tape, cap, adhesive, pin, firewatch cost, asbestos sampler and analysis cost, and misc such as electrode, gases, covering material, and other consumable.
22/MQ CS 0 0 N
Electronics Work CFM: for MISK. 22/MQ CS 0 0 N
Process Funding Document 10/CT OM 0 0 N
MATERIAL LIST
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38BC147405 KEY OP: A09
30-MAY-2026 1034
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC147405 KeyOp: A09
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SA 30088K MK59 FDN AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: F/O - (RE) S/A 30088K, INSTALL FOUNDATION FOR MK59 DECOY LAUNCHER
FOUO Pg 5 of 5
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
300 M ADHESIVE, ORIG: C233,
S.SATO, 080-9350-1452
ORDERED FOR KTR
9B 8040 014175562 NA 4 N 61405090 12/PG