United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
REPAIR ROOF (Building 56)
Subtropical Horticulture Research Center 13601 Old Cutler Road Miami, Florida 33158
Prepared by Jim Glick
Reviewed by Everett Wilson
March 10, 2020
Statement of Work USDA, Agricultural Research Service
Table of Contents
1. Scope of Work 3
4. Utilization of Bio-Based Products 5
5. Safety 5
6. Contractor Requirements 6
7. Documentation Requirements 7
8. General Requirements 7
9. Period of Performance 7
10. Guaranty 8
11. Project Contacts 8
12. Floorplan 9
1. Scope of Work
The contractor shall provide all professional services necessary to supply and install a new roof to current code requirements on building 56 at the USDA, ARS, Subtropical Horticulture Research Center, 13601 Old Cutler Road, Miami, Florida 33158, and provide a detailed proposal with a cost breakdown for the project.
The contractor shall include all services and field labor, equipment (including cranes and rigging equipment), materials, testing and personal protective equipment necessary to perform the work. No Government equipment will be available for use by the contractor.
1.1. Base Bid
The contractor shall provide a detailed proposal and cost breakdown for the entire project as specified in this statement of work.
1.2. Site Visit
(A site visit will be scheduled at a later date after the Corona Virus (COVID-19) Pandemic is under control and we are once again allowed to have visitors on our premises.)
Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing first-hand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.
Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be completed at www.sam.gov/portal/public/SAM http://www.sam.gov/portal/public/SAM
2. Codes and Standards
Applicable Codes and Standards apply and are not limited to the following
ANSI - American National Standards Institute.
ASME - American Society of Mechanical Engineers.
NEC - National Electrical Code, NFPA 72.
OSHA - Occupational Safety and Health Administration
ADA – Americans with Disabilities Act
All work must meet ARS 242.1M “ARS Facilities Design Standards” for the defined scope of this project in addition to meeting all Local, State and Federal codes, and latest IBC codes. The document may be found at https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf.
3. Project Summary
The project consists of the following elements:
1) Set up work area with barriers and safety lines.
2) Protect ground area structures, equipment, plants and vegetation along the perimeter of the roof to protect against falling material during roof removal.
3) Remove all existing roof systems down to the wood deck.
4) Remove any trim, flashing or siding over existing soffits and fascia.
5) Remove all existing gutters, downspouts, splash blocks
6) Inspect wood deck. Repair as needed before installing new roof.
7) Inspect soffits and fascia. Repair as needed before installing new roof.
8) Inspect all roof deck fasteners and replace with new fasteners that meet
Florida building code requirements as required.
9) Inspect roof trusses for hurricane straps. Install hurricane straps per code requirements as needed.
10) Furnish and install primary and secondary water barrier system over entire roof per code requirements as needed.
11) Furnish and install metal roofing (1.5” seamed) that meets Florida building code. Roof color to match surrounding buildings, samples to be submitted and approved by Administrative Officer (AO) before ordering.
https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf
12) Furnish and install all necessary metal flashings and trim needed to complete a weather tight roof system.
13) Furnish and install metal flashing and covering of soffits and fascia.
14) Furnish and install new gutters, downspouts and splash blocks.
The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to daily operations and research programs.
4. Utilization of Bio-Based Products
The contractor shall utilize products and material based from bio- based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:
www.biopreferred.gov
5. Safety
The contractor will submit a Site Safety Specific Plan (SSSP)/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.
Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities and personnel.
http://www.biopreferred.gov/
6. Contractor Requirements
The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.
The project work shall be performed per the following guidelines:
1) Contractor will verify all dimensions and existing site conditions prior to beginning work.
2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.
3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site on a weekly basis.
4) Contractor is required to manage the project and consult with the Government prior to beginning all work phases.
5) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.
6) Contractor will provide daily reports of work performed to the AO and weekly status updates to the EPM.
7) Contractor must have a superintendent on the jobsite when crews are performing the installation work.
8) Contactor will provide their own restroom facility.
9) Contractor to include commissioning of the new system
All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.
7. Documentation Requirements
7.1. Material Submittals
The contractor shall submit for approval all documents necessary to describe the complete design intent to successfully complete and deliver a fully functioning system. Electronic submittals on all equipment and materials used on this project shall be submitted to the EPM, AO, and CO noted in this document. All applicable products will have the Miami Dade Notice of Acceptance highlighted or otherwise noted.
7.2. Pre-Construction Submittals
Prior to construction activities beginning the following submittals must be provided to the AO and EPM for approval.
1. Project Schedule (including daily work start/stop time)
2. Site Specific Safety Plan (SSSP) / Accident Prevention Plan
3. List of contract personnel of the general and subcontractors
8. General Requirements
8.1. Damage to Property:
The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the AO.
8.2. Inspection and Acceptance
A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 2 days in advance with the AO.
9. Period of Performance
The completion of this project shall not exceed 45 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
9.1. Work Hours:
Contractor work hours shall be Monday through Friday, 7:00 A.M. to 4:30 P.M.
except on Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.
10. Guaranty
The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period not less than ten (10) years from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.
11. Project Contacts
TBD
12. Floorplan
BLDG56.pdf
| United States Department of Agriculture |
| Agricultural Research Service |
| 1. Scope of Work |
| 1.1. Base Bid |
| 1.2. Site Visit |
| (A site visit will be scheduled at a later date after the Corona Virus (COVID-19) Pandemic is under control and we are once again allowed to have visitors on our premises.) |
| 2. Codes and Standards |
| 3. Project Summary |
| 4. Utilization of Bio-Based Products |
| 5. Safety |
| 6. Contractor Requirements |
| 7. Documentation Requirements |
| 7.1. Material Submittals |
| 7.2. Pre-Construction Submittals |
| 8. General Requirements |
| 8.1. Damage to Property: |
| 8.2. Inspection and Acceptance |
| 9. Period of Performance |
| 9.1. Work Hours: |
| 10. Guaranty |
| 11. Project Contacts |
| 12. Floorplan |