USDA-ARS-PWA Pour Reinforced Concrete Pad Adams OR
Solicitation number
12905B24Q0029
Issued by

About this file

This statement of work and related federal contract opportunity document outline requirements for a reinforced concrete pad construction project. The United States Department of Agriculture Agricultural Research Service seeks a contractor to construct a 12 foot by 18 foot by 5 inch thick concrete pad with site improvements at its Columbia Plateau Conservation Research Center location in Adams, Oregon. The project is to be completed within 90 calendar days of notice to proceed and will be set aside for small businesses under NAICS code 238110 for construction of foundations and retaining walls with a size standard of $19 million. The solicitation is expected to be issued on or around February 2, 2024 as a firm fixed price construction contract valued at less than $25,000 available via SAM.gov.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

CONCRETE PAD

COLUMBIA PLATEAU CONSERVATION

RESEARCH CENTER

PENDLETON, OR

Date: December 08, 2023

STATEMENT OF WORK

1.0 CONTRACT PROJECT:

a. Project Number: TBD

b. Project Title: Reinforced Concrete Pad

c. Project Location: Columbia Plateau Conservation Research Center 48037 Tubbs Ranch Road, Pendleton, OR

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER (CO):

TBD

USDA-ARS-PWA

Email: Tel. No.:

b. CONTRACTING SPECIALIST (CS):

TBD

c. LOCATION MONITOR (LM):

Columbia Plateau Conservation Research Center 48037 Tubbs Ranch Road, Adams, OR

d. AREA SAFETY AND HEALTH MANAGER

800 Buchanan Street Albany, CA 94710

e. ENGINEERING PROJECT MANAGER (EPM)

TBD

3.0 PROJECT DESCRIPTION:

Construct reinforced concrete pad with required site improvements at USDA-ARS, 48037 Tubbs Ranch Rd., Adams OR 97801. The pad will provide foundation for modular shed.

4.0 PROJECT REQUIREMENTS:

a. Do not disturb hazardous materials and report condition immediately to the Location Monitor regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.

b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

c. Access the site between 7:30 am and 4:00 pm Monday through Friday excluding federal holidays. Contractor staff must sign-in on the first day of arrival and then sign-out on the final day of the project, upon completion.

4.1 Background & Site Description:

Government has a need for a 12 foot wide x 18 foot long x 5 inch thick concrete pad to be installed west of Building B003 (also 535600B003). The site is currently sod.

4.2 Bid Schedule:

Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.

4.3 Description of Work:

a. Provide 12’ x 18’ x 5” pad according to below and Exhibit 1.

b. Excavate site for pad. All debris to be removed off site.

c. Concrete pad finished height to be 4 inches above grade.

d. Footing to be 12 inches wide and 12 inches deep.

e. Slab to be 5” deep.

f. Concrete to be 3,500 PSI compressive strength with 4-7% entrained air.

g. Provide 4” of compacted ¾ minus gravel under slab.

h. Install 3 each #3 rebar in footings. Rebar must be supported so as to not move during pour.

i. Install #3 rebar at 18” on center each way in pad. Rebar must be supported so as to not move during pour.

j. Concrete to be poured monolithically.

k. Concrete to have a brushed finish.

l. Provide 4” of compacted ¾ minus gravel extending 3’ beyond slab.

4.4 Government Furnished Equipment\Services

a. Government will furnish a reasonable amount of electricity and water for the project.

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations.

Contractor shall legally dispose all any materials removed that will not be retained.

5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor. The Contractor shall retain and pay for the services of an independent inspector or testing laboratory to perform all tests expressly required by this contract.

5.6 Protection of Work and Property/Safety Requirements:

a. Contractor shall furnish a Site Specific Safety Plan (SSSP) or Accident Prevention Plan (APP) ten days after contract award. SSSP / APP shall be approved by the Government before construction work commences.

b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.

c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

d. Contractor is responsible for verifying location of any underground utilities and is responsible for any damage caused to such utilities.

5.7 Temporary Facilities:

a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

b. Should the Contractor require any power or utility shutdowns during construction, the

Contractor shall obtain approval for such shutdown from the Location Monitor fourteen

(14) calendar days prior to the need.

5.8 Materials and Equipment:

a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.

c. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.

5.10 Warranty:

a. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO

FINAL PAYMENT (other documents may also be required):

a. General contractor’s minimum one (1) year warranty on work.

b. Release of liens

c. Final Invoice

6.0 Project Schedule:

The Contract time for this project is 90 calendar days from Notice to Proceed.

Photo 2 – Looking South

Photo 3 – Looking North