Attachment I - 1093342 NCGR Irrigation Repairs - SOW.pdf
PDF 1009 KB Posted
- Attached to
- Amendment 01 USDA ARS PWA Irrigation System Repairs Corvallis OR Federal contract opportunity
- Solicitation number
- 12905B23Q0049
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12905B23Q0049 Amendment 01.pdf | ||
| Attachment II - DOL General Decision OR20230022 Rev 5 - 03-17-2023.pdf | ||
| Attachment III - ARS-371 - CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE.pdf | ||
| Attachment IV - ARS-372 - CONTRACTOR REQUEST FOR PAYMENT TRANSMITTAL.pdf | ||
| Attachment V - Contractor RFI FORM.pdf | ||
| RFQ 12905B23Q0049 with T-n-Cs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
IRRIGATION SYSTEM REPAIRS
NATIONAL CLONAL GERMPLASM REPOSITORY
CORVALLIS, OR
Date: February 27, 2023
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Number: TBD
b. Project Title: Irrigation System Repairs
c. Project Location: National Clonal Germplasm Repository - North Farm 33707 Peoria Road, Corvallis, OR
2.0 PROJECT CONTACT PERSONS:
a. CONTRACTING OFFICER (CO):
TBD
USDA-ARS-PWA
Email: Tel. No.:
b. CONTRACTING SPECIALIST (CS):
TBD
USDA-ARS-PWA
Email: Tel. No.:
c. LOCATION MONITOR (LM):
Lauri Reinhold National Clonal Germplasm Repository 33447 Peoria Road; Corvallis, OR Email: lauri.reinhold@usda.gov Tel. No.: 541-738-4218
d. AREA SAFETY AND HEALTH MANAGER
Ken Cushman
USDA-ARS-PWA
800 Buchanan Street Albany, CA 94710 Email: ken.cushman@usda.gov Tel. No.: 510-529-5921
e. ENGINEERING PROJECT MANAGER (EPM) Peter Lane
USDA-ARS-PWA
800 Buchanan St. Albany, CA 94710
Email: peter.lane@usda.gov Tel. No.: 510-559-6340 mailto:lauri.reinhold@usda.gov mailto:ken.cushman@usda.gov mailto:peter.lane@usda.gov
3.0 PROJECT DESCRIPTION:
This project will replace and repair elements of the North Farm irrigation system at the National Clonal Germplasm Repository in Corvallis, OR. This project will address the irrigation system and well #1 and #2.
4.0 PROJECT REQUIREMENTS:
a. Do not disturb hazardous materials and report condition immediately to the Contracting Officer’s Representative (COR) regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.
b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
c. Access the site between 8:00 am and 4:00 pm Monday through Friday excluding federal holidays. Contractor staff must sign-in on the first day of arrival and then sign-out on the final day of the project, upon completion.
4.1 Background & Site Description:
Current Well Documentation:
- When purchased, the property had 4 wells (3 for irrigation and 1 domestic use). No documentation on new wells can be found, and one well was abandoned after purchase.
- State Well No. 12/4E-6E(1), Appl. No. GR-854: SEC 6, TWN 12S W4 . Loc from SEC corner:
S. 21.5 30’E. 1600 ft. from NW cor. SEC 6. Constructed June 1954. Drill depth 34 ft. 6 in steel casing to 34 ft.
- State Well No. 12S/4W-6, No permit number. No location info. Constructed August 1983. Drill depth 90 ft. 10 in steel casing to 36 ft.
- State Well No 12S/4W-6. No permit number. No location info. Constructed August 1983. Drill depth 51 ft. 10 in steel casing to 36 ft.
- Well Locations: See map. It is unknown which well corresponds to the well information above.
- Current Flow Rates: unknown.
Current irrigation system status. See system maps attached. These maps are not up to date with all piping modifications.
Well #1.
- Pump system suboptimal operation
- Marked #1 on colored plot map. Marked #2 on 1991 map.
Well #2.
- Pump system is operational and has the highest horsepower pump.
- Considered the most reliable water supply and has the widest diameter discharge.
- Marked #2 on colored plot map. Marked #1 on 1991 map.
Well #3.
- Pump system operational and has the newest and most modern pump. Has Variable
Frequency Drive, VFD.
- Best quality water (least amount of iron bacteria), but the least reliable (the lowest volume).
- Marked #3 on colored plot map. Marked #3 on 1991 map.
Problems:
- Current configuration is incapable of meeting demand.
- Automation between wells needs repair/replacement for flow/pressure regulation.
- Automation of system valves for zones needs repair/replacement.
- Stationed filtration systems need repair/replacement for iron bacteria.
4.1 Bid Schedule:
Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.
Description Units Quantity Total Base bid – all work not otherwise specified
LS 1
Option Item #1 LS 1 Option Item #2 LS 1 Option Item #3 LS 1 Option Item #4 LS 1
4.2 Description of Work:
All controllers installed to be Wiseconn irrigation controller or approved equal.
a. Include solar power and batteries
b. Controller to be controllable by remote mobile application.
c. Controller to be capable of future expansion to additional pumps and irrigation zone controllers. Each installed controller at wells or valves to have one blank expansion port for future use.
d. All controllers installed for wells and valves to be from same manufacturer and manufactured and marketed for commercial irrigation systems and outside use.
e. Include cellular modem and provide one year of service.
f. Controllers to be installed by dealers registered with manufacturer and within 5 hours of project site for future service.
Provide setup of all equipment and controllers for typical Government irrigation use. Provide training on all equipment and controllers to Government.
Base Bid:
Well #2:
a. Flow test well #1 and #2.
b. Construct 4’ x 14’ x 4” thick concrete pad with welded wire reinforcement for equipment at well #2. Concrete to be 4,000 psi.
c. Construct 3’x6’ backboard at well #2. Use ground contact pressure treated 6x6 posts set in concrete. Use horizontal pressure treated 2x6.
d. Move existing pump infrastructure from well #3 to well #2 including VFD, controllers and other appurtenances. Install disconnect/breaker at supply. Install switch and timer on VFD for manual use on site.
e. Install 3x24 Yamit Sand media filter or approved equal with following characteristics at well #2:
a. 200 GPM capacity
b. #16 silica sand to filter to 130 mesh.
c. Controller with solenoid valves that control automatic backwash
d. Custom fabricated powder-coated manifold to connect to existing mainline.
f. Install at sand media filter inlet: chemigation check valve as backflow preventer, air vent, transducer connected to VFD
g. Install at sand media filter outlet: transducer, flow meter, sustaining valve and butterfly valve. Tie into existing irrigation mainline.
h. Construct wet well with drain rock for filter backwash.
i. Provide irrigation controller. Integrate with VFD, flow meter and pressure transducer.
Well #1:
a. Flow test well #1
b. Construct 4’ x 14’ x 4” thick concrete pad with welded wire reinforcement for equipment at well #1. Concrete to be 4,000 psi.
c. Construct backboard at well #1 suitable for controller. Use ground contact pressure treated posts set in concrete. Use horizontal pressure treated 2x6.
d. Install 3x24 Yamit Sand media filter or approved equal with following characteristics at well #1:
a. 200 GPM capacity
b. #16 silica sand to filter to 130 mesh.
c. Controller with solenoid valves that control automatic backwash
d. Custom fabricated powder-coated manifold to connect to existing mainline.
e. Install at sand media filter inlet: chemigation check valve as backflow preventer, air vent, transducer port
f. Install at sand media filter outlet: transducer, flow meter, sustaining valve and butterfly valve. Tie into existing irrigation mainline.
g. Construct wet well with drain rock for filter backwash.
h. Provide irrigation controller. Integrate with flow meter and pressure transducer. Controller to communicate with well #2 controller
Option Item #1
a. Install irrigation control on the 4 individual irrigation zones marked B1, C1, D1 and E1.
Integrate with controllers on pumps.
b. Well controllers may be used for valves or separate controllers provided for individual valves or groups of valves.
c. Provide new control valves on existing 2” PVC lines underground in new valve boxes.
d. Control wire to be per controller manufacturer recommendation. Minimum bury depth of
12”. Provide warning tape 6” above wire. Route control wire along roadways or between plots.
Option Item #2
e. Install irrigation control on the 2 individual irrigation zones marked C2 and D2. Integrate with controllers on pumps.
f. Well controllers may be used for valves or separate controllers provided for individual valves or groups of valves.
g. Provide new control valves on existing 2” PVC lines underground in new valve boxes.
h. Control wire to be per controller manufacturer recommendation. Minimum bury depth of
Option Item #3
a. Install irrigation control on the 2 individual irrigation zones marked B2 and F. Integrate with controllers on pumps.
b. Well controllers may be used for valves or separate controllers provided for individual valves or groups of valves.
c. Provide new 2” PVC lines from existing hydrants to existing irrigation field lines. Provide new control valves on the new 2” PVC lines underground in new valve boxes.
d. Control wire to be per controller manufacturer recommendation. Minimum bury depth of
Option Item #4
a. Install irrigation control on the 2 individual irrigation zones marked A1 and A2. Integrate with controllers on pumps.
b. Well controllers may be used for valves or separate controllers provided for individual valves or groups of valves.
c. Provide new 2” PVC lines from existing hydrants to existing irrigation field lines. Provide new control valves on the new 2” PVC lines underground in new valve boxes.
d. Control wire to be per controller manufacturer recommendation. Minimum bury depth of
4.3 Government Furnished Equipment\Services
a. Government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations.
Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor. The Contractor shall retain and pay for the services of an independent inspector or testing laboratory to perform all tests expressly required by this contract.
5.6 Protection of Work and Property/Safety Requirements:
a. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.
b. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
c. Contractor is responsible for verifying location of any underground utilities and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the
Contractor shall obtain approval for such shutdown from the Location Monitor fourteen
(14) calendar days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.
5.10 Warranty:
a. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO
FINAL PAYMENT (other documents may also be required):
a. General contractor’s minimum one (1) year warranty on work.
b. Release of liens
c. Final Invoice
6.0 Project Schedule:
The Contract time for this project is 120 calendar days from Notice to Proceed.
7.0 Figures
2002 colored plot map
1991 map
Irrigation Control Zones
| / |