Attachment G - Bid Documents Specifications 546-19-109.pdf

PDF 3 MB Posted

Attached to
Z2NE-- FY22: NRM PLUS UP; (PROJ: 546-19-102) BB Upgrade Water Mains Building 1
Solicitation number
36C24822R0026
Issued by

About this file

This solicitation seeks construction services for Project 546-19-102 to upgrade water mains at the Miami VA Healthcare System. The project scope includes replacing underground transite piping, analyzing and replacing isolation valves, and repairing leaks in crawl spaces and building chases. The acquisition is a 100% SDVOSB set-aside to be awarded as a fixed-price contract. The Department of Veterans Affairs Network Contracting Office 8 is the contracting agency. Price proposals are due January 6, 2022. The point of contact is Apolinar Vargas at apolinar.vargas@va.gov.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UPGRADE WATER MAINS TO

BUILDING 1 FCA-D

Bruce W. Carter VA Medical Center Miami, FL July 8, 2020

Bid Documents Specifications

Project Number: 546-19-102

Upgrade Water Mains to Building 1 FCA-D Miami VAMC, Miami, FL Project No.: 546-19-102

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 10-17 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 02-15 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 35 Special Inspections Appendix 01 45 35.01 - Statement of Special Inspections Appendix 01 45 35.02 - Schedule of Special Inspections 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 02 82 13.31 Asbestos Transite-Type Abatement 09-15

DIVISION 03 – CONCRETE

03 30 53 Cast-in-Place Concrete (Short-Form)

DIVISION 04 – MASONRY

DIVISION 05 – METALS

05 12 00 Structural Steel Framing

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

DIVISION 09 – FINISHES

09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 06-18 09 30 13 Ceramic/Porcelain Tiling 10-15 09 51 00 Acoustical Ceilings 12-16 09 91 00 Painting 01-16

Project No.: 546-19-102

00 01 10-2

DIVISION 10 – SPECIALTIES

DIVISION 11 – EQUIPMENT

DIVISION 12 – FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

DIVISION 21- FIRE SUPPRESSION

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 12 General Motor Requirements for Plumbing Equipment 09-15 22 05 19 Meters and Gages for Plumbing Piping 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 11-19 22 11 23 Domestic Water Pumps 09-15 22 35 00 Domestic Water Heat Exchangers 12-16 22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17 23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 11-16 23 22 13 Steam and Condensate Heating Piping 08-17

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17

DIVISION 27 – COMMUNICATIONS

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 31 23 23.33 Flowable Fill

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving 32 17 23 Pavement Markings 32 90 00 Planting

DIVISION 33 – UTILITIES

33 10 00 Water Utilities

Project No.: 546-19-102 07-01-15

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G001 COVER SHEET

G002 LEGENDS, ABBREVIATIONS AND NOTES

CIVIL

D-1 DEMOLITION AND REMOVALS PLAN - WEST

D-2 DEMOLITION AND REMOVALS PLAN – CENTER

D-3 DEMOLITION AND REMOVALS PLAN – EAST

C-1 GRADING AND EROSION CONTROL PLANS – WEST

C-2 GRADING AND EROSION CONTROL PLANS – CENTER

C-3 GRADING AND EROSION CONTROL PLANS – EAST

C-4 SITE AND UTILITY PLANS – WEST

C-5 SITE AND UTILITY PLANS – CENTER

C-6 SITE AND UTILITY PLANS – EAST

C-7 SITE PHOTOGRAPHS 1

C-8 SITE PHOTOGRAPHS 2

C-9 SITE PHOTOGRAPHS 3

C-10 LOCAL STANDARD DETAILS 1

C-11 PREVIOUS PLAN – WATER TOWER MODIFICATION 1

C-12 PREVIOUS PLAN – WATER TOWER MODIFICATION 2

ABATEMENT

AB101 ABATEMENT PLAN - WEST

AB102 ABATEMENT PLAN - CENTER

AB103 ABATEMENT PLAN – EAST

STRUCTURAL

S001 STRUCTURAL NOTES

S101 FLOOR FRAMING PLAN

Project No.: 546-19-102 07-01-15

00 01 15 - 2

ARCHITECTURAL

A101 NOT USED

A102 OVERALL SIXTH FLOOR PLAN

A103 OVERALL SEVENTH FLOOR PLAN

A104 OVERALL EIGHTH FLOOR PLAN

A105 OVERALL NINTH FLOOR PLAN

A106 OVERALL TENTH FLOOR PLAN

A107 OVERALL ELEVENTH FLOOR PLAN

A108 OVERALL TWELFTH FLOOR PLAN

A401 ENLARGED FLOOR PLANS

A402 NOT USED

A403 NOT USED

A404 ENLARGED FLOOR PLAN

A405 ENLARGED FLOOR PLAN

A406 ENLARGED FLOOR PLAN

A407 ENLARGED FLOOR PLAN

A408 ENLARGED FLOOR PLAN

PLUMBING

P001 PLUMBING SCHEDULES, LEGEND AND DETAILS

PD101 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD102 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD103 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD104 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD105 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD106 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD107 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD108 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PD109 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING

DEMOLITION

PP100 OVERALL PLUMBING PLAN – CRAWL SPACE – PIPING

REPLACEMENT

Project No.: 546-19-102 07-01-15

00 01 15 - 3

PLUMBING (CONTINUED)

PP101 OVERALL PLUMBING PLAN – FIRST FLOOR VALVE REPLACEMENT

PP102 OVERALL PLUMBING PLAN – SECOND FLOOR VALVE

REPLACEMENT

PP103 OVERALL PLUMBING PLAN – THIRD FLOOR VALVE REPLACEMENT

PP104 OVERALL FLOOR PLAN – TENTH FLOOR PLUMBING PLAN

PP105 OVERALL FLOOR PLAN – ELEVENTH FLOOR PLUMBING PLAN

PP106 OVERALL FLOOR PLAN – TWELFTH FLOOR PLUMBING PLAN

PP201 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP201 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP202 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP203 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP204 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP205 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP206 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP207 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP208 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP209 ENLARGED PLUMBING PLAN – CRAWL SPACE – PIPING NEW

WORK

PP211 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP212 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP213 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP214 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP215 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP216 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP217 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

00 01 15 - 4

Plumbing cont.

PP218 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP219 ENLARGED PLUMBING PLAN – FIRST FLOOR – VALVE

REPLACEMENT

PP221 ENLARGED PLUMBING PLAN – SECOND FLOOR – VALVE

REPLACEMENT

PP222 ENLARGED PLUMBING PLAN – SECOND FLOOR – VALVE

REPLACEMENT

PP231 ENLARGED PLUMBING PLAN – THIRD FLOOR – VALVE

REPLACEMENT

PP232 ENLARGED PLUMBING PLAN – THIRD FLOOR – VALVE

REPLACEMENT

PP233 ENLARGED PLUMBING PLAN – THIRD FLOOR – VALVE

REPLACEMENT

PP234 ENLARGED PLUMBING PLAN – THIRD FLOOR – VALVE

REPLACEMENT

PP235 ENLARGED PLUMBING PLAN – 11TH FLOOR C/D – VALVE

REPLACEMENT

PP236 ENLARGED PLUMBING PLAN – 11TH FLOOR A/B – VALVE

REPLACEMENT

PP241 ENLARGED PLUMBING PLAN – 10TH FLOOR C/D – HORIZ.

CONVERSION

PP242 NOT USED

PP243 ENLARGED PLUMBING PLAN – 11TH FLOOR C/D – HORIZ.

CONVERSION

PP244 ENLARGED PLUMBING PLAN – 11TH FLOOR A/B – HORIZ.

CONVERSION

PP245 ENLARGED PLUMBING PLAN – 12TH FLOOR C/D – HORIZ.

CONVERSION

PP246 ENLARGED PLUMBING PLAN – 12TH FLOOR A/B – HORIZ.

CONVERSION

PP301 CRAWL SPACE WATER MAIN ISOMETRIC – PIPING NEW WORK

PP302 TENTH FLOOR C/D – PIPING ISOMETRIC

PP303 ELEVENTH – TWELFTH FLOOR C/D – PIPING ISOMETRIC

PP304 ELEVENTH FLOOR A/B – PIPING ISOMETRIC

PP305 TWELFTH FLOOR A/B – PIPING ISOMETRIC

P051 WATER HEATER SCHEDULES AND LEGENDS

PD251 ENLARGED DOM. WTR. PIPING PLAN - BASEMENT LEVEL -

DEMO WORK

00 01 15 - 5

PLUMBING (CONTINUED)

PD252 ENLARGED DOMESTIC WATER PIPING PLAN - SECOND FLOOR –

DEMO WORK

PD261 ENLARGED PIPING FLOOR PLANS – DEMOLITION

PP251 ENLARGED DOMESTIC WATER PIPING PLAN - BASEMENT LEVEL

- NEW WORK

PP252 ENLARGED STEAM PIPING PLAN - BASEMENT LEVEL - NEW

WORK

PP253 ENLARGED DOMESTIC WATER PIPING PLAN - FIRST FLOOR -

NEW WORK

PP254 ENLARGED DOMESTIC WATER PIPING PLAN - SECOND FLOOR -

NEW WORK

PP261 ENLARGED PIPING FLOOR PLANS

PP262 ENLARGED PIPING FLOOR PLANS

PP271 ENLARGED PIPE CHASE VERTICAL VALVING FLOOR PLANS

PP272 ENLARGED PIPE CHASE VERTICAL VALVING FLOOR PLAN

PP351 WATER HEATER AND VERTICAL CHASE ISOMETRIC RISER

DIAGRAMS

PP451 PLUMBING DETAILS

PP751 CONTROLS AND INSTRUMENTAION

- - - END - - -

Project No.: 546-19-102 12-01-2018 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 RESTORATION

1.10 AS-BUILT DRAWINGS

1.11 WARRANTY MANAGEMENT

1.12 USE OF ROADWAYS

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.14 TEMPORARY USE OF EXISTING ELEVATORS

1.15 TEMPORARY TOILETS

1.16 AVAILABILITY AND USE OF UTILITY SERVICES

1.17 TESTS

1.18 INSTRUCTIONS

1.19 PHOTOGRAPHIC DOCUMENTATION

Project No.: 546-19-102 10-01-17

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing build out, furnish labor and materials and perform work to renovate the existing Ward 5A. Work includes a general demolition and reconstruction of the Fifth Floor “A” wing. Work is interior fit-up but includes all Mechanical, Electrical, Plumbing and Fire Protection systems as required by the drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Engineering Officer.

C. Offices of Toland Mizell Molnar, LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

Project No.: 546-19-102 10-01-17

01 00 00 -2

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, demolition, removal, replacement and reconstruction, and various modifications of existing systems, structures, and construction and certain other items to replace and upgrade the water mains to

Building 1. The project will also include replacing isolation valves and the horizontal conversion of water distribution on floors 10, 11 and 12. The underground mains consist of transite, asbestos piping which must be abated. Some water mains run in the crawl space underneath the buildings as well as chases in the buildings.

Note: For Building 1 outside of this work, 1st Floor Hemodialysis, 3rd floor MICU/PCU and 3rd Floor SPS are currently VA approved project and will need to be considered as a possible de-scope if projects include valves. When contractor makes onsite visit, for estimate, this would need to be part of their assessment.

B. ITEM NO. 2 – BID ALTERNATE NO. 1: All work described on the Drawings and Specifications minus Bid Alternate No. 1 described as follows:

Omit the horizontal conversion of water distribution systems within the areas of the 10th Floor – “C” wing and 10th Floor – “D” wing.

C. ITEM NO. 3 – BID ALTERNATE NO. 2: All work described on the Drawings and Specifications minus Bid Alternate No. 1 and Bid Alternate No. 2 described as follows:

areas of the 12th Floor – “C” wing and 12th Floor – “D” wing.

D. ITEM NO. 4 – BID ALTERNATE NO. 3: All work described on the Drawings and Specifications minus Bid Alternate No. 1, Bid Alternate No. 2 and

Bid Alternate No. 3 described as follows:

areas of the 12th Floor – “A” wing and 12th Floor – “B” wing.

Project No.: 546-19-102 10-01-17

01 00 00 -3

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project

Project No.: 546-19-102 10-01-17

01 00 00 -4 including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

Project No.: 546-19-102 10-01-17

01 00 00 -5

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

Project No.: 546-19-102 10-01-17

01 00 00 -6

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR and will be very limited on site, potentially limited to the project footprint.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

Project No.: 546-19-102 10-01-17

01 00 00 -7

To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing to insure accomplishment of this work in successive phases mutually agreeable to

COR and Contractor, as follows:

Phases: TBD by coordination with COR.

H. Building(s) No. 100 will be occupied during performance of work; but immediate areas of alterations will be vacated.

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

I. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

Project No.: 546-19-102 10-01-17

01 00 00 -8

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

J. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

Project No.: 546-19-102 10-01-17

01 00 00 -9

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

L. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

M. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building. 2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

Project No.: 546-19-102 10-01-17

01 00 00 -10

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR

852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

Project No.: 546-19-102 10-01-17

01 00 00 -11

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

Project No.: 546-19-102 10-01-17

01 00 00 -12

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.10 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

Project No.: 546-19-102 10-01-17

01 00 00 -13

1.11 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

Project No.: 546-19-102 10-01-17

01 00 00 -14

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond must remain effective throughout the construction period

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of

Project No.: 546-19-102 10-01-17

01 00 00 -15 expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

Following oral or written notification by the Contracting Officer, the

Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Project No.: 546-19-102 10-01-17

01 00 00 -16

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

Code 1-Life Safety Systems

a. Fire suppression systems.

b. Fire alarm system(s).

Code 1-Air Conditioning Systems

a. Air conditioning leak in part of the building, if causing damage.

b. Air conditioning system not cooling properly.

Code 1 Doors

a. Overhead doors not operational, causing a security, fire or safety problem.

b. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

Code 3-Doors

a. Overhead doors not operational.

b. Interior/exterior personnel doors or hardware not functioning properly.

Code 1-Electrical

Project No.: 546-19-102 10-01-17

01 00 00 -17

a. Power failure (entire area or any building operational after 1600 hours).

b. Security lights.

c. Smoke detectors.

Code 2-Electrical

a. Power failure (no power to a room or part of building).

b. Receptacles and lights not operational (in a room or part of building).

Code 3-Electrical

a. Exterior lights not operational.

Code 1-Gas

a. Leaks and pipeline breaks.

Code 1-Heat

a. Power failure affecting heat.

Code 1-Plumbing

a. Hot water heater failure.

b. Leaking water supply pipes.

Code 2-Plumbing

a. Flush valves not operating properly

b. Fixture drain, supply line or any water pipe leaking.

c. Toilet leaking at base.

Code 3- Plumbing

a. Leaky faucets.

Code 3-Interior

a. Floors damaged.

b. Paint chipping or peeling.

Project No.: 546-19-102 10-01-17

01 00 00 -18

c. Casework damaged.

Code 1-Roof Leaks

a. Damage to property is occurring.

Code 2-Water (Exterior)

a. No water to facility.

Code 2-Water (Hot)

a. No hot water in portion of building listed.

Code 3

a. All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting

Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Project No.: 546-19-102 10-01-17

01 00 00 -19

1.12 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

Project No.: 546-19-102 10-01-17

01 00 00 -20

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

Project No.: 546-19-102 10-01-17

01 00 00 -21

1.14 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevators for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators.

The COR will ascertain that elevators are in proper condition.

Contractor may use elevators as designated for daily use in hours determined by COR and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.

4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.

5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.

6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

Project No.: 546-19-102 10-01-17

01 00 00 -22

1.15 TEMPORARY TOILETS

A. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.16 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the

Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system.

a. Steam is available at no cost to Contractor.

Project No.: 546-19-102 10-01-17

01 00 00 -23

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

1.17 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work.

This is the start of the file's text. The full file is on GovTribe.