Attachment_F_-_Risk_Assessment.docx
DOCX document 21 KB Posted
- Attached to
- Third Party Cost of Service Review
- Solicitation number
- RFP SCL767092085
- Issued by
- King County, Washington
About this file
This is a Risk Assessment attachment related to the City of Seattle's Third Party Cost of Service Review procurement. The document outlines the risk evaluation framework that will be applied to proposals submitted for this engagement. The assessment appears to establish criteria and methodologies for evaluating potential risks associated with vendor proposals, including organizational capacity, financial stability, technical capability, and implementation feasibility. Proposals are due no later than 12:00 pm on Wednesday, December 23, 2026, with all questions to be submitted through the e-procurement portal at https://procurement.opengov.com/portal/seattle no later than 12:00 pm on Tuesday, December 8, 2026.
The Risk Assessment document serves as an evaluation tool to ensure that the selected third-party provider can successfully execute the cost of service review with minimal organizational or operational risk to the City. By establishing predetermined risk categories and assessment criteria, the City aims to identify vendors with demonstrated experience, adequate resources, and sound methodologies for conducting comprehensive cost of service analyses. This attachment functions as part of the broader solicitation package to guide both the evaluation committee's assessment process and prospective bidders' understanding of how their qualifications and proposed approaches will be evaluated against established risk parameters.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Third_Party_Cost_of_Service_Review.pdf | ||
| Attachment_B_-_Minimum_Quals.doc | DOC document | |
| Attachment_H_-_Insurance_Transmittal_Form.doc | DOC document | |
| Appendix_A_-_SCL_Contract_Boilerplate.pdf | ||
| Attachment_G_-_Cost_Proposal.xlsx | XLSX spreadsheet | |
| Attachment_E_-_Resume_of_Key_Project_Team.docx | DOCX document | |
| Attachment_D_-_Narrative_of_Related_Experience.docx | DOCX document | |
| Attachment_C_-_Approach_to_Scope_of_Work.docx | DOCX document | |
| Attachment_A_-_Consultant_Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RISK ASSESSMENT
CONTROLLABLE / NON-CONTROLLABLE
This template must be used. Modifications to the format of this template may result in disqualification (i.e. altering font size, altering font type, adding colors, adding pictures, etc.). Do not list any names or information that can be used to identify the Consultant’s identity.
You may copy/paste to add or delete individual Risk items, but do not exceed the specified page limits.
Please use the following format:
· Risk # – Title of the Risk (critical aspect of the scope)
· Why is it a Risk? – A brief description of why the risk is critical a successful project outcome.
· Solution – describe all of the following: (a) action steps that will be taken to successfully execute this aspect of the scope, and (b) technical expertise/experience to ensure the proposed action steps will fulfil the Scope of Work.
Bullet points may be useful for listing recommended action steps.
(2 pages maximum) (You may delete all of these instructions)
SECTION 1 – ASSESSMENT OF CONTROLLABLE RISKS
Risk 1:
Why is it a Risk?
Solution:
Risk 2:
Why is it a Risk?
Solution:
Risk 3:
Why is it a Risk?
Solution:
Risk 4:
Why is it a Risk?
Solution:
Risk 5:
Why is it a Risk?
Solution:
Attachment F
RFP# SCL767092085
RISK ASSESSMENT / NON-CONTROLLABLE
This template must be used. Modifications to the format of this template may result in disqualification (i.e. altering font size, altering font type, adding colors, adding pictures, etc.). Do not list any names or information that can be used to identify the Consultant’s identity.
You may copy/paste to add or delete individual Risk items, but do not exceed the specified page limits.
Please use the following format:
· Risk # – Title of the Risk item
· Why is it a Risk? – A brief description of how the risk may impact the project (cost/schedule/scope/quality).
· Solution – include all of the following: (a) action steps to prevent the risk from occurring, (b) definition of potential impacts to project cost/schedule/scope/quality if the risk does occur, and (c) recommended response plan if the risk does occur.
Bullet points may be useful for listing recommended action steps.
(2 pages maximum) (You may delete all of these instructions)
SECTION 2 – ASSESSMENT OF NON-CONTROLLABLE RISKS
Risk 1:
Why is it a Risk?
Solution:
Risk 2:
Why is it a Risk?
Solution:
Risk 3:
Why is it a Risk?
Solution:
Risk 4:
Why is it a Risk?
Solution:
Risk 5:
Why is it a Risk?
Solution:
File details come from the government source that posted it. Updated .