This document is a collection of Data Item Descriptions (DIDs) from the Department of Defense, each specifying reporting and documentation requirements for different types of federal contract activities. The documents cover various reporting needs, including:
- Government Property (GP) Inventory Report (DI-MGMT-80441D): Requires contractors to provide an electronic spreadsheet listing all government-owned property, including details like contract number, asset identification, description, manufacturer information, quantity, location, and property classification. 2. Counterfeit Prevention Plan (DI-MISC-81832): Mandates contractors develop a comprehensive plan to prevent counterfeit parts, including procurement practices, monitoring procedures, training programs, and detailed notification processes for identifying and handling suspect parts. 3. Contract Depot Maintenance (CDM) Monthly Production Report (DI-PSSS-81995A): Requires monthly reporting on maintenance production, including detailed tracking of received items, repairs in progress, completed repairs, shipped serviceables, and next month's production forecast. 4. Additional documents cover Commercial Asset Visibility reporting, Test/Inspection Reports, and Acquisition and Sustainment Data Package Teardown Deficiency Reports, each with specific format and content requirements for different contract management activities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
Title: Government Property (GP) Inventory Report Number: DI-MGMT-80441D Approval Date: 20200609 AMSC Number: 10184 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Preparing Activity: MDA Project Number: MGMT-2020-012 Applicable Forms: None
Use/Relationship: The Government Property (GP) Inventory Report enables the contractor to periodically provide to the Department of Defense (DoD) Service or Agency an inventory listing of GP (i.e., both Government Furnished Property (GFP) and Contractor Acquired Property (CAP)) in the contractor’s possession (to include subcontractors) by contract.
This Data Item Description (DID) is applicable to all contracts where GP will be furnished by the Government (i.e., GFP) or acquired, fabricated, or otherwise provided by a contractor (i.e., CAP) in performance of a contract.
This DID contains the format, content, and intended use information for the data deliverable resulting from the work task described in the solicitation.
This DID supersedes DI-MGMT-80441C.
Requirements:
1. Reference documents. None.
2. Format. The report shall be in an electronic .xls or .xlsx compatible format.
3. Content. The report shall contain the following column headers (i.e., data fields):
A. Contract Number B. Agency or Service Asset Identification Number (GFP Only) C. Contractor Asset Identification Number D. Item Description E. Manufacturer Part Number F. Manufacturer Model Number G. Manufacturer Serial Number H. National Stock Number (NSN) (if applicable) I. Quantity J. Unit of Measure K. Unit Acquisition Cost L. Unique Item Identifier (if registered in the Item Unique Identification (IUID) Registry;
GFP only) M. Asset Location N. Asset Sub-Location (if applicable) O. Type of Government Property (i.e., Government Furnished Property (GFP) or
Contractor Acquired Property (CAP) P. Classification of Government Property (i.e., Communication Security (COMSEC), Equipment (EQP), Material (MAT), Special Test Equipment (STE), or Special Tooling
Source: http://assist.dla.mil -- Downloaded: 2020-12-07T16:17Z Check the source to verify that this is the current version before use.
DI-MGMT-80441D
(ST))
Q. Date of Last Physical Inventory R. Federal Condition Code
END OF DI-MGMT-80441D
Source: http://assist.dla.mil -- Downloaded: 2020-12-07T16:17Z
Source: http://assist.dla.mil -- Downloaded: 2020-08-20T18:47Z
DATA ITEM DESCRIPTION I Form Approved OMB No.0704.0188
1.nTLE 2.IOENTIFICATIONNUMBER
TEST/ INSPECTION REPORT DI-NM’I-80809B
L OESCRIPTlOtVPURPOSE
3.1 The testl inspection report is used to document testl inspection results, findings, and analyses that will enable the government or contracting agency to evaluate compliance with system requirements, performance objectives, specifications, and test linspection plans.
1.APPROVALDATE 5.OFFICEOFPRIMARYRESPONSIBILITY(OPB) Ea.DTICAPPLICABLE 6b.CWIEP AppliCable
(YVMMOD)
F/AFMC-DCJP
970124
,.APPLlCAT\0NflNTER7iElAT10NSH1P
7.1 This data item description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement
I as delineated in the contract.
I
7.2 This DID is applicable to engineering (developmental ), preliminary qualification, qualification, and acceptance testing.
7.3 This DID supersedes DI-NDTI-80809A and DI-MISC-80653
1.APPROVALLIMITATION 9a.APPLICABLEFORMS 9b.AMSCNUMBER
F7231
10,PREPARATIONlNSTRUCnONS
10.1 Format. Contractor format is acceptable.
paragraph 10.2 and its subparagraphs in a manner understanding
10.2 CQnL!aL. The test/inspection report shall
applicable.
Organize the information required by that facilitates presentation and contain the following information, as
10. 2.1 Cove. and tile uaae. The following information shall appear on the outside front :over and title page:
a. Report date.
b. Report number (contractor or government)
Contractor’ s name, address, and commercia 1 and government entity code.
Contract number and contract line item number or sequence number (if applicable)
e. ‘fvpe of test/inspection (for example. first article acceptance test, aualitv con formanc-e-inspection, d-evelopmental test-, qualification test, f Identification of item tested/inspected.
9. Date or period of test/inspection.
h. Name and address of requiring government activity.
i. Security classification, downgrading and declassifying environmental Lest) .“ information, if applicable.
(Continued on page 2 )
1.DIS77UBUTIONSTATEMEW
DISTRIBUTION STATEMRNT A : APPROVED FOR PUBLIC RELBASE; DISTRIBUTION IS UNLIMITED.
ID Form 1664,APR 89 PreviOLIsedtliomwe obsdem. Page 1 of & Pages 39123
DI-NDTI-80809B
Block 10, Preparation Instructions (continued)
10.2.2 ~. The table of contents shall identify the following:
a. The title and starting page of each major section, paragraph, and apPendix of the report.
b. The page, identifying number, and title of each illustration (for example; figure, table, photograph, chart, and drawing)
10 .2.3 -ductim. The introduction shall include the following information:
10.2 .3.1 obyectlve W. The specific test/ inspection objective (s) as specified in the contract tasking document.
10. 2.3.2 L.temls) tes~. Complete identification of the item(s) testedl inspected including the following:
a. Nomenclature.
b. National stock number.
Model number, part number t and serial number :: Type of item (for example, prototype, production item, laboratory model )
e. Serial or lot number.
f. Applicable engineering changes
9. Production item specification, if applicable.
h. Date of manufacture.
10.2 .3.3 Complete inspection requirements correlated to contractual following:
Required testl inspection parameters :: Performance requirements, acceptance or environmental criteria.
10.2.4 ~. Complete test/inspection report following:
identification of the testl requirements including the compliance limits, and summary including the
a. A brief discussion of the significant test/inspection results, ObSerVati Qns, conclusions, and recommendations covered in greater detail elsewhere in the report.
b. Proposed corrective actions and schedules for failures or problems encountered.
c. Identification of deviations, departures, or limitations encountered, referenced to the contract requirements.
d. Tables, graphs, illustrations, or charts as appropriate to simplify the summary data.
10.2.5 ~. Complete identification of all documents referenced in the test finspection report including the following, as applicable:
a. Prior testf inspection reports on the same item.
b. Test /inspection plans and procedure documents
c. Prior certifications of compliance.
d. Contractor’ s file designation where test/ inspection records are maintained.
e. Input parameters used.
The applicable issue of the documents cited therein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
Page 2 of 4 Pages
10.2.6 ~. The body of the testlinspection report shall be as follows :
10 .2.6.1 KzZL_ + de.tlflca~.
Complete identification of each item of test equipment used in the testlinspection including the following:
a.
b.
c.
d.
e.
f.
9.
10. 2.6.2
Nomenclature.
Model number.
Serial number.
Manufacturer.
Calibration status.
Accuracy data.
Comments, if applicable.
Testlinmection kuhtv mstd.b&mn and set–w. Complete description of the physical set-up used in conducting the test/inspection to include the following:
a. Location or orientation of the item.
b. Location. orientation, or settinm of test equipment and instrumentation.
c. Location, orientation, or settings of sensors and probes
d. Location or orientation of interconnections, cables, and hoop-ups.
e. Electrical power, pneumatic, fluidic, and hydraulic requirements.
Drawings, illustrations, and photographs maY be used for clarification.
10 .2.6.3 wrocedur~. Complete description of the procedures used in conducting the test/inspection to include the following:
a. Item selection and inspection that verified suitability for test/ inspection.
b. Summarized sequence of testing/inspection steps, including a description of how the item was operated during the test/inspection, and any control conditions imposed.
10 .2.6.4 A copy of all testlinspection results and analysis to include the following:
10.2.6 .4.1 ~. The actual recorded data (for example, log book entries, oscillographs, instrument readings, plotter graphs) If the recorded data is extensive, provide it in an appendix.
10. 2.6.4.2 Test/ insQec!iion resu. Identification of all testlinspection results to include the following:
a. Matrices comparing results achieved against test/inspection objectives or requirements
b. A discussion of these matrices as to their significance, and how they compare to any prior testlinspections.
Calculation examples.
;; Discussion of anomalies, deviations, discrepancies, or failures, including their impact, causes, and proposed corrective actions The discussion shall address discrepancies between design requirements and the tested/inspected Configuration.
10. 2.6.5 Conclusicxls Test/ inspection conclusions distinguished between objective and subjective to include the following:
a. The effectiveness of the testlinspection procedures in measuring item performance.
Page 3 of 4 Pages
b. The success or failure of the item to meet required test/inspection objectives.
c. The need for repeat, additional, or alternative tests linspections.
d. The need for item redesign or further development.
e. The need for improved test/inspection procedures, techniques, or facilities.
f. The adequacy and completeness of the test/inspection requirements.
10.2 .6.6 Recommendations appropriate to the test/inspection results and conclusions including the following:
a b.
c.
d.
e.
f.
9.
h.
Acceptability of the item tested/inspected (pass or fail) Additional testing/inspection required. ,.
Redesign required.
Problem resolution.
Test/inspection procedure or facility improvements Disposition of items tested/inspected.
Documentation changes required.
Testing/ inspection improvements
10.2.7 The following certifications shall be included, .as
applicable:
10.2 .7.1 A statement that the testlinspection was performed in accordance with applicable testlinspection plans and procedures, and that the results are true and accurate. The authentication shall include the signature of the contractor personnel that performed the test(s) /inspection(s) , a contractor representative authorized to make such certification, and any government witnesses
10.2 .7.2 A statement identifying those requirements not tested/inspected or measured that were previously validated.
Include identification of the data and method employed for such validation (for example, prior test/inspection, analytical verification, equivalent item, and so on) The authentication shall include the signature of a contractor representative authorized to make such authentication and any government witness.
10.2 .7.3 A statement that the item tested/ inspected either passed or failed item acceptability requirements This authentication shall include the signature of a contractor representative authorized to make such authentication and any government witness
10.2.8 Appendices shall be used to append detailed
test/inspection daia, drawings, photographs , or other documentation too voluminous to include in the main body of the report This includes referenced documentation not previously provided by the government, and test/ inspection reports from any associated test/inspection activity that may have performed some of the testing/inspecting requirements.
Page 4 of 4 Pages
Title: Acquisition and Sustainment Data Package (ASDP) Teardown Deficiency Report
Number: DI-PSSS-81534B Approved Date: 20220809
AMSC Number: F10348 Limitation: N/A
DTIC Applicable: No GIDEP Applicable: No
Preparing Activity: 11 (AFLCMC/EZSC) Project Number: PSSS-2022-004
Applicable Forms: N/A
Use/Relationship: The Acquisition and Sustainment Data Package (ASDP) Teardown Deficiency Report provides a factual narrative analysis of a deficiency which has been noted on equipment.
a. This Data Item Description (DID) is applicable when contractors are responsible for maintaining custodial records for government property being repaired, or, when detailed analysis is required for components undergoing a teardown investigation.
b. This DID contains the format, content, and intended use information for the data deliverable resulting from the work task described in the solicitation.
c. This DID supersedes DI-PSSS-81534A.
Requirements:
1. Reference documents. None.
2. Format. The ASDP Teardown Deficiency Report shall be in a text searchable format. If a model (e.g., Cameo, CAD, etc.) is used for the analysis or resolution of problems, the model shall be embedded in its native format. The Data Objects/Attributes and Associated Metadata (DOAM) listing shall be in Microsoft Excel spreadsheet format in accordance with the template provided in the DOAM Specification attached to the contract. All data shall be in the English language.
3. Content. The Teardown Deficiency Report shall include an analysis of the deficiency which includes cause of failure, recommended corrective action and recommendations for actions to prevent recurrence of the failure/deficiency, and the applicable category of the failure defined as follows:
a. Workmanship and non-conformance. Any deficiency (e.g., physical, chemical, electrical, functional) noted in materiel which is attributed to non-conformance to applicable specifications, drawing, standards, or Technical Order (TO); or workmanship during manufacture, repair modification or maintenance.
b. Material failure. The failure of an end item which was attributable to neither the repair nor the manufacturing process, but was due to an unpredictable failure of an internal component or sub-assembly.
c. No defect found/could not duplicate: Investigation of the exhibit revealed no deficiency.
Equipment conforms to specifications and TO standards and procedures.
d. Technical data, deficiency: Technical data (including TOs, drawings, and work specifications) was deficient or inadequate so as to cause the deficiency/failure on the item.
Source: http://assist.dla.mil -- Downloaded: 2022-10-06T17:08Z
DI-PSSS-81534B
e. Field induced deficiency. Deficiency confirmed by the investigation to have been caused by operator error, i.e., wrong voltage applied, misaligned, maladjusted, mishandling, or not used for intended purpose.
f. Maintenance deficiency. An unfavorable characteristic of an item that impedes the accomplishment of maintenance operations which results in excessive maintenance operations and/or in excessive maintenance man-hour consumption.
g. Design deficiency. A condition that limits or prevents the use of material for purpose intended or required where the material meets all other specifications.
h. Handling or shipping deficiency. A deficiency induced by improper handling or shipping, i.e., improper packaging, which prohibits the use for intended purpose.
i. Packaging specifications inadequate - not complied with. Unsatisfactory conditions including item damage resulting from improper packaging.
3.1 DOAM. The completed Teardown Deficiency Report template, provided in the DOAM Specification attached to the contract, shall comply with the format requirements (see 2. above) so that it can be ingestible into a Product Lifecycle Management (PLM) solution to ensure proper tying, tracing, and linking to the lowest component of the end item to which the delivered Teardown Deficiency Report Information is applicable. Any field that is not applicable shall be marked “NA.”
End of DI-PSSS-81534B.
Source: http://assist.dla.mil -- Downloaded: 2022-10-06T17:08Z
TITLE: COUNTERFEIT PREVENTION PLAN
Number: DI-MISC-81832 Approval Date: 20110121 AMSC Number: 9181 Limitation:
DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NRO Applicable Forms: N/A
Use/Relationship: The Counterfeit Prevention Plan will be used by the procurement activity to determine and evaluate the effectiveness of the contractor’s counterfeit protection plan and award fee.
a. This Data Item Description contains the format and content preparation instructions for the data product generated by the specific and discrete task requirements delineated in the statement of work.
b. This DID is related to Parts, Materials and Processes Selection List (PMPSL).
c. This DID is related to “As Designed” and “As Built” Parts List.
d. The Counterfeit Prevention Plan will be updated as counterfeiting methods evolve to include any new indicators, as well as new prevention processes needed (either discovered directly or provided by the Government).
1. The Counterfeit Prevention Plan shall be in contractor format and shall include the following, as a minimum:
a. Procurement practices and procedures to include procurement of all parts and materials from original qualified parts/materials equipment manufacturer (OEM) or it franchised/authorized distributor.
b. Procurement practices and internal processes used for exceptions to buying from
OEM or OEM franchised distributors in cases where items are no longer available including a process to qualify/certify non-OEM parts & materials.
c. Monitoring procedures to include the delivery of test results from random sampling and supply chains surveillance that does not assume any source is safe to identify possible penetration of OEM supply chain.
d. Training/certification program for receiving inspectors.
e. Process to verify counterfeit.
DI-MISC-81832
- 2 -
f. Processes to identify, store, and report counterfeit parts.
g. Process to ensure subcontracts contain the following requirements (As a minimum):
(1) Requirements to procure only from Original Equipment Manufacturer
(OEM) or OEM franchised distributors
(2) Procurement practices and internal processes used for exceptions to buying from OEM or OEM franchised distributors including a process to qualify/certify non-OEM parts & materials obtained
(3) Requirements to monitor supply (including delivery of test results from random sampling and supply chain surveillance that does not assume any source is safe) to identify possible penetration of OEM supply chain
(4) Training/certification program for receiving inspectors
(5) Process to verify counterfeit
(6) Processes to identify, store, and report counterfeit parts.
(7) Notification procedure (tailored to specific sub-contractor based on following Notification Procedure)
h. Self-audit of internal processes.
i. Monitor processes at all subcontractor levels processes and verify compliance through on-site audits.
j. Notification Procedure:
(1) Step 1: The contractor shall quarantine all suspect products pending further direction. The contractor shall provide a statement, with problem description, justifying why this is considered suspect and how it was detected. The contractor shall NOT notify the supplier that the items are suspected as being counterfeit items. However, consultation with the OEM is authorized. Make certain the parts and all members of the lot procured for use on this contract are stored in correct environmental controls. These parts need to be protected as evidence.
(2) Step 2: Contractors that identify suspect items shall immediately notify their customer that is the next link toward the prime contractor.
Notification shall be passed up the customer chain until reaching the prime contractor. The prime contractor shall immediately notify the cognizant Contracting Officer (CO) and Contracting Office Technical Representative (COTR) of all suspect items identified.
DI-MISC-81832
- 3 -
(3) Step 3: The contractor shall make certain that the original documentation is secured as evidence and maintain any and all documentation associated with the part to include:
a. Part information such as part identifying number, lot date code, manufacturer information and originator/point of contact information
b. Any information reflecting part procurement/acquisition traceability which should include a copy of the purchase order, any and all correspondence between the buyer and the supplier to include: e-mails, records of phone conversations and paper letters of correspondence
c. Part documentation from the purported original manufacturer, distributors and suppliers (certificate of compliance and certificate of conformance)
d. All visual examination and physical analysis/testing results and the technical data package showing that the parts passed the required screening and qualification tests
e. List of company products affected
(4) Step 4: Determine that the part is or is not counterfeit (Usually accomplished as part of root cause analysis of non-conforming parts and/or materials)
(5) Step 5: If the parts are found to be counterfeit, they shall be isolated and controlled pending direction from law enforcement.
(6) Step 6: The contractor shall provide any additional required information to the government’s investigation team
END OF DI-MISC-81832
Title: COMMERCIAL ASSET VISIBILITY (CAV) REPORTING
Number: DI-MGMT-81838 Approval Date: 20110914 AMSC Number: N9211 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility: SA/WSS 071.02 Applicable Forms: N/A
Use/relationship:
The Commercial Asset Visibility (CAV) application provides a web-based, automated method of tracking Government owned reparable assets as they flow through the repair cycle at the contractor's repair facility. The main purpose of CAV is to provide an inventory management system for reparable assets while they are at commercial repair vendors. CAV on the World Wide Web allows the contractor to report transactions as they occur. These transactions automatically update the CAV database. An integrated, relational database allows the commercial repair vendors to access their repair data to produce all of the required status and activity reports.
This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement, as delineated in the contract.
1. Format. The CAV System transactions are processed via the World Wide Web. Input formats and methodology are defined in the Contract Statement of Work.
2. Content. The Contractor reporting shall contain the following transactions, status code changes and report types, as described in the Contract Statement of Work:
A. Receipt of Asset
1) On Contract
2) Not on Contract
3) Procurement
4) "A" Condition
5) Rotable Pool
6) Loaned Asset
B. Inductions C. Items Awaiting Parts D. Re-inductions E. Completions F. Shipments
Source: http://assist.dla.mil -- Downloaded: 2019-05-06T18:27Z
DI-MGMT-81838
G. Bulk Shipments H. Proof of Shipment I. Items that are Beyond Economic Repair (BER) J. Survey/Scrap Items K. Reversals L. Report of Discrepancies M. Print DD Form 1348's N. Print Material Movement Documents O. Print CAV Inventory Labels P. Print Item Action Reports Q. Print Repair History Reports R. Print Condition Code Reports S. Print Awaiting Parts Report T. Print Proof of Shipment Reports U. Perform Item Maintenance V. Print Report of Discrepancies (RODs) W. Add and Delete Carriers
3. End of DI-MGMT-81838.
Source: http://assist.dla.mil -- Downloaded: 2019-05-06T18:27Z
Title: CONTRACT DEPOT MAINTENANCE (CDM) MONTHLY PRODUCTION REPORT Number: DI-PSSS-81995A Approved Date: 20201130 AMSC Number: F10209 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Preparing Activity: 70 (419 SCMS/GUBA) Project Number: PSSS-2020-012 Applicable Forms: N/A Use/Relationship: The Contract Depot Maintenance (CDM) Monthly Production Report provides the Government with monthly maintenance production figures, status and accountability of assets at the contractor facility, performance to schedule, anticipated production for the next month, and a summary of unresolved problems at the end of the report period.
This Data Item Description (DID) contains the format, content, and intended use information for the data deliverable resulting from the work task described in the contract.
a. This DID may be used on any depot level maintenance contract.
b. This DID supersedes DI-PSSS-81995.
Requirements:
1. Reference documents. None.
2. Format. The CDM Monthly Production Report shall be in the Table I format below.
3. Content. The CDM Monthly Production Report shall include the following data, provided by the Production Management Specialist (PMS) and the Contractor, through the end of the month:
3.1 Part I: Blocks 1 through 4 of the report shall contain the following information provided by the PMS:
a. As of date: The day, month, and year (DDMMMYYYY) applicable to the report. Data shall be through the end of the month.
b. Block 1: PMS’s name, PMS’s code, PMS’s email address, and PMS’s phone number.
c. Block 2: Contractor name, the Department of Defense Activity Address Code (DoDAAC) assigned to the contractor for shipment of material, the contractor’s Commercial and Government Entity (CAGE) code, the contractor’s email address, and the contractor’s phone number.
d. Block 3: Contract number and Program (PRGM) or Weapon System (WS) supported.
e. Block 4: Government item manager’s or technical Point of Contact’s (PoC’s) name.
3.2 Blocks A through O of the report shall contain the following information:
a. Block A: Item identification, which shall include the Federal Supply Class (FSC) under
A-1, and the National Item Identification Number (NIIN) of the item being reported under A-2.
b. Block B: Delivery/Call Order number. When the awarded contract is a delivery/call order type, this is the applicable order number. When an item is awarded on more than one order, the order number is repeated for each order until completed. If the current report completes the call, the word “completed” shall be added.
c. Block C: The contract line item number (CLIN), which shall be the CLIN assigned to the National Stock Number (NSN) in the contract.
Source: http://assist.dla.mil -- Downloaded: 2021-01-07T15:21Z
DI-PSSS-81995A
d. Block D: Quantity on contract or delivery order (DO)/call
e. Block E: Reparables received, which shall be the number of reparable items received for repair, and shall include the quantity of reparables received during the report month under E-1 and the cumulative quantity of reparables received from the start of the contract through the report month under E-2.
f. Block F: Miscellaneous (Misc.) assets received that are not part of the contract, in various condition codes, which shall include the quantity received during the report month under F-1 and the cumulative total received from the start of the contract through the report month under F-2.
g. Block G: Reparables (REPS) on hand, which shall be the number of reparables on hand waiting for induction into repair.
h. Block H: Total number of reparables currently inducted (IND) into work.
i. Block I: Quantity of reparables awaiting parts (AWP).
j. Block J: Quantity (QTY) produced (PROD), which shall include the quantity that completed repair and was produced during the report month under J-1 and the cumulative total that completed repair and was produced from the start of the contract through the report month under J-2.
k. Block K: Serviceables (SERV) on hand, which shall be the quantity of serviceables on hand awaiting shipping action.
l. Block L: Serviceables shipped, which shall be the number of serviceables shipped from the repair facility, and shall include the number of serviceables shipped during the report month under L-1 and the cumulative number of serviceables shipped from the start of the contract under L-2.
m. Block M: QTY condemned, which shall include the quantity of reparables condemned during the report month under M-1 and the cumulative quantity of reparables condemned from the start of the contract under M-2.
n. Block N: Misc. Shipped/Condemned Shipped, which shall include the misc. assets received in Block F that are not part of the contract, in various condition codes or condemned assets shipped during the report month under N-1 and the misc. or condemned assets shipped from the start of the contract through the report month under N-2.
o. Block O: Next Month Forecast PROD, which shall be the quantity of items scheduled to be produced next month.
3.3 Part II, Production Summary. A Production Summary shall be included only if:
a. The previously reported production forecast was not shipped,
b. The current production forecast does not equal the contract scheduled quantity, or
c. The Contractor anticipates a problem with production in the near future.
DI-PSSS-81995A
End of DI-PSSS-81995A. 3
This Mo
To Date
This Mo
To Date
This Mo
To Date
This Mo
To Date
This Mo
To Date
This Mo
To Date
FSC NIIN
1 2 2 1 2
H.
QTY IND
TO
WORK
i.
AWP
G.
REPS ON
HAND
(Not
Inducted)
DURING REPORTING PERIOD
K.
SERV ON
HAND
(Not
Shipped)
N.
MISC.
SHIPPED/
CONDEMNED
SHIPPED
4. GOVERNMENT ITEM MANAGER OR
TECHNICAL POC
2. CONTRACTOR/DODAAC/CAGE CODE/EMAIL/PHONE # 3. CONTRACT NUMBER/WS/PRGM
Part II, Production Summary
E.
REPARABLES
RECEIVED
1 1 2 1
L.
SERVICEABLES
SHIPPED
M.
QTY
CONDEMNED
A.
ITEM
IDENTIFICATION
B.
DELIVERY/
CALL ORDER
NUMBER
TABLE I. Format of (CDM) Monthly Production Report Due Date:
Within 10 business days of the previous month's last calendar date
Part I
F.
MISC.
RECEIVED
1 2
J.
QTY
PROD
O.
NEXT
MONTH
FORECAST
PROD
CONTRACT DEPOT MAINTENANCE (CDM) MONTHLY PRODUCTION REPORT
Month and As-Of
Date
(DDMMMYYYY)
1. PMS/PMS CODE/EMAIL/PHONE #
C.
CONTRACT
LINE ITEM
NUMBER
(CLIN)
D.
QTY ON
CONTRACT
OR
DO/CALL
| DID_80441D_GPI_REPORT |
| AMSC Number: 10184 Limitation: N/A |
| Requirements: |
| DID_80503_DR_REPORT |
| DID_80809B_TEST&INSPECT_REPORT |
| DID_81534B_ASDP_REPORT |
| DID_81832_CPP_REPORT |
| DID_81838_CAV_AF_REPORT |
| DID_81995A_CDM-Production_REPORT |