This is a Vendor Pre-Operational Performance Report Card attachment for a Department of Management Services (DMS) contract opportunity. The document outlines twenty-one performance requirements that vendors must meet during the pre-operational phase of a project. Key requirements include preparing and distributing meeting agendas two business days in advance, submitting initial project work plans within twenty business days of contract execution, and preparing a RACI matrix within thirty calendar days of contract signing. Vendors must document change control items within two business days, provide impact assessments within ten business days, and ensure all deliverables meet quality standards through a 10-5-5 review cycle. Additional performance standards address project management obligations such as milestone tracking, weekly status reporting with updated Gantt charts, risk and issue management, stakeholder engagement, and participation in Joint Application Development sessions. The vendor must maintain staffing levels at ninety percent or greater of the approved Staffing Plan and complete all scheduled jobs within the designated timeframe or within two clock hours of the scheduled window.

The performance report card includes requirements for document management, utilizing DMS's Project Online environment as the single repository for all artifacts, tracking risks, issues, action items, and decisions. Vendors must demonstrate compliance with federal and state privacy, confidentiality, and security requirements and submit training plans for approval at least thirty calendar days prior to training delivery, with evaluation results shared within five business days. All written documents and deliverables must demonstrate quality and completeness with proper proofreading, business and technical writing standards that limit ambiguity, appropriate English proficiency, and alignment with Deliverables Expectation Documents. Weekly communication and progress reporting are mandatory, with DMS approval required for any adjustments to timelines or changes to baselined milestone dates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment D: Vendor Pre-Operational Performance Report Card

Report Card #
Category
Report Card Performance Requirement
Status (Met/Not Met)
1.A.001
Agenda and Minutes
Prepare agendas and other materials (as appropriate) and distribute agendas and materials two (2) business days prior to the event.
1.A.002
Change Control
Perform systems maintenance and modifications, as specified in this RFP, for all component parts of the solution, as required by DMS within the mutually agreed-upon timeframes. Document new Change Control items within two (2) business days from the date that the Change Control items are identified. Provide a full impact assessment within ten (10) business days from the date that the Change Order is logged.
1.A.003
Change Management
Prepare and submit to DMS change requests related to scope and operational changes (e.g., system changes, procedural changes, contractual changes) and implement DMS approved changes per the DMS Change Management Plan.
1.A.004
Deliverable and Artifact Management
Ensure all Deliverables and Artifacts are clearly indicated in the Project Work Plan (schedule).

Ensure all Deliverables and Artifacts are delivered per the agreed upon due dates and are managed according to the 10-5-5 review cycle. Ensure all Deliverables and Artifacts have a level of quality and completeness that indicates they have been reviewed and proofread by the Vendor prior to delivery. Ensure all Deliverables and Artifacts meet the requirements as specified in the Deliverables Expectation Document (DED).

1.A.005
Document Management -- Project Management
Utilize DMS’s document repository/Project Online environment as the single repository for all artifacts and activities, including: 1) tracking all risks, issues, action items, decisions, change requests; 2) submission of all deliverables, invoices, status reports, meeting minutes, and other documents; and 3) posting/managing project schedules (work plans).
1.A.006
Document Review
Manage the deliverable review process utilizing the 10-5-5 Review Cycle. Any adjustments to the timeline should be approved by DMS.
1.A.007
Document Standards
Provide all written documents and deliverables with a level of quality and completeness that indicates that they have been reviewed and proofread by the Vendor prior to being delivered to DMS. Indicators of quality and completeness include, but are not limited to: 1) a standard of business and technical writing that limits ambiguity and rework by DMS; 2) a level of English proficiency that limits the need for DMS edits for grammar and clarity; and 3) content that meets expectations as defined in DED and/or alignment discussions.
1.A.008
Joint Application Development
Participate in Joint Application Development (JAD) sessions/meetings.
1.A.009
Project Management
Ensure all milestone dates agreed to with DMS are clearly identified in the project schedule, tracked, and met (on time). Any changes to the baselined milestone dates should be approved by DMS.
1.A.010
Project Management – Project Work Plan
Ensure an initial draft of the Vendor’s schedule (project work plan) is delivered, reviewed, approved, and incorporated into the Master Program Schedule within twenty (20) business days of contract execution. Ensure the schedule (project work plan) is developed and maintained per the DMS Schedule Management Plan and standards. Report progress against the schedule through weekly, written status reports and/or dashboard (or on a frequency agreed-upon by DMS), at weekly review meetings with DMS, and through a weekly update of the schedule (project work plan).
1.A.011
Project Management – RACI Matrix
Prepare a RACI Matrix (utilizing the DMS approved template) outlining the primary roles and responsibilities for the project within thirty (30) calendar days of contract signing. Provide sufficient staff to conduct all project activities. Ensure all onsite requirements are met. Ensure staff onboarding and off-boarding activities are managed per the DMS Resource Management Plan.
1.A.012
Project Management – Risks and Issues
Ensure risks and issues related to the Vendor’s commitments and deliverables are identified, assigned, prioritized, documented timely, communicated, and managed according to the DMS Risk Management Plan and the DMS Issue Management Plan. Ensure all risks and issues are proactively managed and escalated as needed to minimize impact to the project.
1.A.013
Project Management -- Stakeholder Management
Work with DMS to identify key stakeholders, conduct a stakeholder analysis, and plan stakeholder engagement activities and communications according to the DMS Communication Management Plan.
1.A.014
Project Management - Strategic Planning
Facilitate kick-off sessions and strategic planning sessions as needed to plan, establish, document, and communicate the project goals, objectives, direction, and approach to: 1) facilitate stakeholder introductions; and 2) ensure project activities are initiated in an effective (well-planned) and efficient manner.
1.A.015
Project Work Plan - WBS
Develop and maintain a Project Work Plan (schedule) that identifies tasks, milestones, deliverables, dependencies, work effort, duration and resource assignments required for project execution. Deliver schedule updates weekly that reflect actual hours worked, task slippages, and critical path analysis.
1.A.016
Risks, Issues, Decisions, and Action Items
Document new risks, issues, key decisions, and action items within two (2) business days from the date they are identified. This includes clearly documenting the risk, issue, decision, and/or action item, establishing an owner, and establishing a target due date.
1.A.017
Schedule Management
All scheduled jobs should be completed successfully within the scheduled timeframe or within two (2) clock hours of the scheduled timeframe window.
1.A.018
Security
Meet all federal and state privacy, confidentiality, and security requirements within the Vendor’s operation.
1.A.019
Staffing Levels
Ensure the appropriate experienced staffing level is maintained throughout the project to ensure objectives are met on time and with quality. Maintain staffing levels throughout the project at ninety percent (90%) or more of the Staffing Plan. Ensure Vendor staff have the appropriate experience and are dedicated to the project in accordance with the approved Staffing Plan and their role in the Project Plan.
1.A.020
Training
Submit and obtain approval for training (date, time, audience, agenda, and materials) no later than thirty (30) calendar days prior to the training. Ensure training evaluations are conducted for each session and the results are shared with DMS within five (5) business days of the training event.
1.A.021
Weekly Status Reporting
Provide DMS with consistent, complete, accurate, and timely status reports on a weekly basis using a DMS-approved template. This includes an updated Gantt Chart for the project schedule.