Attachment D_Fire Plan_NFSR 462 and 462A.pdf
PDF 222 KB Posted
- Solicitation number
- 127EAX26Q0079-001
About this file
This document is an Emergency and Fire Plan for federal contract work on National Forest lands during fire season.
The contractor must comply with all State and Federal Fire Laws and is responsible for preventing fires caused by project activities, immediately extinguishing controllable fires, and notifying the Forest Service of any fires that cannot be immediately extinguished. The contractor may be held liable for all damages and costs incurred by the Government for fire suppression efforts. All internal combustion engines must be equipped with approved spark arresters per USDA Forest Service Standard 5100-1a or SAE recommended practices, with specific exemptions for turbocharged engines, multi-position engines, and vehicles with factory-designed mufflers. Each piece of equipment requires fire suppression tools including shovels, axes or Pulaskis, and fire extinguishers. A sealed fire toolbox must be located within the operating area containing a 5-gallon backpack pump-type fire extinguisher, two axes, two McLeod fire tools, one serviceable chain saw with at least 20-inch cutting bar, and enough shovels for all employees.
Fire preparedness requirements prohibit smoking during fire season except in barren areas or mineral soil clearings of at least three feet diameter, with designated smoking areas requiring written Forest Service approval. Equipment service areas, parking areas, and gas/oil storage areas must be cleared of inflammable material for at least 50 feet radius. Welding activities must be confined to cleared areas with a minimum 10-foot radius. The contractor must provide a serviceable communication system to contact Forest Service or emergency agencies. Operations are restricted according to an Industrial Fire Precaution Plan with escalating restrictions from Plan A (normal precautions) through Plan D (shutdown of most operations), triggered by fire restriction stages, partial forest closures, and Red Flag Warnings. The contractor must provide a fire guard and comply with operational shutdown schedules that vary by fire precaution level, particularly restricting power saw use, loading, and equipment operation during peak fire danger hours.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Emergency and Fire Plan
A. The Contractor is required to comply with State and Federal Fire Laws during fire season.
The Contractor shall take all steps necessary to prevent his/her employees from setting fires not required in completion of the project.
The Contractor shall be responsible for preventing the ignition of fire that could result from actions for the project and shall take immediate action to extinguish all such fires that can be safely extinguished.
The Contractor must immediately notify Forest Service if a fire indirectly ignited by the Contractor, or the Contractor's agents or employees, cannot be immediately extinguished or escapes the work site.
The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.
B. Contractor Tool and Equipment Guidelines that Meet or Exceed Federal and State Fire Laws
Each internal combustion engine shall be equipped with a spark arrester qualified and rated under USDA Forest Service Standard (Spark Arrester Guide) 5100-1a or the latest revision of Society of Automotive Engineers "medium size engine, SAE recommended practice J350" unless it is:
a. Equipped with a turbine-driven exhaust supercharger such as the turbocharger. There shall be no exhaust bypass.
b. A multi-position engine, such as on power saws purchased after 6/30/77 which must meet the performance levels set forth in the Society of Automotive Engineers "multi-positioned small engine exhaust fire ignition standard, SAE recommended practice J335B" as now or hereafter amended.
Those purchased prior to the above date shall be equipped with an approved spark arrester/muffler containing a 0.023 inch mesh screen in good condition.
c. A passenger carrying vehicle or light truck, or medium truck up to 40,000 GVW, used on roads and equipped with a factory designed muffler and an exhaust system in good working condition.
d. A heavy duty truck, such as a dump or log truck, or other vehicle used for commercial hauling, used only on roads and equipped with a factory designed muffler and with a vertical stack exhaust system extending above the cab.
e. Exhaust equipment described in this Subsection, including spark arresters and mufflers, shall be properly installed and constantly maintained in serviceable condition.
The Contractor should furnish and have available for emergency use on each piece of equipment used in conjunction with performance of the work as listed below, hand tools and/or equipment as follows:
a. One shovel, one axe (or Pulaski) and a fully charged fire extinguisher U.L. rated at 4 B:C or more on each truck, personnel vehicle, tractor, grader and other heavy equipment.
b. One shovel and one backpack 5-gallon water-filled tank with pump with each welder.
c. One shovel and one chemical pressurized fire extinguisher (fully charged) for each gasoline-powered tool, including but not restricted to chain saws, soil augers, rock drills, etc. Fire extinguishers shall be not less than 8-ounce capacity. Shovel must be kept within 100 feet from each chain saw when used off cleared landing areas.
All tools and equipment recommended above should be in good workable condition and should meet the following principal Forest Service guidelines for fire tools:
a. Shovels shall be size "O" or larger and be not less than 46 inches in overall length.
b. Axes (or Pulaski) shall have 2-1/2 pound or larger heads and be not less than 28 inches in overall length.
It is recommended that a sealed box of tools be located within the operating area, at a point accessible in the event of fire. This fire toolbox should at a minimum contain:
a. One 5-gallon, backpack pump-type fire extinguisher filled with water.
b. Two axes
c. Two McLeod fire tools
d. One serviceable chain saw of three and one-half or more horsepower with a cutting bar 20 inches in length or longer
e. Enough shovels so that each employee at the project can be equipped to fight fire.
f. The Contractor should make available this box of firefighting tools for use at location(s) of the work.
The fire toolbox shall remain unlocked but should be sealed to prevent use for other than emergency use only.
C. Fire Preparedness Guidelines that meet or exceed State and Federal Fire Laws
Smoking and Fire Rules. Smoking is not permitted during fire season, except in a barren area or in an area cleared to mineral soil at least three feet in diameter. In areas closed to smoking, the FS Project Administrator may approve special areas to be used for smoking. The Contractor shall sign these areas.
Contractor shall post signs regarding smoking and fire rules in conspicuous places for all employees to see. Contractor's supervisory personnel shall require compliance with these rules. Under no circumstances shall smoking be permitted during fire season while employees are operating light or heavy equipment or walking or working in grass and woodlands.
Storage and Parking Areas. Equipment service areas, parking areas, and gas and oil storage areas shall be cleared of all inflammable material for a radius of at least 50 feet. Small mobile or stationary engine sites shall be cleared of inflammable material for a radius of at least 15 feet from such engine. The FS Project Administrator must approve areas of the type described above prior to use.
Welding. Contractor shall confine welding activity to cleared areas having a minimum radius of ten feet measured from place of welding.
Oil Filter and Glass Jugs. Contractor shall remove from National Forest land all oily rags and used oil filters.
Reporting Fires. The Contractor shall notify the Forest Service of any fires encountered in the vicinity of the project. The Contractor should take control action upon discovery of a fire as safety and conditions allow.
Communications. The Contractor should furnish a serviceable telephone, radiotelephone, or radio system that allows the Contractor to contact the Forest Service or other law enforcement or emergency agencies in the event of a fire or other medical emergency. If the project's location makes communication clearly impractical, the FS Project Administrator will accept a reasonable alternative. The communications system shall be operable during the Contractor's operation in the fire precautionary period and at the time fire patrol person service is required.
D. EMERGENCY FIRE PRECAUTIONS
Contractor will restrict operations in accordance with the attached Emergency Fire Precaution Schedule.
When there is a predicted change, Forest Service shall inform the Contractor by 6:00 pm, Mountain Standard Time (7:00 pm MDT), of the predicted change in the Industrial Fire Precaution Plan. The Project Contact may, after consultation with the Forest Supervisor, adjust the predicted Industrial Fire Precaution Plan for local weather and site conditions on Project Area. These conditions will be determined per the findings of the attached, Project Fire Precautions Assessment, document. Changes in the predicted Industrial Fire Precaution Plan will be provided to the Contractor in writing, at least 5 days in advance of the changes going into effect. These changes may warrant the operation to transition into more stringent Industrial Fire Precautions, such as going from Precaution B to C, even if the “Staged Restrictions” do not change. Or the findings and determinations of site-specific conditions from the Assessment may warrant additional fire tools or equipment to be on site, such as a water tender, size to be determined based on operation and conditions.
EMERGENCY FIRE PRECAUTION SCHEDULE
FIRE RESTRICTION/CLOSURE “STAGE”
“STAGED” RESTRICTION LEVELS INDUSTRIAL FIRE PRECAUTION PLAN
NO RESTRICTIONS A
STAGE I B
STAGE II C
STAGE III (PARTIAL FOREST
CLOSURE) **
C or D
STAGE IV (TOTAL FOREST
CLOSURE)
D
RED FLAG WARNING (Issued by National Weather Service)
D
PARTIAL FOREST CLOSURE
Timber project areas which are outside the boundaries of the partial forest closure may continue to operate under Industrial Fire Precaution Plan “C” operating criteria as agreed upon between the CO and Contractor in writing.
Timber project areas within the boundaries of the proclaimed partial forest closure area are to operate under Industrial Fire Precaution Plan “D”.
Staged restriction levels are determined by the Line Officer in conjunction with Fire Management Officer(s) and Project Contact(s). The process is a mix of quantitative and subjective measures which allows Line Officers a broad level of discretion considering local conditions and issues when deciding to implement fire restrictions and/or area closures.
INDUSTRIAL FIRE PRECAUTION PLAN - DESCRIPTION
A - Normal Fire Precautions. No fire guard required.
B - Normal Fire Precautions except designated areas for smoking and warming or cooking fires require a written permit. Contractor will provide fire guard.
C - All power saws and mechanical fellers except for mechanical fellers equipped with hydraulic shears will shut down from 9:00 am until 8:00 pm Mountain Standard Time (10:00 am to 9:00 pm MDT), except chainsaws may be used from 9:00 am until 2:00 pm Mountain Standard Time (10:00 am to 3:00 pm MDT), for limbing on landings cleared to mineral soil. Loading is authorized to continue from 12:00 noon until 2:00 pm, Mountain Standard Time (1:00 pm to 3:00 pm MDT), on landings cleared to mineral soil. Log hauling trucks must be out of the Project area to a surfaced road by 2:00 pm, Mountain Standard Time (3:00 pm MDT). Shutdown from 12:00 noon until 8:00 pm Mountain Standard Time (1:00 pm to 9:00 pm MDT); all machine treatment of slash;
mechanical equipment used for shearing, bunching, or delimbing; skidding; cable yarding; blasting;
welding; metal cutting; and clearing. Operations on mineral soil involving road excavation, watering, grading, surfacing, rock crushing, and/or other equipment maintenance may continue. No smoking, warming, or cooking fires are permitted at any time. Contractor will provide fire guard.
D - Shutdown all operations; except operations on mineral soil involving road excavation, watering, grading, gravel surfacing, and rock crushing may continue with special Forest Service permit.
Contractor will provide fire guard.
E - Reporting all Wildfires Contractor's employees shall report all fires to any of the following Forest Service facilities and/or personnel listed below, but not necessarily in the order shown:
E. Forest Service Contact List in case of Fire or Other Emergency
Contact Name Office Telephone Cell Telephone Nearest FS Station Mount Taylor
Basic Fire Info 505-287-8833
Nearest FS Station Mountainair
Basic Fire Info 505-847-2990
Nearest FS Station Magdalena
Basic Fire Info 575-854-2281
Nearest FS Station Sandia
Basic Fire Info 505-281-3304
Nearest FS Station Kiowa-Rita Blanca
Basic Fire Info 575-374-9652
Nearest FS Station Black Kettle
Basic Fire Info 580-497-2143
Mount Taylor FMO Adrian Padilla 505-287-8833 505-414-9469 Mountainair FMO Anthony Martinez 505-847-2990 505-506-1971 Magdalena FMO Ken Watkins 575-854-2281 505-681-8736 Sandia FMO Brad Tausan 505-281-3304 x5130 505-362-3613
Black Kettle & Kiowa- Rita Blanca FMO
Matt Lamb 580-497-2143 580-4976954
Project Technical Point of Contact/Inspector
Peggy O’Keefe 505-346-3848 530-708-1677
Project Technical Point of Contact/Inspector
Patrick Burkett 505-346-3883
Mount Taylor Ranger Yolynda Begay 505-287-8833 Mountainair Ranger Ernie Taylor 505-847-2990 Magdalena Ranger (Vacant) 575-854-2281 Sandia Ranger Crystal Powell 505-281-5117 KRB Ranger Mike Atkinson 575-374-9652 575-429-9288 Black Kettle Ranger Tom Smeltzer 580-497-2143 580-497-7712 Cibola Dispatch FIRE #1 505-346-2660
F. Contractor’s Key Personnel to Call in case of Fire or Other Emergency
Contact Name Office Telephone Cell Telephone Administrative Contact Project Contact