About this file

This document is a Specifications Attachment for a contract opportunity issued by the Louisiana Department of Military Affairs (DMA) for window replacement at the Coushatta Readiness Center. The project involves replacing 16 existing windows with Oldcastle Series FG5751T thermal Stormax aluminum hurricane-resistant windows, with specific dimensions of up to 40" W x 49" H. The windows will be glazed with Solarban 70 Gray two tempered outboard lite and include a bronze anodized spacer. The work will be performed at 510 Wilkerson St in Coushatta, LA, with the project contact being SFC Brian Smith and Project Manager Darren Thomas.

The contract specifies comprehensive requirements for the contractor, including field dimension verification, site security, damage prevention, compliance with safety regulations, and provision of personal protective equipment. The contractor must provide a one-year warranty on workmanship and installations, operate during specified hours (Tuesday-Friday, 7:00 AM to 5:30 PM), and complete all work in compliance with OSHA, NEC, and local regulations. Additional responsibilities include utility notification, storage and disposal of materials, pre-approval of specification sheets, and submission of a construction work schedule 48 hours prior to project commencement.

View the file

Other files

File Type Posted
3000025505.pdf PDF
Attachment A - Special Terms and Conditions Pages 1-14.docx DOCX document
Attachment B - Job Site Verification Form - Page 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment C – Specifications RFx 3000025505

**If bidding other than specified, please provide manufacturer’s specs for “or equal” items. **

Scope of Work:

The Contractor shall provide all labor and materials in order to replace 16 windows for the Louisiana Department of Military Affairs (DMA).

Location:

DMA LANG Coushatta Readiness Center Construction and Facilities Management Office 510 Wilkerson St Coushatta, LA 71019

DMA Contact:

SFC Brian Smith; (318) 286-2524 Project Manager Darren Thomas; +1 (318) 450-7536; darren.k.thomas.mil@army.mil

Specifications:

· The Contractor shall protect all paved surface in location for dumpsters with ¾” plywood as applicable.

· The Contractor shall complete any required selective demolition to complete the repairs.

· The Contractor shall remove the existing 16 windows on the exterior of the building and repair any necessary damage to the permanent brick prior to the installation of replacement windows. (See image on page 3)

· The Contractor shall install 16 Aluminum Hurricane resistant windows and Glazing.

· The Contractor shall install 16 Oldcastle Series FG5751T thermal Stormax or equal 2 ½’’ x 5’’ framing up to 40 ¾” W x 49 ¾” H, glazed with 1-5/16” Storm glass made with Solarban 70 Gray two tempered outboard lite, ½’ bronze anodized spacer, two layers of 1/4'’ clear heat strengthened glass with proprietary Storm glass interlayer.

Specify Brand/Model Bidding: _______________________________

General Conditions:

· The Contractor shall be responsible for field verifying all dimensions and existing site conditions of work to be performed. The Contractor shall inspect and verify information provided herein on existing materials and equipment, etc. is correct and inform Project Manager (PM) of any errors or questions prior to commencement of work.

· The Contractor shall make the building, and any sensitive items secure at the end of each workday by any means necessary to secure same and by the approval of the unit Point of Contact (POC).

· The Contractor shall take all precautions necessary to prevent damages when making the repairs. This includes movement and parking of equipment on grass or unimproved areas surrounding site, as well as surrounding walls in stairwell areas.

· All work must comply with all applicable State and Local Safety Environmental requirements. Occupational Safety and Health Administration (OSHA), National Electrical Code (NEC), Parish, City and State regulation will be required. The Contractor shall supply all employees with PPE.

· The Contractor shall call LA 1-Call and all utility companies prior to digging (If necessary)

· The Contractor shall warranty their workmanship, repairs, and installations for a minimum of a one-year period.

· Hours of operation Tuesday- Friday, 7:00 AM to 5:30 PM and closed on all recognized state and federal holidays.

· The Contractor shall contact, prior to mobilization and demobilization, the Project Manager for staging and for satisfactory completion.

· The Contractor shall be responsible for providing any storage containers. If an onsite storage area is required, the Contractor must confirm a storage location for any materials, fixtures, equipment, trailers, etc. stored on site during the term length of the contract. The location shall be approved by the Project Manager during the pre- construction meeting.

· The Contractor shall be responsible for disposal and storage of all materials being removed or installed throughout the project.

· The Contractor shall provide warranty information for the materials used in completing this project.

· The Contractor shall provide a construction work schedule (Gnant like) 48 hours prior to start of work detailing each task of work.

· All specification sheets and submittals must be pre-approved by the Project Manager prior to ordering.

Weather Days are included in the contract time.