Attachment C - Specifications - Pages 1-2.docx

DOCX document 19 KB Posted

Attached to
Metal Buildings Construction - DOC
Solicitation number
3000024457
Issued by
East Feliciana Parish, Baton Rouge City, Louisiana

About this file

Attachment C - Specifications is a Scope of Work document for the Louisiana Department of Corrections (DOC) soliciting construction services for three metal buildings at Dixon Correctional Institute in Jackson, LA. The project involves constructing three distinct structures: a 30' x 60' Maintenance Equipment Shed with five 12' equipment bays, a 24' x 40' x 10' Compound Three Hobby Shop Enclosure requiring steel wall sheeting and specific window and door installations, and a 30' x 30' Maintenance Bay #2 with two 15' equipment bays. Work is to be performed Monday through Friday from 7:00 am to 3:30 pm, with the contractor responsible for material disposal and subject to strict facility entry protocols.

The solicitation requires contractors to provide all materials, labor, equipment, and tools for construction, with significant security considerations including mandatory vehicle and personnel searches, background checks, and compliance with institutional policies. Contractors must attend a post-contract execution conference/training with facility staff before commencing work. Site visits are available by contacting Will Bunch at 225-634-6101, and contractors must adhere to specific building specifications including concrete post installations, varying building heights, and precise dimensional requirements for each structure. No specific pricing, funding sources, or contract term details are provided in this specification document.

View the file

Other files

File Type Posted
Attachment A - Special Terms and Conditions Pages 1-14.docx DOCX document
3000024457.pdf PDF
Attachment B - Job Site Verification Form - Page 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment C – Specifications RFx 3000024457

Scope of Work:

The Contractor shall furnish all materials, labor, equipment, and tools needed to construct three metal buildings for the Louisiana Department of Corrections (DOC).

Location:

Dixon Correctional Institute 5568 Highway 68 Jackson LA 70748

Site Visit Contact:

Will Bunch 225-634-6101

Building #1 Maintenance Equipment Shed specifications:

· The Contractor shall build a steel building off of an existing one.

· The building shall be 30’ wide by 60’ long.

· The building height shall start off at 17’ high at the existing building and slope down to 13’ at the end of the new building.

· The building shall have five 12’ bays to park equipment in.

· The Contractor shall concrete main post in the ground.

Building #2 – Compound Three Hobby Shop Enclosure specifications:

· The Contractor shall build steel wall sheeting onto an existing 24’ by 40’ by 10’ building.

· The walls shall include four 36” x 36” windows.

· The walls shall include two 36” steel personal doors and one steel roll door to be 10’ by 8’.

Building #3 – Maintenance Bay #2 specifications:

· The Contractor shall build a steel building off of an existing one.

· The building shall be 30’ wide by 30’ long.

· The building height shall start off at 17’ high at the existing building and slope down to 13’ at the end of the new building.

· The building shall have two 15’ bays to park equipment in.

· The Contractor shall concrete main post in the ground.

General Terms and Conditions:

· Warranty if applicable

· Work shall be performed Monday-Friday from 7:00 am – 3:30 pm.

· The Contractor’s representatives are subject to a search of their vehicles, possessions and persons. This is necessary to preclude the introduction of weapons, ammunition, explosives, cell phones, alcohol, escape devices, drugs and drug paraphernalia or other forbidden items or contraband into the prison environment. All searches of visitors will be conducted in accordance with Department Regulation No. C-02-005 and Penitentiary Directive No. 09.004 and 09.004A.

· The Contractor’s representatives are subject to a background check.

· The Contractor’s representatives must follow all institutional policies and procedures while performing work on facility grounds.

· The Contractor is subject to a conference/training with facility staff after the contract is executed and before performing any work.

· Disposal of all materials, and debris shall be the responsibility of the Contractor.