Attachment C-Financial Management Reporting (NF 533).pdf

PDF 66 KB Posted

Attached to
NRESS III RFP 80HQTR26R0002
Solicitation number
80HQTR26R0002
Issued by

About this file

This document is a Financial Management Reporting Requirements attachment for a NASA solicitation (80HQTR26R0002) with a contract yet to be determined. The document outlines detailed reporting requirements for contractors using NASA 533 series reports, specifying that individual reports must be submitted for each Task Order and a cumulative summary report. Contractors are required to provide cost data across multiple categories including prime and subcontractor direct labor hours, direct labor costs, overhead expenses, and other direct costs (ODCs).

Key reporting stipulations include submitting an initial report within 30 working days after contract award, with subsequent monthly (NF 533M) and quarterly (NF 533Q) reports distributed by specific deadlines. Contractors must also include narrative explanations for any variances exceeding 10% between estimated and actual labor hours or costs, detailing the reason for the variance, its impact on the task order, and specific corrective actions. The reports must break down costs by labor categories, overhead, G&A expenses, and include a total cost-plus-fixed-fee calculation, following NASA Procedural Requirements NPR 9501.2E for financial management reporting.

View the file

Other files

File Type Posted
AMD 05-Attachment A-SOW.pdf PDF
NRESS III 80HQTR26R0002 Questions and Answers 1-163.xlsx XLSX spreadsheet
AMD 04-Enclosure 3-GPM Labor Hours and PDs.pdf PDF
AMD 04-NRESS III SF30 80HQTR26R0002.pdf PDF
NRESS III 80HQTR26R0002 Questions and Answers 1-164.pdf PDF
AMD 3-NRESS III SF30 80HQTR26R0002.pdf PDF
NRESS III 80HQTR26R0002 Questions and Answers 1-56.pdf PDF
AMD 2-Exhibit 1A-1B All IDIQ Std by CY.xlsx XLSX spreadsheet
AMD 2-Attachment A-SOW.pdf PDF
AMD 2-Exhibit 2-11 All IDIQ by CY.xlsx XLSX spreadsheet
AMD 2-NRESS III RFP 80HQTR26R0002.pdf PDF
Amendment 01-NRESS III SF30 80HQTR26R0002.pdf PDF
ELibrary 16-Human Research Program Work Plan H-12-Redacted.pdf PDF
ELibrary 18-Lunar Data Analysis Program Work Plan S-311-Redacted.pdf PDF
ELibrary 5-Split-Funding Advice to Award Office Ex.pdf PDF
ELibrary 7-Correspondence-Selected Notification Letter.pdf PDF
ELibrary 10-Correspondence-Declined Notification Letter.pdf PDF
ELibrary 12-Ex Step-1 Encourage Letter.pdf PDF
ELibrary 17-Management and IT Support Work Plan M-04-Redacted.pdf PDF
ELibrary 19-Discovery AO 2019 Work Plan S-346-Redacted.pdf PDF
ELibrary 2-NSPIRES System Diagram.pdf PDF
ELibrary 3-Panel Review Evaluation Ex.pdf PDF
ELibrary 8-Correspondence-Courtesy Status.pdf PDF
ELibrary 9-Correspondence-Selectable.pdf PDF
ELibrary 11-Ex Step-1 Discourage Letter.pdf PDF
ELibrary 20-Space Technology Research Grant Work Plan T-23-Redacted.pdf PDF
ELibrary 1-NSPIRES IT and Software Components.pdf PDF
ELibrary 4-Selection and Evaluation Statement Ex.pdf PDF
Attachment G-Contract Historical Data.pdf PDF
Attachment H-OCI Avoidance Plan.pdf PDF
Attachment J-OCI DRD.pdf PDF
Enclosure 1-Contract Historical Data-Incumbent.pdf PDF
Enclosure 4-QASP.pdf PDF
Exhibit 2-11 All IDIQ by CY.pdf PDF
Attachment E-Contract Data Requirements List.pdf PDF
Attachment I-Information Systems Security Plan.pdf PDF
Attachment K-Security Requirements DRD.pdf PDF
Attachment L-Requirements Statements List.pdf PDF
Enclosure 3-GPM Labor Hours and PDs.pdf PDF
Enclosure 6-RTO 2.pdf PDF
Enclosure 7-RTO 3.pdf PDF
Enclosure 8-Optional C-SCRM Questionnaire.pdf PDF
NRESS III RFP 80HQTR26R0002.pdf PDF
Attachment A-SOW.pdf PDF
Attachment B -DL Rates_ Indirect Rates_ and Fee.pdf PDF
Attachment D-GFP.pdf PDF
Attachment F-DOL Wage Determination 2015-4281.pdf PDF
Enclosure 2-Past Performance Questionnaire.pdf PDF
Enclosure 5-RTO 1.pdf PDF
Exhibit 1A-1B All IDIQ Std by CY.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

SOLICITATION 80HQTR26R0002

CONTRACT TBD

Contract TBD

Attachment C

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

An individual 533 Report shall be provided for each Task Order in addition to a cumulative 533 Report summarizing all Task Orders issued. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus [10] percent (+/- [10]%) between the

Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total

Cost amount shown in the current month for each individual task order. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth

(10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

(06/2014) 3

Prime Direct Labor Hours – Offsite

(List applicable labor categories)

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours – Offsite

Subcontractor B Direct Labor Hours – Offsite

Subcontractor C Direct Labor Hours – Offsite

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours:

Total Prime and Subcontractors Hours – Offsite

Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Prime Direct Labor Costs – Offsite

Total Prime Direct Labor Costs

5. Prime Overhead Expenses:

Offsite Overhead

Total Prime Overhead

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

(06/2014) 4

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)