Attachment C-Drawings-VA-LA-Pineville-Replace-Elevators-502-24-102.pdf
PDF 31 MB Posted
- Solicitation number
- 36C77626R0101
About this file
This document is a set of architectural drawings for the replacement and modernization of elevators at Alexandria VA Medical Center in Alexandria, Louisiana, serving as Attachment C to the solicitation for Project 502-24-102.
The project encompasses modernization and replacement of elevators in Building 7 and Building 9 at the facility. Building 7 work includes: upgrading interiors and doors of traction elevators (Elevators 1 and 2), retrofitting and modernizing a hydraulic medical records elevator (Elevator 3), and retrofitting and modernizing a traction cartlift serving sterile processing department with two stops spanning five floors (Elevator 4 and 5). Building 9 requires retrofit and modernization of two hydraulic elevators serving the entire building. The drawings indicate that construction must be phased with only one elevator per building operational during work at any given time, and both buildings may be worked on simultaneously. Work on levels 2 and 3 involving door and jamb replacement must occur outside regular business hours. All work must comply with ICRA (Infectious Control Risk Assessment) Class II, III, and IV requirements as specified in specification section 01 35 26 - Safety Requirements, with temporary barriers, HEPA-equipped exhaust systems, and adhesive walk-off mats required at construction entrances. The 102-sheet drawing set includes floor plans for all levels (basement through penthouse), ICRA plans showing construction zone isolation for each phase, demolition plans, reflected ceiling plans, and detailed architectural, mechanical, electrical, and fire protection drawings. The design team includes Spees Design Build as architect/engineer of record and Northbay Elevator as the elevator consultant. The drawings are dated March 24, 2026 (100% Construction Documents phase) and comply with NFPA 101 Life Safety Code and International Building Code 2024, with the VA serving as the Authority Having Jurisdiction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCHITECT
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
PHONE: (206) 590-2118
DESIGN TEAM
FIRE PROTECT
ELECTRICAL
PLUMBING
MECHANICAL
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
PHONE: (206) 590-2118
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
PHONE: (206) 590-2118
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
PHONE: (206) 590-2118
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
PHONE: (206) 590-2118
ELEVATOR
NORTHBAY ELEVATOR
PHONE: (707) 583-3100
3715 SANTA ROSA AVE
SANTA ROSA, CA 95407
PROJECT INFORMATION
STATE:
COUNTY:
JURISDICTION:
OWNER:
SITE ZONING:
CONST TYPE:
OCCUPANCY:
CODE ANALYSIS PROJECT DESCRIPTION
MODERNIZATION AND REPLACEMENT OF
ELEVATORS IN BUILDING 7 AND BUILDING 9 AT
ALEXANDRIA VA MEDICAL CENTER.
BUILDING 7:
1. TRACTION ELEVATORS. SCOPE LIMITED
TO UPGRADING THE INTERIORS AND
DOORS.
2. MEDICAL RECORDS ELEVATOR -
HYDRAULIC ELEVATOR THAT WILL
REQUIRE RETROFIT AND
MODERNIZATION.
3. STERILE PROCESSING DEPARTMENT
CARTLIFT - TRACTION ELEVATOR WITH
ONLY TWO STOPS AND SPANNING 5
FLOORS. ELEVATOR WILL REQUIRE
RETROFIT AND MODERNIZATION.
BUILDING 9:
1. TWO HYDRAULIC ELEVATORS SERVING
THE BUILDING WILL REQUIRE RETROFIT
AND MODERNIZATION.
APPLICABLE BUILDINGS
BUILDING 7 & BUILDING 9
ICRA CLASS REQUIREMENTS
SEE ICRA SHEET(S) & SPEC SECTION 01 35 26 -
SAFETY REQUIREMENTS
LOUISIANA
RAPIDES PARISH
ALEXANDRIA
GOV, VETERANS AFFAIRS
SEE FIRE LIFE SAFETY SHEET(S)
SEE FIRE LIFE SAFETY SHEET(S)
GENERAL NOTES
1. DO NOT SCALE DRAWINGS.
BUILDING 9
BUILDING 7
BUILDINGS IN SCOPE OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
G-001
COVER SHEET
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
REPLACE ELEVATORS IN BLDG 7 & BLDG 9
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
PROJECT #: 502-24-102
DRAWING INDEX
PAGE # SHEET # SHEET NAME
GENERAL
1 OF 102 G-001 COVER SHEET
2 OF 102 GS101 PHASING PLAN - BUILDING 7
3 OF 102 GS102 PHASING PLAN - BUILDING 9
ARCHITECTURAL
4 OF 102 A-001 ARCH SYMBOLS, ABBREVIATIONS, & GENERAL NOTES
5 OF 102 AS100 BUILDING 7 - ICRA PLANS - ELEVATORS 1 & 2
6 OF 102 AS101 BUILDING 7 - ICRA PLANS - ELEVATORS 1& 2
7 OF 102 AS102 BUILDING 7 - ICRA PLANS - ELEVATOR 3 & ROOM 29
8 OF 102 AS103 BUILDING 7 - ICRA PLANS - ELEVATORS 4, 5
9 OF 102 AS104 BUILDING 7 - ICRA PLANS - ELEVATORS 4, 5
10 OF 102 AS105 BUILDING 7 - ICRA PLANS - ELEVATORS 4, 5
11 OF 102 AS106 BUILDING 7 - ICRA PLANS - MED RECORDS & SPS CARTLIFT
12 OF 102 AS107 BUILDING 7 - ICRA PLANS - PENTHOUSE
13 OF 102 AS108 BUILDING 9 - ICRA PLANS
14 OF 102 AS109 BUILDING 9 - ICRA PLANS
15 OF 102 AS110 BUILDING 9 - ICRA PLANS
16 OF 102 A-100 BUILDING 7 - BASEMENT - OVERALL FLOOR PLAN
17 OF 102 A-101 BUILDING 7 - LEVEL 01 - OVERALL FLOOR PLAN
18 OF 102 A-102 BUILDING 7 - LEVEL 02 - OVERALL FLOOR PLAN
19 OF 102 A-103 BUILDING 7 - LEVEL 03 - OVERALL FLOOR PLAN
20 OF 102 A-104 BUILDING 7 - LEVEL 04 - OVERALL FLOOR PLAN
21 OF 102 A-105 BUILDING 7 - PENTHOUSE - OVERALL FLOOR PLAN
22 OF 102 A-106 BUILDING 9 - LEVEL 01 - OVERALL FLOOR PLAN
23 OF 102 A-107 BUILDING 9 - LEVEL 02 - OVERALL FLOOR PLAN
24 OF 102 A-108 BUILDING 9 - LEVEL 03 - OVERALL FLOOR PLAN
25 OF 102 A-109 BUILDING 9 - PENTHOUSE - OVERALL FLOOR PLAN
26 OF 102 AD100 BUILDING 7 - BASEMENT - DEMO ENLARGED PLANS
27 OF 102 AD101 BUILDING 7 - LEVEL 01 - DEMO ENLARGED PLANS
28 OF 102 AD102 BUILDING 7 - LEVEL 02 - DEMO ENLARGED PLANS
29 OF 102 AD103 BUILDING 7 - LEVEL 03 - DEMO ENLARGED PLANS
30 OF 102 AD104 BUILDING 7 - LEVEL 04 - DEMO ENLARGED PLANS
31 OF 102 AD106 BUILDING 7 - PENTHOUSE - DEMO ENLARGED PLANS
32 OF 102 AD107 BUILDING 9 - LEVELS 01, 02, 03, PH. - DEMO ENLARGED PLANS
33 OF 102 AD110 BUILDING 7 - BASEMENT - DEMO ENLARGED RCP
34 OF 102 AD111 BUILDING 7 - LEVEL 01 - DEMO ENLARGED RCP
35 OF 102 AD112 BUILDING 7 - LEVEL 02 - DEMO ENLARGED RCP
36 OF 102 AD113 BUILDING 7 - LEVEL 03 - DEMO ENLARGED RCP
37 OF 102 AD114 BUILDING 7 - LEVEL 04 - DEMO ENLARGED RCP
38 OF 102 AD116 BUILDING 7 - PENTHOUSE - DEMO ENLARGED RCP
39 OF 102 AD117 BUILDING 9 - LEVELS 01, 02, 03, PH. - DEMO ENLARGED RCP
40 OF 102 AE100 BUILDING 7 - BASEMENT - ENLARGED PLANS
41 OF 102 AE101 BUILDING 7 - LEVEL 01 - ENLARGED PLANS
42 OF 102 AE102 BUILDING 7 - LEVEL 02 - ENLARGED PLANS
43 OF 102 AE103 BUILDING 7 - LEVEL 03 - ENLARGED PLANS
44 OF 102 AE104 BUILDING 7 - LEVEL 04 - ENLARGED PLANS
45 OF 102 AE105 BUILDING 7 - PENTHOUSE - ENLARGED PLANS
46 OF 102 AE106 BUILDING 9 - LEVELS 01, 02, 03, PH. - ENLARGED PLANS
47 OF 102 AC100 BUILDING 7 - BASEMENT - ENLARGED RCPS
48 OF 102 AC101 BUILDING 7 - LEVEL 01 - ENLARGED RCPS
49 OF 102 AC102 BUILDING 7 - LEVEL 02 - ENLARGED RCPS
50 OF 102 AC103 BUILDING 7 - LEVEL 03 - ENLARGED RCPS
51 OF 102 AC104 BUILDING 7 - LEVEL 04 - ENLARGED RCPS
52 OF 102 AC105 BUILDING 7 - PENTHOUSE - ENLARGED RCPS
53 OF 102 AC106 BUILDING 9 - LEVELS 01, 02, 03, PH. - ENLARGED RCPS
54 OF 102 A-601 ROOM FINISH SCHEDULE, DETAILS
55 OF 102 A-602 BLDG 7 - ELEVATOR SCOPE
56 OF 102 A-603 BLDG 7 - ELEVATOR SCOPE
57 OF 102 A-604 BLDG 7 & 9 - ELEVATOR SCOPE
FIRE PROTECTION
58 OF 102 F-001 FIRE PROTECTION GENERAL NOTES & ABBREVIATIONS
59 OF 102 F-101 BUILDING 7 - BASEMENT OVERALL FIRE PROTECTION FLOOR PLAN
60 OF 102 F-102 BUILDING 7 - PENTHOUSE -OVERALL FIRE PROTECTION FLOOR PLAN
61 OF 102 FD401 BUILDING 7 - FIRE PROTECTION - DEMOLITION ENLARGED PLANS
62 OF 102 F-401 BUILDING 7 - FIRE PROTECTION - ENLARGED PLANS
MECHANICAL
63 OF 102 M-001 MECHANICAL GENERAL NOTES & ABBREVIATIONS
64 OF 102 M-002 MECHANICAL LEGENDS
65 OF 102 M-101 BUILDING 7 - BASEMENT - OVERALL FLOOR PLAN
66 OF 102 M-102 BUILDING 7 - PENTHOUSE - OVERALL FLOOR PLAN
67 OF 102 M-103 BUILDING 9 - PENTHOUSE - OVERALL FLOOR PLAN
68 OF 102 MD401 BUILDING 7 - PENTHOUSE - ENLARGED DEMOLITION PLANS
69 OF 102 M-401 BUILDING 7 - BASEMENT - ENLARGED PLANS
70 OF 102 M-402 BUILDING 7 - PENTHOUSE - ENLARGED PLANS
71 OF 102 M-403 BUILDING 9 - PENTHOUSE ENLARGED FLOOR PLAN
72 OF 102 M-501 MECHANICAL DETAILS
73 OF 102 M-601 MECHANICAL SCHEDULES
ELECTRICAL
74 OF 102 E-001 ABBREVIATIONS, GENERAL NOTES, AND SHEET INDEX
75 OF 102 E-002 ELECTRICAL LEGENDS
76 OF 102 E-100 BUILDING 07 - BASEMENT - OVERALL FLOOR PLAN
77 OF 102 E-101 BUILDING 07 - PENTHOUSE - OVERALL FLOOR PLAN
78 OF 102 E-102 BUILDING 09 - LEVEL 01 - OVERALL FLOOR PLAN
79 OF 102 E-103 BUILDING 09 - PENTHOUSE - OVERALL FLOOR PLAN
TRUE
NORTH
NOT TO SCALE
FACILITY SITE PLAN
SIGNATURES
DIRECTOR
ASSOCIATE DIRECTOR
CHIEF ENGINEERING
COR
SAFETY OFFICER
INFECTION CONTROL
Revisions: Date:
DRAWING INDEX
PAGE # SHEET # SHEET NAME
80 OF 102 E-401 BLDG 07 - PENTHOUSE- ENLARGED ELECTRICAL PLANS
81 OF 102 E-402 BLDG 07 - BASEMENT - ENLARGED ELECTRICAL PLANS
82 OF 102 E-403 BLDG 07 - ELECTRICAL ROOM 29 - ENLARGED ELECTRICAL PLANS
83 OF 102 E-404 BLDG 07 - BASEMENT - ENLARGED ELECTRICAL PLANS
84 OF 102 E-405 BLDG 07 - PENTHOUSE - ENLARGED ELECTRICAL PLANS
85 OF 102 E-406 BLDG 07 - BASEMENT - ENLARGED ELECTRICAL PLANS
86 OF 102 E-407 BLDG 07 - BASEMENT - ENLARGED ELECTRICAL PLANS
87 OF 102 E-408 BLDG 07 - BASEMENT - ENLARGED ELECTRICAL PLANS
88 OF 102 E-409 BLDG 9 - PENTHOUSE - ENLARGED ELECTRICAL PLANS
89 OF 102 E-410 BLDG 9 - LEVEL 01 - ENLARGED ELECTRICAL PLANS
90 OF 102 E-501 ELECTRICAL DETAILS
91 OF 102 E-502 BUILDING 07 ELECTRICAL DETAILS
92 OF 102 E-503 BUILDING 09 ELECTRICAL DETAILS
93 OF 102 EF601 FIRE ALARM RISER DIAGRAM
94 OF 102 E-601 BUILDING 07 - ONE-LINE DIAGRAMS - EXISTING - PART 1 OF 2
95 OF 102 E-602 BUILDING 07 - ONE-LINE DIAGRAMS - EXISTING - PART 2 OF 2
96 OF 102 E-603 BUILDING 09 - ONE-LINE DIAGRAMS - EXISTING
97 OF 102 E-611 BUILDING 07 - ONE-LINE DIAGRAMS - REVISED - PART 1 OF 2
98 OF 102 E-612 BUILDING 07 - ONE-LINE DIAGRAMS - REVISED - PART 2 OF 2
99 OF 102 E-613 BUILDING 09 - ONE-LINE DIAGRAMS - REVISED
100 OF 102 E-701 ELECTRICAL SCHEDULES
101 OF 102 E-702 ELECTRICAL SCHEDULES
102 OF 102 E-703 ELECTRICAL SCHEDULES
03/23/2026
UP
UP
PB
PB
A
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA BB CC DD EE FF GG HH II JJ KK LL MM NN OO PP
CLOSET
HAC
11E
SPD BULK
STORAGE
SPD ADMIN
23B
CLERK
23C
CHIEF
ASST CHIEF
23A
DISPATCH AREA
CART
25A
HAC
34B
PROCUREMENT
TR
TLT
MECH CHASE
STOR
H.K. RM.
OFFICE
5PBX
5ABREAK
5B
ELEC SWITCH
STORAGE
TRANSFORMER
ELECTRICAL
SWITCHGEAR
STAIR
PIPE BASEMENT
MEDICAL
RECORDS
MECH
15A
PIPE BASEMENT
LINEN CHUTE
PIPE BASEMENT
PREP ASSEMBLY
35STERL
MECHANICAL
EQUIPMENT
MECH CHASE
BM2
MENS LOCKER
26 TLT
26A
WOMEN'S LOCK
TLT
ETO
DECONTAM
TRASH
ELEC
29ELEC
STAIR
MECH CHASE
BM4
STERILE/NONSTERILE
STORAGE
EXTERIOR SILVER
RECOV
EXTERIOR MED
GAS
ASST CHIEF
OFFICE
40-
BM5 STAIR
SECRETARY
OFFICE
CHIEF OFFICE
41B
CLEAN LINEN
SUPPLY
TELEPHONE/COMPUTER
IRM OFFICES
LOBBY
BM1
STORAGE
ENTRY
1A
OFFICE
1B
OFFICE
1C
OFFICE
SPECIMEN
STORAGE
11B
AUTOPSY
11A
VEST
BATH
11C
MORGUE
11D
WORK AREA
WORK AREA
WORK AREA
WORK AREA
57D
OFFICE
57E
WORK AREA
57C
BIOMEDICAL
ENGINEERING
FILES
57A
RECEIVING &
CLEANING
MECHANICAL
EQUIPMENT
BATTERY
FILES
57B
EMS LOCKERS
54 IRM SOFTWARE
SUPPORT
STAIR
TLT
TLT
HAC
BM6
COMPUTER
STOR
STOR
45A
TLT
TLT
STOR
52A
PIPE BASEMENT
LOBBY
LOBBY
E-3
CORRIDOR
ELEV
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
ELEVATOR
ELEV-3
CARTLIFT
ELEVATORS TO BE RENOVATED IN
TWO PHASES. TO DO ONE ELEVATOR
PER PHASE.
ELEVATORS TO BE RENOVATED IN
TWO PHASES. TO DO ONE ELEVATOR
PER PHASE.
OUT OF SCOPE
2 HR FIRE RATED WALL (EXISTING)
1 HR FIRE RATED WALL (EXISTING)
SMOKE RATED WALL (EXISTING)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
GS101
PHASING PLAN - BUILDING 7
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
PROJECT
NORTH
TRUE NORTH
(DASHED)
Revisions: Date:
1/16" = 1'-0"
BUILDING 7 - BASEMENT - PHASING PLAN
LEGEND
GENERAL NOTES
1. BOTH BUILDINGS MAY BE WORKED ON AT THE SAME TIME,
BUT ONLY ONE ELEVATOR PER BUILDING MAY BE WORKED
ON AT A TIME.
2. COORDINATE ORDER OF ELEVATOR PHASING WITH THE VA
COR.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A
B
C
D
E
F
G
H
I
OCCUP. THERAPY
GROUP EXERCISE
TRASH AREA
PATIENT LAUNDRY
SOILED LINEN COLLECTION
PATIENT CLOTHES
M STAFF LOCKERS
F STAFF LOCKERS
RECREATION THERAPY STORAGE
ELEC
VRS LOBBY
121A
CORRIDOR
121B
CORRIDOR
121C
VRS
121D
VRS WORKROOM
121E
VRS PROGRAM MANAGER
121F
VHS BREAK ROOM
121G
VRS CONF
121H
VRS PEER
121J
VRS PSA
121K
COPY
121L
STOR
121M
PSYCHOLOGY
VRS
DINING
STOR
122A
ELEC
122B
INPATIENT PA
PATIENT WAITING
PATIENT WAITING
PTSD TESTING ROOM
124A
PSYCOLOGY
124B PDSD PSYCH
124C
PSYCHOLOGY
124D
PTSD MSA
124E
F TLT
125B
M TLT
125C
PTSD
125D
PTSD
125E
PTSD
125F
PTSD
125G
VESTIBULE
RECREATION THERAPY OFFICE
ELEC
INPATIENT DIETARY
PTSD
PSYCH INTERN
PSYCH INTERN
SW RECOVERY
ACOS MH
ASST HEAD NRUSE
INPATIENT PSYCH
TLT
ELEC
CLO
TLT
STORAGE
HAC
CHAPLAIN
GROUP AREA
108INPT SOC WORK
109STOR.
110A
STORAGE
111A
TELEPHONE EQUIPMENT
115A
STOR
115B
WATER HEATER
115C
ELEC EQUIP
115D
M STAFF TLT
116A
F STAFF TLT
117A
MH AO
127A
DACOS MH
127B
BREAK EQUIP
127C
ACOS MH
127D
CORRIDOR
100A
CORRIDOR
100C
CORRIDOR
100B
CORRIDOR/ELEV LOBBY
100D CLERKS
125A
CORRIDOR
CORRIDOR
CORRIDOR
122C
STAIR
STAIR
STAIR
ELEVATOR
ELEVATOR
OUT OF SCOPE
2 HR FIRE RATED WALL (EXISTING)
1 HR FIRE RATED WALL (EXISTING)
SMOKE RATED WALL (EXISTING)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
GS102
PHASING PLAN - BUILDING 9
MK Author
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/8" = 1'-0"
BUILDING 9 - PHASING PLAN
ELEVATORS TO BE RENOVATED IN
TWO PHASES. TO DO ONE
ELEVATOR PER PHASE.
Revisions: Date:
LEGEND
GENERAL NOTES
1. BOTH BUILDINGS MAY BE WORKED ON AT THE SAME TIME,
BUT ONLY ONE ELEVATOR PER BUILDING MAY BE WORKED
ON AT A TIME.
2. COORDINATE ORDER OF ELEVATOR PHASING WITH THE VA
COR.
101A
EXTERIOR ELEVATION
INTERIOR ELEVATION
BUILDING SECTION FLAG
WALL SECTION FLAG
CALLOUT FLAG
VERTICAL GRID LINE
HORIZONTAL GRID LINE
TRUE NORTH ARROW
PROJECT NORTH ARROW
(TRUE NORTH DASHED)
ELEVATION / LEVEL MARKER
KEY NOTE
ROOM TAG
(SF OPTIONAL)
CEILING HEIGHT TAG
WALL TAG
FLOOR TAG
ROOF TAG
DOOR TAG
WINDOW TAG
SPECIALTY EQUIPMENT TAG
SIGNAGE TAG
SIGNAGE KEY NOTE
(AW SHEETS ONLY)
SIGNAGE MATERIAL TAG
(AW SHEETS ONLY)
TOILET
150 SF
A
01A
TRUE
NORTH
W1
PROJECT
NORTH
TRUE NORTH
(DASHED)
A01
D88
A5175SOAP DISH
ACT 2x2
9' - 0" AFF
F-1
R-1
SYMBOLS
A-101
A-101
A-101
EXISTING TO REMAIN
NEW CONSTRUCTION
TO DEMOLISH
(DEMO SHEET(S) ONLY)
ABOVE
BELOW
EXISTING DOOR TO REMAIN
EXISTING DOOR TO DEMOLISH
(DEMO SHEET(S) ONLY)
NEW DOOR
AREA SHOWN ON SHEET
OUT OF SCOPE
INACCESSIBLE DURING PHASE
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA BOUNDRY
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA BARRIER
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA DOOR
(ICRA SHEET(S) ONLY)
ADHESIVE WALK-OFF MATS
(ICRA SHEET(S) ONLY)
TEMPORARY ICRA AIR PRESSURE
(ICRA SHEET(S) ONLY)
CONTRACTOR PATH OF TRAVEL
(ICRA SHEET(S) ONLY)
SMOKE COMPARTMENT PERIMETER
(FIRE LIFE SAFETY SHEET(S) ONLY)
SMOKE RATED WALL
1 HR FIRE RATED WALL
2 HR FIRE RATED WALL
SMOKE & 1 HR FIRE RATED WALL
FIRE EXTINGUISHER CABINET
(FIRE LIFE SAFETY SHEET(S) ONLY)
EMERGENCY EGRESS ROUTE
(FIRE LIFE SAFETY SHEET(S) ONLY)
SPRINKLER PER FIRE PROTECTION
DIFFUSER PER MECHANICAL
(SIZE & PROPORTION MAY VARY)
LIGHT FIXTURE PER ELECTRICAL
(SIZE & PROPORTION MAY VARY)
MATERIALS
EARTH
SAND
BATT INSULATION
RIGID INSULATION
CONCRETE
STEEL
PLYWOOD, FIRE RATED
GYPSUM BOARD, TYPE 'X'
GYPSUM BOARD, LEAD LINED
ACOUSTICAL CEILING TILE, 2' x 2'
ACOUSTICAL CEILING TILE, 2' x 4'
A-101
A-101
FEC
IN-04.02-01
ABBREVIATIONS
SYMBOLS
& AND
∠ ANGLE
@ AT
℄ CENTERLINE
° DEGREES
# NUMBER
A
AB ANCHOR BOLT
ABA ARCHITECTURAL BARRIERS ACT
A(C)T ACOUSTICAL (CEILING) TILE
ACM ASBESTOS CONTAINING MATERIAL
ACW ACOUSTICAL WALL
ADA AMERICANS W/ DISABILITIES ACT
ADJ ADJACENT
A/E ARCHITECT/ENGINEER
AF ACCESS FLOOR
AFF ABOVE FINISH FLOOR
AGG AGGREGATE
ALT ALTERNATE
ALUM ALUMINUM
APPROX APPROXIMATELY
ARCH ARCHITECT(URAL)
ASPH ASPHALT
A/V AUDIO / VIDEO
B
BARR BARRIER
BATH BATHROOM
BB BACKER BOARD
BLD(G) BUILDING
BLK(G) BLOCK(ING)
BLW BELOW
BM BEAM
BMT(U) BONE MARROW TRANSPLANT (UNIT)
BO BOTTOM OF
BOC BOTTOM OF CURB
BOS BOTTOM OF SLAB
BRC BRACE, BRACING
BRKT BRACKET
BRNG BEARING
BTM BOTTOM
BTWN BETWEEN
C
CAB CABINET
CC CONTRACTOR FURN, CONTRACTOR INST
CD CONSTRUCTION / CONTRACT DOCUMENTS
CJ CONTROL JOINT
CLG CEILING
CLR CLEAR(ANCE)
CMU CONCRETE MASONRY UNIT
CO CONTRACTING OFFICER
COL COLUMN
COMP COMPOSITION
CONC CONCRETE
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTINUOUS
COORD COORDINATE
COR CONTRACTING OFFICER REPRESENTATIVE
CORR CORRIDOR
CS CONCRETE SEALER
CT CERAMIC TILE
CTR CENTER
CV CONTRACTOR FURNISHED, VA INSTALLED
D
DB DESIGN BUILD
DBL DOUBLE
DC DIRECT CURRENT
DD DESIGN DEVELOPMENT
DEMO DEMOLISH(ION)
DEPT DEPARTMENT
DG DESIGN GUIDE
DIA DIAMETER
DIM DIMENSION
DM DESIGN MANUAL
DWN DOWN
DR DOOR
DTL DETAIL
DWG DRAWING(S)
E
E EAST
EA EACH
EJ EXPANSION JOINT
ELEC ELECTRIC(AL)
ELEV ELEVATION OR ELEVATOR
ENG ENGINEER(ING)
EOC EDGE OF CURB
EOP EDGE OF PAVEMENT
EPDM ETHYLENE PROPYLENE DIENE TERPOLYMER
EQ EQUAL
EQUIP EQUIPMENT
ES EACH SIDE
ETS EXPOSED TO STRUCTURE
EX(IST) EXISTING
EXP EXPANSION
EXT EXTERIOR
F
FA FIRE ALARM
FD FLOOR DRAIN
FE(C) FIRE EXTINGUISHER (CABINET)
FF FACTORY FINISH
FFB FINISH FLOOR BREAK
FIN FINISH(ED)
FLASH FLASHING
FLR FLOOR(ING)
FLRSNT FLORESCENT
FNDN FOUNDATION
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOS FACE OF STUDS
FP FIRE PROOF
FR FIRE RATED
FRM FRAME
FT FOOT, FEET
FTG FOOTING
FUR FURRING
FURN FURNISHED
G
GA GAGE, GAUGE
GALV GALVANIZED
GE GENERAL ELECTRIC
G(W)B GYPSUM (WALL) BOARD
GC GENERAL CONTRACTOR
GL GRID LINE
GLB GLUE LAMINATED BEAM
GMU GLASS MASONRY UNIT
GOV(T) GOVERNMENT
GYP GYPSUM BOARD
H
HAC HOUSEKEEPING AIDES CLOSET
HDR HEADER
H(D)W(E) HARDWARE
HM HOLLOW METAL
HORZ HORIZONTAL
HPDL HIGH PRESSURE DECORATIVE LAM
HR HOUR
HT HEIGHT
HVAC HEATING, VENTILATION & AIR CONDITIONING
I
ICRA INFECTIOUS CONTROL RISK ASSESSMENT
ID INSIDE DIAMETER OR DIM
ILSM INTERIM LIFE SAFETY MEASURES
INCL INCLUDE(D,ING)
INST INSTALL
INSUL INSULATION
INT INTERIOR
J
JT JOINT
K
KV KILOVOLT
L
LAM LAMINATE(D)
LAV LAVATORY
LCM LEAD CONTAINING MATERIAL(S)
LD LEAD
LT LIGHT
M
MAT MATERIAL(S)
MAX MAXIMUM
MDF MEDIUM-DENSITY FIBREBOARD
MECH MECHANIC(AL)
MEP MECHANICAL, ELECTRICAL, PLUMBING
MFR MANUFACTURE(R)
MIN MINIMUM
MISC MISCELLANEOUS
MOD MODIFIED
MTL METAL
N
N NORTH
N(/)A NOT APPLICABLE
NEG NEGATIVE
NO. NUMBER
NOM NOMINAL
NTS NOT TO SCALE
O
O.C. ON CENTER(S)
OPN(G) OPEN(ING)
OPP OPPOSITE
OPT OPTION(AL)
OVHD OVERHEAD
P
P PAINT
PCONC PRECAST CONCRETE
PCRA PRE-CONSTRUCTION RISK ASSESSMENT
PL PLATE
PLAM PLASTIC LAMINATE
PLY(WD) PLYWOOD
PNL PANEL
PR PAIR
PRFB PREFABRICATED
PS PLASTIC
PT PORCELAIN TILE
PTN(S) PARTITION(S)
PVMT PAVEMENT
PREP PREPAIR
Q
QTY QUANTITY
R
RAD RADIUS
RB RESILIENT BASE
RCP(S) REFLECTED CEILING PLAN(S)
REF REFERENCE
REINF REINFORCE(D,ING)
REP REPRESENTATIVE
REQ(S,(')D) REQUIRE(D,S,MENT(S))
RESIL RESILIENT
REV REVERSE
RF ROOF
RM ROOM
RMV REMOVE
RO ROUGH OPENING
S
S SOUTH
SCHED SCHEDULE
SCI(D) SPINAL CORD INJURY (& DISABILITY)
SD SCHEMATIC DESIGN
SDSF SOLID SURFACE
SECT SECTION
SF SQUARE FEET
SFRM SPRAY APPLIED FIRE-RESISTIVE MATERIAL
SHG SHINGLES
SHLD(G) SHEILD(ING)
SHT(G) SHEET (SHEATHING)
SIM SIMILAR
SM SEAM
SOW SCOPE OF WORK
SPEC SPECIFICATION
SQ SQUARE
SS STAINLESS STEEL
ST STAIN
STDG STANDING
STF STAFF
STL STEEL
STOR STORAGE
STRUCT STRUCTURAL
SURG SURGERY, SURGICAL
SUSP SUSPENDED
SV SHEET VINYL
SYS SYSTEM
T
TBD TO BE DETERMINED
TBL TABLE
TEMP TEMPORARY
T&G TONGUE AND GROOVE
THK THICK(NESS)
THRESH THRESHOLD
TOC TABLE OF CONTENTS
TOS TOP OF SLAB
TPH TOILET PAPER HOLDER
TRANS TRANSITION
TS TUBE STEEL
TYP TYPICAL
U
UNO UNLESS NOTED OTHERWISE
UON UNLESS OTHERWISE NOTED
V
VA VETERANS AFFAIRS
VAR VARIES
VB VAPOR BARRIER
VC VA FURNISHED, CONTRACTOR INSTALLED
VERT VERTICAL
VIF VERIFY IN FIELD
VV VA FURNISHED, VA INSTALLED
W
W WEST
W/ WITH
WD WOOD
WDW WINDOW
WGHT WEIGHT
W/O WITHOUT
WP WATERPROOF(ING)
WR WATER RESISTANT
WRK WORK
X
XRY X-RAY
FIRE LIFE SAFETY NOTES
1. COMPLY WITH NFPA 241 FOR ALL CONSTRUCTION WORK.
THIS INCLUDES REPLACING CEILING TILES AT THE END OF
EACH WORK SHIFT.
2. PLEASE NOTE, AS AN AGENCY OF THE FEDERAL
GOVERNMENT, THE VA IS NOT SUBJECT TO LOCAL
IMPOSITIONS OF CODE ENFORCEMENT PROCEDURES
(DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS,
FEES, ETC). THE VA SHALL FUNCTION AS THE AUTHORITY
HAVING JURISDICTION (AHJ).
3. THE BELOW CODES HAVE BEEN USED FOR ANALYSIS.
A. NATIONAL FIRE PROTECTION AGENCY (NFPA) 101
LIFE SAFETY CODE, 2024. NFPA 101 TAKES
PRECEDENCE OVER IBC.
B. INTERNATIONAL BUILDING CODE (IBC), 2024.
4. EXISTING BUILDING CONSTRUCTION TYPES SHALL NOT BE
ALTERED AS PART OF THIS PROJECT.
5. EXISTING BUILDING OCCUPANCY SHALL NOT BE ALTERED
AS PART OF THIS PROJECT.
6. EXISTING EGRESS SHALL NOT BE ALTERED AS PART OF
THIS PROJECT. AS SUCH, EGRESS CALCULATIONS ARE
NOT PROVIDED.
7. OCCUPANT LOADS SHALL NOT BE ALTERED AS PART OF
THIS PROJECT. AS SUCH, EXISTING EXIT WIDTHS SHALL
NOT BE ALTERED.
8. EXISTING FIRE RATED ASSEMBLIES SHALL BE MAINTAINED.
ANY EXISTING PENETRATIONS TO BE DEMOLISHED SHALL
BE PATCHED TO MATCH ADJACENT EXISTING FIRE
RATINGS. ANY NEW PENETRATIONS SHALL BE
FIRESTOPPED.
9. ANY NEW PENETRATIONS THROUGH EXISTING FIRE RATED
ASSEMBLIES SHALL BE FIRE STOPPED AND EXISTING
RATING MAINTAINED.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
A-001
ARCH SYMBOLS, ABBREVIATIONS,
& GENERAL NOTES
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
Revisions: Date:
OUT OF SCOPE
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
LOBBY
BM1
STORAGE
OFFICE
1C
CORRIDOR
I1 I2
I3
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
LOBBY
BM1
OFFICE
1C
CORRIDOR
I1 I2
I3
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
ELEVATOR LOBBY
E-1-2
CORRIDOR
I1 I2
I3
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
ELEVATOR LOBBY
E-1-2
CORRIDOR
I1 I2
I3
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
LOBBY
CORRIDOR
C2-7
CONF
200H
CORRIDOR
I1 I2
I3
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
LOBBY
CORRIDOR
C2-7
CONF
200H
CORRIDOR
I1
I2
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1 & 2
BUILDING 7
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS100
BUILDING 7 - ICRA PLANS -
ELEVATORS 1 & 2
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.1/4" = 1'-0"
BLDG 7 - ELEV 1,2 - BASEMENT - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BLDG 7 - ELEV 1,2 - BASEMENT - ICRA PLAN - PHASE 2
1/4" = 1'-0"
BUILDING 7 - ELEV 1,2 - LEVEL 01 - ICRA PLAN - PHASE 2
1/4" = 1'-0"
BUILDING 7 - ELEV 1,2 - LEVEL 01 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 1, 2 - LEVEL 02 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 1, 2 - LEVEL 02 - ICRA PLAN - PHASE 2
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
CORRIDOR
LOBBY
MEDICAL
SERVICE
300A
SECRETARY
300G
I1
I2
I3
ELEVATOR
ELEV-2
ELEC
4M1
ELEVATOR
ELEV-1
OFFICE
400E
LOBBY
CORRIDOR
I1 I2
I3
ELEVATOR
ELEV-2
ELEVATOR
ELEV-1
CORRIDOR
LOBBY
MEDICAL
SERVICE
300A
SECRETARY
300G
I1
I2
I3
ELEVATOR
ELEV-2
ELEC
4M1
ELEVATOR
ELEV-1
OFFICE
400E
LOBBY
LOBBY
C4-16
ELEVATOR
ELEV-3
OFFICE
400A
CORRIDOR
I1
I2
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1 & 2
BUILDING 7
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS101
BUILDING 7 - ICRA PLANS -
ELEVATORS 1& 2
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
1/4" = 1'-0"
BUILDING 7 - ELEV 1, 2 - LEVEL 03 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 1, 2 - LEVEL 04 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 1, 2 - LEVEL 03 - ICRA PLAN - PHASE 2
1/4" = 1'-0"
BUILDING 7 - ELEV 1, 2 - LEVEL 04 - ICRA PLAN - PHASE 2
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
9' - 2"
ELEVATOR
ELEV-3
I1
I2
I3
CORRIDOR
ELEVATOR
ELEV-3
ELEVATOR LOBBY
E-3
CASHIER
168B
I1
I2
I3
CORRIDOR
LOBBY
ELEVATOR
ELEV-3
CORRIDOR
CHIROPRACTOR
OFFICE
COPY
200B
CORRIDOR
C2-7
I1
I2
I3
LOBBY
2E-3
LOBBY
LOBBY
C4-16
ELEVATOR
ELEV-3
WAITING
ROOM
OFFICE
400A
I1
I2
I3
ELEVATOR
ELEV-3
CORRIDOR
LOBBY
MEDICAL
SERVICE
300A
OFFICE
300B
CONFERENCE
I1
I2
I3
LOBBY
3E-3
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BUILDING 7
RM 29
I2
ELEC
ELEC
TRASH
STAIR
BM3
CLASS II
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS102
BUILDING 7 - ICRA PLANS -
ELEVATOR 3 & ROOM 29
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1. ICRA CLASS II & III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
1/4" = 1'-0"
BLDG 7 - ELEV 3 - BASEMENT - ICRA PLAN
1/4" = 1'-0"
BUILDING 7 - ELEV 3 - LEVEL 01 - ICRA PLAN
1/4" = 1'-0"
BUILDING 7 - ELEV 3 - LEVEL 02 - ICRA PLAN
1/4" = 1'-0"
BUILDING 7 - ELEV 3 - LEVEL 04 - ICRA PLAN
1/4" = 1'-0"
BUILDING 7 - ELEV 3 - LEVEL 03 - ICRA PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
Revisions: Date:
1/4" = 1'-0"
BUILDING 7 - BASEMENT - ROOM 29 - ICRA PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
OFFICE
LOBBY
PROCUREMENT
TR
I1 I2
I3
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
OFFICE
LOBBY
PROCUREMENT
TR
4' - 0"
I1
I2
I3
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
AMBULATORY
EXAM
ELEVATOR LOBBY
INSTR
ELEC
100B
ELEVATOR LOBBY
1008A
WAITING AREA
I1
I2
I3
I1I2
I3
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
EXAM
ELEVATOR LOBBY
ELEVATOR LOBBY
1008A
ELEC
100B
INSTR
WAITING AREA
AMBULATORY
I1
I2
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
4 & 5
BUILDING 7
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS103
BUILDING 7 - ICRA PLANS -
ELEVATORS 4, 5
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/4" = 1'-0"
BLDG 7 - ELEV 4,5 - BASEMENT - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BLDG 7 - ELEV 4,5 - BASEMENT - ICRA PLAN - PHASE 2
1/4" = 1'-0"
BUILDING 7 - ELEV 4,5 - LEVEL 01 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 4,5 - LEVEL 01 - ICRA PLAN - PHASE 2
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
LOBBY
TELE
2M4
ELEC
2M3
CORRIDOR
EMG/NCS
EXAM
SECRETARY
OFFICES
I1
I2
I3
4' - 3 5/8"
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
LOBBY
TELE
2M4
ELEC
2M3
CORRIDOR
EMG/NCS
EXAM
SECRETARY
OFFICES
I1
I2
I3
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
LOBBY
STORAGE
TEL
3M4
ELEC
3M3
CORRIDOR
PATIENT
WAITING
PATIENT
WAITING
I1 I2
I3
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
LOBBY
STORAGE
TEL
3M4
ELEC
3M3
CORRIDOR
PATIENT
WAITING
PATIENT
WAITING
I1
I2
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
4 & 5
BUILDING 7
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS104
BUILDING 7 - ICRA PLANS -
ELEVATORS 4, 5
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/4" = 1'-0"
BUILDING 7 - ELEV 4 & 5 - LEVEL 02 - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 4 & 5 - LEVEL 02 - PHASE 2
1/4" = 1'-0"
BUILDING 7 - ELEV 4 & 5 - LEVEL 03 - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 4 & 5 - LEVEL 03 - PHASE 2
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
LOBBY
CONTROL
STATION
TLT
404B
M
IN
4'
0"
5' - 0"
OFFICE
406C
BRONCH
406B
HAC
406A
LOBBY
C4-5
STORAGE
406F
STORAGE
406G
LOBBY
C4-7
ENDOSCOPY
XRAY CONTROL
459C
OR SUPV
444A
ELEC
4M7
I1
I2
I3
I1
I2
I3
ELEVATOR
ELEV-5
ELEVATOR
ELEV-4
LOBBY
CONTROL
STATION
TLT
404B
OFFICE
406C
STERIS ROOM
406D
LOBBY
BRONCH
406B
HAC
406A
EXAM
OR SUPV
444A
C4-7
STORAGE
406F
STORAGE
406G
STORAGE
406H
MIN
6' - 0"
I1
I2
I3I1
I2
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
4 & 5
BUILDING 7
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS105
BUILDING 7 - ICRA PLANS -
ELEVATORS 4, 5
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/4" = 1'-0"
BUILDING 7 - ELEV 4 & 5 - LEVEL 04 - PHASE 1
1/4" = 1'-0"
BUILDING 7 - ELEV 4 & 5 - LEVEL 04 - PHASE 2
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
CARTLIFT
BUILDING 7
MED RECORDS
MEDICAL
RECORDS
ELEV
MECH
15A
PIPE BASEMENT
PIPE BASEMENT
CLASS II
I2 I1
DOWN
CARTLIFT
STERILE/NONSTERILE
STORAGE
MIN
3' - 8"
CLASS IV
I1
I2
I3
I1
M
IN
ELEV
RECORDS,
WORKING
SUPPLY
OFFICE
114BCLASS II
I2
I2
I3
I1
I3
I1
UP
CARTLIFT
CLEAN CORE
SUPPORT CARE
UROLOGY
459B
ENDOSCOPY
DICTATION
499D
LOUNGE
449A
GENERAL OR
TLT
449F
I4
CLASS IV
I1
I2
I3
I1
EXISTING SINK
TO REMAIN
XRAY CONTROL
459C
INSTRUMENT PREP
AND
STERILIZATION
OUT OF SCOPE
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
CONTRACTOR PATH OF TRAVEL
HEPA EQUIPPED EXHAUST
HEPA EQUIPED FILTER
2 HR FIRE RATED WALL (EXISTING & NEW)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS106
BUILDING 7 - ICRA PLANS - MED
RECORDS & SPS CARTLIFT
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1. ICRA CLASS II & IV REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
I4 TEMPORARILY SEAL DOOR FOR DURATION OF
CONSTRUCTION PHASE.
PROJECT
NORTH
TRUE NORTH
(DASHED)
1/4" = 1'-0"
BUILDING 7 - MED RECORDS ELEV - BASEMENT - ICRA PLAN
1/4" = 1'-0"
BLDG 7 - BASEMENT - SPS CARTLIFT - ICRA PLAN
1/4" = 1'-0"
BUILDING 7 - MED RECORDS ELEV - LEVEL 01 - ICRA PLAN
1/4" = 1'-0"
BUILDING 7 - LEVEL 04 - SPS CARTLIFT - ICRA PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BUILDING 7
OUT OF SCOPE
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
CONTRACTOR PATH OF TRAVEL
HEPA EQUIPPED EXHAUST
HEPA EQUIPED FILTER
2 HR FIRE RATED WALL (EXISTING & NEW)
PASSENGER
ELEVATOR PH
PB3
SURGERY
ELEVATOR PH
PB2
STAIR
CART ELEVATOR
PH
PB4
I2
I2
I2
I2
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS107
BUILDING 7 - ICRA PLANS -
PENTHOUSE
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
1. ICRA CLASS II REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I2 TACKY MAT.
PROJECT
NORTH
TRUE NORTH
(DASHED)
Revisions: Date:
1/8" = 1'-0"
BUILDING 7 - PENTHOUSE - FLOOR PLAN - ICRA PLANS
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
ELEVATOR
CORRIDOR/ELEV
LOBBY
100D
INPATIENT PA
PSYCOLOGY
124B
CORRIDOR
I4
ELEVATOR
I1
I2
I3
ELEVATOR
CORRIDOR/ELEV
LOBBY
100D
INPATIENT PA
PSYCOLOGY
124B
CORRIDOR
ELEVATOR
I1
I2
I3
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BUILDING 9
ELEVATOR
TLT
201A
BREAK AREA
ELEV LOBBY
HAC
CLEAN LINEN
203 STOR
CLEAN UTIL
ELEVATOR
ELEV LOBBY
250A
+ I1
I2
I3
ELEVATOR
TLT
201A
BREAK AREA
ELEV LOBBY
HAC
CLEAN LINEN
203 STOR
CLEAN UTIL
ELEVATOR
I1
I2
I3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS108
BUILDING 9 - ICRA PLANS
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
I4 TEMPORARILY SEAL DOOR FOR DURATION OF
CONSTRUCTION PHASE.
1/4" = 1'-0"
BUILDING 9 - ELEV 1 & 2 - LEVEL 01 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 9 - ELEV 1 & 2 - LEVEL 01 - ICRA PLAN - PHASE 2
1/4" = 1'-0"
BUILDING 9 - ELEV 1 & 2 - LEVEL 02 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 9 - ELEV 1 & 2 - LEVEL 02 - ICRA PLAN - PHASE 2
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BUILDING 9
ELEVATOR
WAITING AREA
PHYS OFFICE
B.M.S. EQUIP
STORAGE
ELEVATOR
I1
I2
I3
ELEVATOR
LOBBY
ELEVATOR
WAITING AREA
PHYS OFFICE
B.M.S. EQUIP
STORAGE
COMMUNICATION
CENTER
3C-6
CORRIDOR
CORRIDOR
ELEVATOR
I2 ELEVATOR
LOBBY
COORDINATE ICRA BARRIERS TO
AVOID DISRUPTION OF ACCESS TO
ELEVATOR 2 WHILE ELEVATOR 1 IS IN
CONSTRUCTION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS109
BUILDING 9 - ICRA PLANS
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPEES DESIGN BUILD
23830 PACIFIC HWY S
KENT, WA 98032
(206)-209-2246
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PROJECT
NORTH
TRUE NORTH
(DASHED)
1. ICRA CLASS III REQUIREMENTS MUST BE MET
THROUGHOUT THE ENTIRE DURATION OF CONSTRUCTION.
2. COMPLY WITH ALL REQUIREMENTS IN SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
3. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE
LOCKED AT ALL TIMES UNLESS IN USE BY THE
CONTRACTOR. WHEN IN USE, ACCESS WILL BE
CONTROLLED AND MONITORED BY THE CONTRACTOR.
4. ADHESIVE WALK-OFF MATS TO BE USED AT ALL
CONSTRUCTION ENTRANCES AND EXITS, INCLUDING ANTE
ROOMS.
5. TEMPORARY BARRIERS AND DOORS MAY ONLY BE
DEMOLISHED ONCE GIVEN FINAL APPROVAL BY THE VA
COR.
6. TEMPORARY FIRE RESISTIVE SHEET PLASTIC WITH ZIPPER
ACCESS MAY BE USED AS A MEANS OF DUST CONTROL
WHILE CONSTRUCTING AND DEMOLISHING TEMPORARY
ICRA BARRIERS.
7. CONSTRUCTION WORK TO BE DONE IN PHASES SO ONE
ELEVATOR REMAINS OPERATIONAL.
8. WORK AT LEVELS 2 AND 3 FOR REPLACEMENT OF DOOR
AND JAMB TO BE DONE OUTSIDE OF REGULAR BUSINESS
HOURS.
9. DO NOT DISTURB FLOORING WHILE CONSTRUCTION
OCCURS ON ANY FLOOR, UNLESS OTHERWISE NOTED.
I1 TEMPORARY ICRA DOOR.
I2 TACKY MAT.
I3 TEMPORARY ICRA BARRIER.
1/4" = 1'-0"
BUILDING 9 - ELEV 1 & 2 - LEVEL 03 - ICRA PLAN - PHASE 1
1/4" = 1'-0"
BUILDING 9 - ELEV 1 & 2 - LEVEL 03 - ICRA PLAN - PHASE 2
PROJECT
NORTH
TRUE NORTH
(DASHED)
INACCESSIBLE DURING PHASE
EXISTING WALL TEMPORARILY ACTING AS AN ICRA
BOUNDRY. SEAL ALL OPENINGS, PENETRATIONS, &
HVAC DUCTS AS REQUIRED PER SPECIFICATION
SECTION 01 35 26 - SAFETY REQUIREMENTS.
TEMPORARY ICRA BARRIER FRAMED TO
STRUCTURE ABOVE. CONSTRUCT AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA DOOR AND FRAME AS REQUIRED
PER SPECIFICATION SECTION 01 35 26 - SAFETY
REQUIREMENTS.
TEMPORARY ICRA AIR PRESSURE
HEPA EQUIPPED EXHAUST
2 HR FIRE RATED WALL (EXISTING)
AREA SHOWN
PROJECT
NORTH
TRUE NORTH
(DASHED)
BUILDING 9
ELEV
MACHINE
I2
CLASS II
STAIR
STAIR
STAIR
I2
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
AS110
BUILDING 9 - ICRA PLANS
MK AJ
100% CONSTRUCTION
DOCUMENTS
03/24/2026
502-24-102
ALEXANDRIA VA MEDICAL CENTER, ALEXANDRIA - LA
REPLACE ELEVATORS IN BLDG 7
& BLDG 9
SPE…