Attachment B - Statement of Work Termite HRCC.docx

DOCX document 54 KB Posted

Attached to
Pesticide Treatment Services for the Mark Twain National Forest, Houston Ranger District
Solicitation number
12444524Q0061
Issued by

About this file

This document is a Statement of Work for a pest control contract with the US Department of Agriculture (USDA) Forest Service for the Mark Twain National Forest, Houston Ranger District. The contract requires yearly inspection and treatment of five historic buildings totaling 5,193 square feet to prevent termite and other wood-destroying pest infestations. The contractor must be licensed and certified in Missouri to perform the required liquid and preventative bait treatments. The contract also requires the contractor to provide a written inspection report and schedule the next treatment. The contractor is responsible for any spills or leaks that occur during performance. The contractor must be able to perform corrective action within 48 hours if the initial treatment is ineffective.

The related federal contract opportunity is a total small business set-aside solicitation for these pest control services, with a North American Industry Classification System (NAICS) code of 561710 and a $17.5 million size standard. The contract is anticipated to be a firm-fixed price with a base period and four option periods. Contractors must be registered in the System for Award Management (SAM) to be considered for award.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B - Statement of Work

US Department of Agriculture (USDA)

Statement of Work

Contents

Project3
General Information3
1.0 Scope of Work3
2.0 Background3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Government Furnished4
5.0 Deliverables / Schedule4
6.0 Travel4
7.0 Contractor’s Key Personnel4
8.0 Security Requirements4

Project Pest Control/Termite Treatment Services for the Mark Twain National Forest, Houston Ranger District.

General Information

1.0 Scope of Work

Inspect and treat yearly to prevent the infestation of termites and any other wood destroying pests.

Facilities/Buildings and Square Footage:

Houston Ranger District facilities to include 3 office buildings, 1 warehouse and 1 storage building. All buildings are in the National Register of Historic Places. Square footage of the building are as follows:

Main Office 1120 sq. ft.

Front Office 899 sq. ft.

Garage 576 sq. ft.

Warehouse:2448 sq. ft.

Storage Building: 150 sq. ft.

Total square footage: 5193 sq. ft.

2.0 Background

Yearly inspection of the district buildings which are classified as historic. Provide preventive measures to treat and prevent pest infestations. June 2023 termites were found in the warehouse building, with the environment that the district is in and the age of the buildings it makes these building a prime spot for termites.

Contractor Requirements

3.0 Technical Requirements / Tasks

Treat all buildings with liquid and preventative baits with one year guarantee.

All work shall be performed in compliance with all appropriate local, State, and Federal rules, regulations, codes, and laws. The Contractor shall at all times observe and comply with those laws and regulations in effect at contract award, as well as new legislation and amendments that become effective during the term of this contract. The Contractor shall follow all manufacturers and regulatory guidelines in the application of pest control services.

The Contractor shall meet the licensing requirements of the State of Missouri to provide pest control in the categories specified in this contract. All pesticide applicators shall meet the licensing and certification requirements for the respective state where they are applying product. The Contractor shall provide proof of certification and licensing prior to award. Proof of certification from any state shall be provided with the proposal.

The Contractor shall provide all labor, supervision, equipment, tools, and other items, resources, and services necessary to provide pest control services.

Termite Control Service:

· Report of any conditions that are likely to cause re-infestation problems.

· Provide a written inspection report to COR.

· Schedule the next full treatment of termite control

· Provide certification of termite treatment to the COR

RE-PERFORMANCE

The Contractor shall perform corrective action within 48 hours after receipt of notice from the COR that inspection has revealed control measures applied by the Contractor were ineffective in reducing target pests to an acceptable level. Re-performance shall be made at no additional cost to the Government and shall be required until the desired results are achieved.

The Contractor is solely responsible for any and all spills or leaks and subsequent clean ups that may be required during the performance of this contract which occur as a result of or are contributed to by the actions of its agents, employees, or subcontractors. The Contractor shall clean up such spills or leaks to the satisfaction of the Government. Pesticide spills shall be cleaned, decontaminated, and reported.

WEATHER AND ENVIRONMENTAL CONDITIONS

Average weather occurrences are not a reason for delivering services later than scheduled or requested; however, abnormal conditions are a legitimate reason. Environmental conditions caused by weather events, such as excessive rainfall, can cause some areas to become inaccessible due to soil conditions, flooding, etc. The Government understands that this may cause delays or cancellations of planned work. All delays shall be coordinated with the COR and any delays not agreed upon shall be taken to the CO for consideration.

4.0 Government Furnished

No government furnished property will be available on this contract.

5.0 Deliverables / Schedule

Yearly pest control treatment services for the Mark Twain National Forest, Houston Ranger District, located in Missouri.

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

N/A

8.0 Security Requirements

N/A

***End of Document*** image1.png

File details come from the government source that posted it. Updated .