This is a Special Provisions document for highway construction issued by the Oregon Department of Transportation for the I-84 Echo Salt Shed Fencing Project located on the Old Oregon Trail Highway in Umatilla County, scheduled for May 2025. The project scope consists of three primary work elements: removal of existing Type 1 fencing, construction of CL-6R chain link security fencing, and installation of chain link fence gates. The work is governed by the 2024 edition of the Oregon Standard Specifications for Construction as modified by these special provisions. A mandatory pre-work conference must be scheduled between the contractor and the State Project Manager at a mutually agreed upon time, with work commencing within ten working days of the conference following issuance of the Notice to Proceed. A pre-bid conference is not required; however, bidders are solely responsible for inspecting the project sites prior to submission and cannot claim grounds for charges to the State beyond the bid price based on failure to conduct site inspection.

The document addresses specific technical and procedural requirements across five primary sections: Quality of Materials, Mobilization, Environmental Protection, Removal of Structures and Obstructions, and Fences specifications. Material certification requirements are included for Federal-aid projects, requiring completion of origin certificates as furnished by the Engineer. No specific contract pricing, award amounts, or renewal terms are detailed in this special provisions document. This is classified as a State Project with applicable specifications managed under standard Oregon Department of Transportation procedures.

View the file

Other files

File Type Posted
Mats Towels Lease RFQ 2025 Advertisement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

FOR HIGHWAY CONSTRUCTION

OREGON DEPARTMENT OF TRANSPORTATION

SALEM, OREGON

FENCING

I-84: ECHO SALT SHED FENCING PROJECT

OLD OREGON TRAIL HIGHWAY

UMATILLA COUNTY

MAY 2025

ATTACHMENT B SPECIFICATIONS

I84: Echo Salt Shed Fencing Project

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

WORK TO BE DONE

SECTION 00165 - QUALITY OF MATERIALS

SECTION 00210 - MOBILIZATION

SECTION 00290 - ENVIRONMENTAL PROTECTION

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

SECTION 01050 - FENCES

OREGON DEPARTMENT OF TRANSPORTATION

FOR

Fencing I-84: Echo Salt Shed Fencing Project

Old Oregon Trail Highway Umatilla County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for fencing elements. Modified Special Provisions were prepared by me or under my supervision.

Sections 00165, 00310 and 01050

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

2025.04.07 11:34:18 -07'00'

SPS_M25027, I-84: Echo Salt Shed Fencing Project, Contract, May 2025 1

WORK TO BE DONE

The Work to be done under this Contract consists of the following:

1. Remove existing Type 1 fencing as shown or directed.

2. Construct CL-6R chain link security fencing.

3. Install chain link fence gates.

Perform additional and Incidental Work as called for by the Specifications and Plans.

APPLICABLE SPECIFICATIONS

The Specifications that are applicable to the Work on this Project is the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions.

All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.

CLASS OF PROJECT

This is a State Project.

COORDINATION WITH STATE PROJECT MANAGER

The Contractor shall meet with the State Project Manager for a pre-work conference at a time mutually agreed upon. Work shall commence within ten working days of this meeting, providing the Notice to Proceed has been issued. A pre-bid conference will not be required.

Bidders are solely responsible for inspecting the sites prior to bidding. In no event shall failure to inspect the site constitute grounds for charges to the State more than the bid price.

I-84: Echo Salt Shed Fencing Project

SPS_M25027, I-84: Echo Salt Shed Fencing Project, Contract, May 2025 2

SECTION 00165 - QUALITY OF MATERIALS

Comply with Section 00165 of the Standard Specifications modified as follows:

00165.35(e) Certificate of Origin of Construction Materials – Replace this subsection, except for the subsection number and title, with the following:

When a certificate of material origin for construction materials is specified, complete the form furnished by the Engineer as required by 00160.20(d) for Federal-aid projects.

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications.

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Comply with Section 00310 of the Standard Specifications.

SECTION 01050 - FENCES

Comply with Section 01050 of the Standard Specifications.