This statement of work outlines snow removal requirements for three sites managed by the USDA Forest Service Ottawa National Forest. The contractor will be responsible for plowing the Ontonagon Ranger District office when snow reaches six inches or more by 6:30 a.m. each day Monday through Friday, excluding holidays. At the Mass City warehouse, plowing will be conducted as needed when in the vicinity. The Bergland Heritage Site requires plowing when snow reaches ten inches to ensure emergency vehicle access. All three sites will require removal of accumulated snowbanks by loader or tractor as needed. The contractor must repair any lawn damage from plowing activities before May 10th and carry liability insurance. Quotes should include hourly equipment rates. No other terms are specified in the statement of work or associated federal contract opportunity solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Snow Removal, Ottawa National Forest, newest first.
File Type Posted
12444624Q0001 0002.pdf PDF
Attachment E Maps Photos.pdf PDF
12444624Q0001 0001.pdf PDF
Attachment D Submission Package Rev 1.docx DOCX document
12444624Q0001 Snow Removal RFQ.pdf PDF
Attachment A Schedule of Items.docx DOCX document
Attachment C Wage Determination.pdf PDF
Attachment D Submission Package.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents

Project3
General Information3
1.0 Scope of Work3
2.0 Background3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Government Furnished3
5.0 Deliverables / Schedule3
6.0 Travel4
7.0 Contractor’s Key Personnel4
8.0 Security Requirements4
9.0 Data Rights4
10.0 Section 508 – Electronic and Information Technology Standards4
Attachment4

Project Ottawa NF, Ontonagon - Bergland – Mass City admin. site snowplowing

General Information

1.0 Scope of Work

Snow plowing/removal at the Ontonagon RD office, the Bergland heritage site, and the Mass City warehouse.

2.0 Background

Snow plowing of driveways/parking areas and snow removal when the snowbanks become significant.

Contractor Requirements

3.0 Technical Requirements / Tasks

Ontonagon Ranger District – 1209 Rockland Road, Ontonagon, MI 49953

· Plowing will be completed by 6:30 a.m. Eastern Time, Monday through Friday, excluding legal holidays, when snow accumulation is six (6”) inches or more.

· Payments will be based on actual on-site plowing time. Travel time to the site is not included. End loader/tractor may be required to remove snowbanks mid-season, depending on accumulation of snow.

· Contractor is responsible for lawn repairs caused from snow plowing (i.e. removal of gravel pushed on lawn, sod turned up, seeding and mulching areas of exposed soil). Contractor is required to make repairs in the spring, before May 10th, at their own cost.

· Proof of liability insurance is required.

· Quotes submitted must include type of equipment and cost per hour.

Mass City warehouse – 1390 M-26, Mass City, MI 49948

· The site will be plowed as needed determined by contractor checks while already in the vacinity. Access to garage doors to be cleared of snow buildup from County plowing activities.

· Payments will be based on actual on-site plowing time. Travel time to the site is not included. End loader/tractor may be required to remove snowbanks mid-season, depending on accumulation of snow.

· Contractor is responsible for lawn repairs caused from snow plowing (i.e. removal of gravel pushed on lawn, sod turned up, seeding and mulching areas of exposed soil). Contractor is required to make repairs in the spring, before May 10th, at their own cost.

· Proof of liability insurance is required.

· Quotes submitted must include type of equipment and cost per hour.

Bergland Site – 691 W M-28, Bergland, MI 49910

· The site will be plowed when snow accumulation is ten (10”) inches or greater, providing sufficient access for emergency vehicles (fire trucks, etc.) is the primary objective for this site.

· Payments will be based on actual on-site plowing time. Travel time to the site is not included. End loader/tractor may be required to remove snowbanks mid-season, depending on accumulation of snow.

· Contractor is responsible for lawn repairs caused from snow plowing (i.e. removal of gravel pushed on lawn, sod turned up, seeding and mulching areas of exposed soil). Contractor is required to make repairs in the spring, before May 10th, at their own cost.

· Proof of liability insurance is required.

4.0 Government Furnished

NONE

5.0 Deliverables / Schedule

NONE

6.0 Travel

NONE

7.0 Contractor’s Key Personnel

NONE

8.0 Security Requirements

NONE

9.0 Data Rights

NONE

10.0 Section 508 – Electronic and Information Technology Standards

NONE