Attachment B - Dam Maintenance Specs.pdf
PDF 177 KB Posted
- Solicitation number
- 12444525Q0048
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work for dam maintenance in Shawnee National Forest, specifically in the Hidden Springs Ranger District across Hardin, Johnson, and Pope Counties, Illinois. The project requires removing debris from spillway risers and tree removal along the upstream face and crest of multiple dams, including the Whoopie Cat Dam. Contractors must work between 7:00 am and 6:00 pm Monday through Friday, with limited vehicular access, particularly at the Whoopie Cat Dam site. Key requirements include carefully removing wood debris and trees (both greater and less than 6-inch diameter), disposing of all materials off Forest Service lands, preventing public access to work sites, and restoring disturbed areas by grading, seeding with a standard lawn mix, and applying mulch. The contractor is responsible for complying with local regulations, removing all litter, and ensuring minimal damage to the dam structures during the maintenance process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Shawnee National Forest Dam Maintenance Hidden Springs Ranger District
Hardin, Johnson and Pope Counties, Illinois
PART 1 - SUMMARY
1.1 SCOPE – STATEMENT OF WORK
A. This project is to remove debris from the top of spillway riser and tree removal along the upstream face and crest of the dams.
1.2 ACCESS TO SITE
A. The contractor shall have full access to the site from 7:00 am until 6:00 pm, Monday through Friday.
B. Access to Whoopie Cat Dam has no vehicular access. Access will be from the road to Tecumseh dam and through an old wildlife plot; when you see the dam below you can take off down the hill to reach the primary spillway and crest. Vehicle access is not available past the entrance of the wildlife opening.
1.3 CONTRACTORS OPERATIONS
A. Contractor shall provide signs, barricades, fencing, etc. to prevent publics access to the work site.
1.4 DEBRIS DISPOSAL
A. Debris and material removed shall be placed in a location off Forest Service lands.
B. At the end of the project the contractor shall remove all litter from the site.
PART 2 - CLEARING, GRUBBING, SEEDING
2.1 SCOPE
A. The work shall consist of clearing and disposing of logs, brush, and rubbish from the designated areas on the primary spillway riser inlets, on the lake shoreline, and along the crest of the dam.
2.2 TREE AND DEBRIS REMOVAL
A. Wood debris on top of the spillway riser shall be removed and disposed of with no damage to structure and the dam area around it.
B. Trees greater than 6-inch diameter shall be cut, the roots removed and backfilled.
C. Trees less than 6-inch diameter shall be cut flush with the surrounding ground and chemically treated to prevent regrowth.
D. Care shall be taken to keep damage to the dam a minimum.
2.3 DISPOSAL
A. All materials cleared and grubbed from the designated areas shall become the property of the contractor and be disposed of off Forest Service lands. Contractor is responsible for complying with all local rules and regulations and the payment of all fees that may result from disposal at locations away from the project site.
2.4 MATERIALS
A. MATERIALS
1. Suitable fill shall be added in areas of root wad removal as necessary.
2. Contractor shall seed and mulch all disturbed areas.
3. Seed mixture shall be a standard commercially available lawn mix, free of noxious weeds.
4. Mulch shall be commercially available straw, certified free of seed, mold or other objectionable materials.
B. APPLICATION
1. Contractor shall grade the area to be filled, then seeded to match the surrounding ground.
2. Spread the seed mixture at the rate recommended by the manufacturer.
3. Apply mulch immediately after seeding.