Attachment B

RFQ: 36C24820Q1378

B.2 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

1.00 EA __________________ __________________

Rental of Electric Steam Boiler

1.00 JB __________________ __________________

Installation

1.00 JB __________________ __________________

Removal

GRAND TOTAL __________________

Statement of Need / Salient Characteristics Please include all technical information regarding offered Items.

All equipment must meet the following specifications:

Background:

The Malcom Randall VA Medical Center at 1601 southwest Archer road in Gainesville, Florida needs a 10 – 15 hp rental boiler on a skid (electric) to temporarily provide steam to the ACA Building Hot Water Heat Exchanger for one month while replacing the ACA Steam Piping with new piping.

Objective:

Have a qualified contractor bring in an electric boiler on a skid and set it up to provide heating steam to the ACA Building for a month while replacing the ACA Steam Piping.

SCOPE OF WORK

Contractor shall rent and setup 1 Temporary Electric Boiler (10-15 hp) to the ACA Building

• Bring in 1 temporary electric steam boiler (10-15 hp) on a skid

• 480 volts AC

• Less than or equal to 480 amps. (only have 600 amp breaker to supply the unit with on site)

• 90 PSI Maximum

• Boiler must be able to be placed outside

• Set up by the south entrance to ACA Mechanical Room

• Connect steam hoses to ACA Heat Exchangers in ACA Mechanical Room

• Connect Electric Power to ACA in ACA Electrical Room next to Mechanical Room

• Turn on and test the temporary Boiler

• When contacted by POC, disconnect all hoses and Electrical prior to removing Boiler

• Provide all documentation to the Contracting Officers Representative

Qualifications/Certifications

• The contractor shall be qualified and have the required levels of professional and technical experience to perform the work required by this statement of work.

• The contractor and all of the individuals working on the project site must have taken the OSHA Certified 10-hour safety course.

Safety Regulations All applicable safety regulations shall be observed during all work of this contract.

The VA Safety Officer shall have full authority to see that the contractor obeys all safety rules and regulations relative to the fulfillment of this contract.

Provide the necessary barricades/signage where required.

Scheduling and Hours of Work All work shall be scheduled with the COR.

Skid Will be placed here.

ACA Electrical room Near Skid Placement

Spare Breaker in electrical Room near Doors.

Steam Connection hook up.