ATTACHMENT A Statement of Work to S-24800-00018342.pdf

PDF 885 KB Posted

Attached to
27-2005 Design/Build Temporary Cyber Site
Solicitation number
S-24800-00018342
Issued by
Oregon

About this file

This Statement of Work (SOW) is a Design-Build contract executed by the Oregon Air National Guard (OANG) under Invitation to Bid (ITB) S-24800-00018342 for site preparation to accommodate a temporary cyber facility. The project encompasses two Contract Line-Item Numbers (CLINs): CLIN 0001 for design services and CLIN 0002 for construction execution. The contractor shall provide all architectural and engineering services, labor, materials, equipment, and supervision required to design and prepare the site, including site preparation drawings, utility survey confirmation, environmental permitting coordination, soil and foundation work to support the temporary facility with approximately 230 footers, and construction of new potable water, sanitary sewer, electrical power, and communication lines that tie existing infrastructure to the facility's connection points. The project requires compliance with Unified Facilities Criteria (UFC) standards for utility construction and coordination with 142 CES/CEV (PANG Environmental Management) regarding environmental permitting and potential contaminated media management. The design phase includes submission of phased deliverables at 35%, 65%, and 100% completion stages, all stamped by a Professional Engineer, with construction commencing only after Government approval of the 100% design. The contractor must submit comprehensive preconstruction documentation including structural load calculations, project baseline schedule, Accident Prevention Plan, Contaminated Media Management Plan (if applicable), site staging and laydown plan, Quality Control Plan, and Entry Authorization List for base security clearances at least 72 hours prior to work commencement.

The construction work is structured as a not-to-exceed price based on the finalized 100% design, with the contractor bearing full responsibility for site preparation, civil improvements, utility installation, environmental compliance, and project closeout including as-built documentation and DD Form 1354 for real property transfer. All contractor personnel and subcontractors must comply with base access and security requirements, work within standard hours, utilize Government utilities at no cost with restoration to original condition, and maintain site security and housekeeping standards with daily removal of demolished materials. The contractor is solely responsible for protection of Government property and must repair any damage to existing conditions at no additional cost. Environmental compliance is extensive, including coordination with the Port of Portland for Municipal Separate Storm Sewer System (MS4) permit compliance, Oregon DEQ approval for stormwater management and potential dewatering operations, comprehensive management of PFAS-contaminated soil or groundwater, asbestos surveys and management, spill prevention and notification procedures, and air permit compliance for any equipment installations. Hazardous materials must be registered with base HAZMART five days prior to arrival, and all hazardous waste disposal becomes the Government's property at the contractor's expense. The contractor is responsible for payment or reimbursement of any environmental fines or penalties resulting from non-compliance with permit requirements or regulatory enforcement actions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 52 of 68

ATTACHMENT A

Statement of Work

SW- DESCRIPTION OF WORK:

This project is a Design-Build (D-B) requirement executed under two Contract Line-Item Numbers

(CLINs): CLIN 0001 (Design) and CLIN 0002 (Construction). The Contractor shall provide all architectural and engineering (A&E) services, labor, materials, equipment, and supervision required to design and prep the site as demarcated on the provided site plan. The site will contain a temporary trailer facility delivered after this work concludes that needs to be structurally sound and connected to water, sanitary sewer, electric, and communication. Work shall include, but is not limited to, the following:

Design site preparation drawings that includes all construction elements

Confirm existing utilities through site survey Coordinate with 142 CES/CEV (PANG Environmental Management) regarding requirements for environmental permitting. As needed, produce DEQ permitting application documents including a Contaminated Media Management Plan if dewatering or soil disposal are required.

Construct soil and foundation requirements to support temporary facility. Likely includes soil enhancement, addition of base course, compaction, and addition of approximately 230 footers to comply with provided blocking plan Construct new potable water line in accordance with UFC 3-230-01 and UFC 3-420-01 that ties existing water line to facility’s water connection point Construct new sanitary sewer line in accordance with UFC 3-240-01 and UFC 3-420-01 that ties existing sanitary sewer line to facility’s sanitary sewer connection point Construct new electrical power line in accordance with UFC 3-550-01 that ties existing power line to facility’s power connection point Construct new communication line in accordance with UFC 3-580-01 that ties existing communication line to facility’s communication room

SW- LOCATION OF WORK:

SW- PRINCIPAL FEATURES:

General Project Notes and requirements:

1. Base Access and Security

Please see ITB for full clearance instructions. All Contractor personnel, subcontractors, and delivery drivers must comply with installation security requirements. The Contractor shall submit all required documentation for background checks and base passes prior to the start of work no less than 72 hours prior to start of work. Delays caused by the Contractor’s failure to submit security paperwork in a timely manner are not excusable delays.

with the facility manager to arrange for Government escorts.

2. Standard Work Hours and Holidays

Holidays.

After-major utility outages, noisy work, or crane lifts), a written request must be submitted to the Contracting

Officer and Base Civil Engineer at least ten (10) business days in advance for approval.

3. Use of Government Utilities

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 53 of 68 for construction purposes from existing building outlets at no cost to the Contractor.

and shall remove all temporary connections and return the utility sources to their original condition upon project completion.

4. Site Maintenance, Storage, and Housekeeping

The Contractor is solely responsible for the security of their tools, materials, and equipment. The

Government assumes no liability for theft or damage to Contractor property.

demolished materials shall be removed from the site daily and placed in Contractor-provided dumpsters.

The site shall be kept free of tripping hazards and combustible waste.

Contractor to provide portable restroom and cleaning contract for contractor use.

5. Protection of Government Property pavement, sidewalks, interior finishes, and furniture. Any damage caused by the Contractor’s operations

(e.g., heavy equipment cracking a sidewalk, roof damage from dropped tools, scratched walls) shall be repaired or replaced by the Contractor to match existing conditions at no additional cost to the

Government.

Contractor shall coordinate with Base Civil Engineering to identify and mark all underground utilities.

Any new roads required to access site must be included in contract. If access road is not required as part of the design, the contractor shall repair government property to original state and use.

6. Environmental Hazards: Polyfluoroalkyl Substances (PFAS) contamination of water and soil may be present at this site. The Contractor shall coordinate with 142 CES/CEV and follow any soil and dewatering management procedures deemed applicable. If the project will include dewatering and/or the disposal of excavated soil, a Contaminated Materials Management Plan (CMMP) must be drafted, approved by the

OR DEQ, and followed. The SOW includes the testing and management of these materials. Re-use of excavated soil is highly encouraged. In the event that gross contamination is encountered, the Contractor shall immediately halt work in that area and notify the Contracting Officer and 142 CES/CEV. Please see Environmental Protection Requirements packet included in ITB for additional stipulations.

7. Asset Data and Real Property Documentation: DD Form 1354 (Transfer and Acceptance of DoD Real and descriptive data (including make/model/serial) of the newly installed assets, as well as identifying the demolished equipment being removed from the installation's real property records.

1. Design Element (CLIN 0001)

1. A A1 Initial Concept

1. B A2 35%

1. C B1

1. D B2 65%

1. E 100% Stamped Engineered

The Contractor shall provide a complete, stamped engineering design solution to prep the site for temporary facility installation, as demarcated on the provided siting plan.

Additional building and site plans will be provided by the Government at the pre-bid walkthrough.

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 54 of 68

Design Deliverables and Accountability:

stages for Government review and approval.

Professional Engineer (PE).

site improvements and footers.

Site Plan: The design must include all geotechnical improvements.

Utility Plan: The design must include location of all new utility lines, where they will tie into existing utilities, and where they will tie into the temporary facility.

Note: Construction (CLIN 0002) shall not commence until the 100% design is formally approved by the Base Civil Engineer or designated Government representative.

2. Construction Element (CLIN 0002) 02-A Construction Price Not to exceed

The Contractor shall provide all equipment, labor, materials, and supervision required to execute the approved 100% design. As this is a Design-Build contract, the construction scope shall be executed as a

Not-to-Exceed amount based on the finalized 100% design. The Contractor is responsible for providing a fully prepared site for installation of the temporary facility.

The construction scope of work shall include, but is not limited to, the following requirements:

A. Execution & Qualifications accomplish said work.

B. Civil Construct earth improvements and foundations according to design requirements identified as necessary to structurally support temporary facility Soil removal and replacement, if necessary

Base course addition, if necessary Compaction, if necessary

Installation of approximately 100 footers as recommended by provided blocking plan and foundation design

C. Utilities

Identify and confirm existing utility lines that will be tied to new utility lines

Construct new potable water line in accordance with UFC 3-230-01 and UFC 3-420-01 that ties existing water line to facility’s water connection point

Construct new sanitary sewer line in accordance with UFC 3-240-01 and UFC 3-420-01 that ties existing sanitary sewer line to facility’s sanitary sewer connection point

Construct new electrical power line in accordance with UFC 3-550-01 that ties existing power line to facility’s power connection point

Construct new communication line in accordance with UFC 3-580-01 that ties existing communication line to facility’s communication room

D. Environmental Compliance Coordinate with 142 CES/CEV regarding OR DEQ environmental permitting requirements

Provide dewatering plan, if necessary Provide Contaminated Media Management Plan, if necessary

Follow rules/regulations listed in the ITB, Environmental Protection Requirements

E. Closeout (Turnover)

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 55 of 68

As- -exact locations of the new utilities and foundations.

Preconstruction Submittals:

Submittal Item

Action Required

Description

Phased Design

Packages

Government Approval

35%, 65%, and 100% (Issued for Construction) Drawings and Specifications stamped by a Professional

Engineer.

Structural Load

Calculations

Government Approval

Stamped engineering calculations proving the new footers and soil profile will support temporary facility.

Project Baseline

Schedule

Government Approval

Detailed Gantt chart showing design phases, equipment lead times, demolition, installation, and commissioning.

Accident Prevention Plan (APP)

Government Approval

Comprehensive safety plan including Activity Hazard Analyses (AHAs) for lifts, electrical work, and confined spaces.

Contaminated Media

Management Plan

(CMMP)

Government Approval

Plan detailing procedure for safe handling and disposal of contaminated water and/or soil.

Site Staging & Laydown

Plan

Government Approval

Map showing proposed locations for dumpsters, cranes, and material storage without blocking fire lanes.

Technician Certifications

Notification Only

Copies of necessary licenses and certifications.

Quality Control Plan (QC Plan)

Government Approval

Prior to the commencement of any physical work under CLIN 0002, the Contractor shall submit a comprehensive Contractor Quality Control (CQC) Plan for Government approval. The Contractor is strictly responsible for the overall quality of all design and installation performed under this contract.

The CQC Plan submittal shall include, at a minimum:

1.

qualifications, and contact information of the designated CQC Manager responsible for executing the plan.

2.

-Up phases) for all definable features of work.

3.

inspections, factory tests, and field tests (including TAB and Commissioning) mapped to the project timeline.

4.

tracking, and correcting non-compliant work or Government-identified punch-list items.

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 56 of 68

CQC Manager shall submit Daily Quality Control Reports to the designated Government representative.

These reports shall document all work performed, weather conditions, personnel on site, safety inspections conducted, testing accomplished, and any deviations from the approved 100% design.

Utility Outage Requests

Notification / Coordination

Formal notification submitted in advance (usually 14 days) to shut down power, communication, water, or sewer.

Progress Meeting Minutes

Government Approval

Formal minutes submitted by the contractor within 3 days of any design charrettes, pre-construction meetings, or within 1 business day of weekly progress meetings.

Schedule of Values (SOV)

Government Approval

A detailed cost breakdown of the project (e.g., $X for Demolition, $Y for the Boiler, $Z for Electrical). This is how the contractor’s monthly progress payment invoices are approved. Submittal shall be given in a single page format. Example available.

Monthly Invoicing Package

Government Approval

Invoice Package shall include:

Invoice Package numbered in sequential order

Cover Page with contents outlined Invoice amount and include details

Monthly payroll

SOV

Single Page showing recent meeting minutes summary with % completion rate.

Entry Authorization List (EAL) /

Base Pass Requests

Government Approval

Roster of all contractor and subcontractor personnel, submitted in advance for background checks and base access badging.

Safety Data Sheets (SDS)

Government Approval the military installation (e.g., refrigerants, pipe adhesives, welding gases, paint, lubricants). Must be approved by Base Bioenvironmental or Safety before the chemicals cross the gate.

Hot Work Permits

Government Approval

Required daily (or weekly) for any welding, brazing (copper refrigerant lines), or grinding. Must be coordinated with the Base Fire Department.

Construction & Execution Submittals:

Submittal Item

Action Required

Description

Waste Tickets Notification Provide all waste tickets (including recycle and scrap metal)

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 57 of 68

Daily QC / Safety

Reports

Notification Only

Contractor's daily logs detailing work performed, weather conditions, workers on site, and safety inspections.

Punch List Government Approval

Pre-Final Inspection and Punch List Management Upon the Contractor’s determination that the project is substantially complete, the Contractor shall request

Government representatives.

1. -Final deficiencies, incomplete work, or items requiring correction shall be developed. The Contractor is responsible for documenting this list and submitting it as a formal submittal within three (3) business days of the inspection.

2.

(14) calendar days from the date of the Pre-Final Inspection to correct all items identified on the Punch

List.

3.

Acceptance Inspection. The Government will verify that every item on the Punch List has been completed to the required standard.

4.

CLIN 0002 and release of final payment are strictly of all commissioning tests, and Government approval of all closeout submittals (including As-Builts, O&M

Manuals, and the DD Form 1354).

DD Form and Acceptance of

DoD Real Property)

Government Approval Form 1354 detailing the capitalized cost of all site improvements and the cost of the demolished equipment. The base cannot take financial ownership of the new site without this form.

Final Release of Claims

Government Approval

A legal document submitted with the final invoice stating the contractor has been paid in full and will not file any further financial claims against the government for this project.

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 58 of 68

Attachment 1 – Temp Facility Specs

Attachment 2 – Utility Connection Points

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 59 of 68

Attachment 3 – Site Map

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 60 of 68

Attachment 4 – Environmental Specifications

142d WG Environmental Specifications for Contracts (Comprehensive)

1. Existing Base Stormwater Permit Compliance: The contractor shall provide all preventative and protective measures needed to control stormwater runoff from the construction site in a manner consistent with the base 1200-Z permit and associated Stormwater Pollution Control Plan (copies are available from the base

Environmental Manager), to the satisfaction of the contracting officer and base environmental officer.

2. Mandatory 1200-C Construction Stormwater Permit: Any project that disturbs one acre or more of land (including grading, excavation, or building construction) must obtain 1200 C permit construction stormwater coverage. The ANG must receive an approved NPDES Construction Stormwater Permit before beginning ground disturbing work.

1. Guidance for completion of stormwater plans, permit applications, and filing fees can be found on the

Oregon.gov website here:

1. Permit Guidance: https://www.oregon.gov/deq/wq/wqpermits/Pages/Stormwater-Construction.aspx

2. Fee Schedule: https://www.oregon.gov/deq/wq/regulation/Pages/table70fees.aspx

2. The ANG, as the permit registrant, is always the legally responsible entity under the 1200-C permit.

Contractors may build, install, and support compliance activities, but they cannot assume permit obligations or liability. The ANG must oversee contractor work to ensure it aligns with the SWPCP and all permit requirements. The contractor is responsible for facilitating this oversite as requested.

3. When construction activities have been completed, the Contractor must provide ANG with Permit

Termination Notice, for submittal to the DEQ (subject to OR DEQ and base commander approval).

4. The Contractor shall provide all preventative and protective measures needed to control stormwater runoff from the construction site in a manner to ensure compliance with the issued 1200-C permit and the associated Stormwater Pollution Control Plan.

5. The Contractor is responsible for the payment (or reimbursement) of any fines or penalties incurred from EPA or OR DEQ regulatory enforcement actions resulting from the Contractor’s failure to meet defined

1200-C permit requirements.

3. Hazardous Materials: The contractor shall register all hazardous materials brought on base with the base HAZMART by submitting product Safety Data Sheets (SDS) and quantities used to the base HAZMART to their satisfaction 5-days prior to the hazardous material arriving on base (HAZMART POC: Mr. Eric

Moe, phone (503) 335-4299 or 4974).

4. Hazardous Materials Storage: Store all hazardous materials in accordance with Article 80 of the Oregon Uniform Fire Code. Ensure all hazardous materials and wastes are stored with adequate secondary containment, in accordance with 40 CFR 112: https://www.ecfr.gov/current/title-40/chapter-I/subchapter- D/part-112. Whenever possible, arrangements should be made to store hazardous materials undercover or indoors.

5. Wash Water: Washing of any equipment or vehicles (including concrete trucks and equipment) is strictly prohibited on the Installation without written authority to do so. The contractor may submit a Plan for Washing Operations for approval by the Base Civil Engineer for discharge to sanitary sewer. Approval may require the contractor’s Plan provide pretreatment, sampling & analysis, or other best management practices deemed necessary by the 142 CES and/or OR DEQ. Unless approved otherwise, all wash water must be collected for proper disposal. Contact 142 CES/CEV for additional guidance.

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 61 of 68

6. Groundwater/Dewatering: The contractor shall obtain approval for dewatering from the base commander through the contracting officer and base environmental 142 CES/CEV, prior to dewatering. The contractor shall submit an engineering proposal to the base commander which includes a site-specific Contaminated

Media Management Plan (CMMP); 142 CES/CEV will work with the contractor and OR DEQ for dewatering authority. Any contaminated groundwater removed by the contractor for dewatering must be treated for contaminant removal or collected and disposed of offsite at an approved facility.

7. Excavating at Contaminated Sites: As required, the contractor shall provide appropriate training and air monitoring to excavate at sites where contaminated soil or groundwater have been identified. Appropriate training and air monitoring shall be determined by the contractor to meet OSHA requirements for contaminants. Where excavated materials in areas identified as contaminated cannot be backfilled to the same location, the contractor shall provide disposal at an approved offsite location.

8. Contaminated Soil Management: To ensure contamination is not spread from one location to another, strict management of excavated soils and dewatered water is required. Soil and water excavated from ANG properties must not be relocated without written approval from ANG (142 CES/CEV). The Contractor is responsible for sample collection and analysis to determine characterization of soil or water before being relocated. Excavated soil may be temporarily stockpiled on the site, provided it is placed upon appropriate plastic sheeting. BMPs must be employed to control wind and water erosion, while stockpiled.

1. For soils or water contaminated with PFAS: The Contractor is responsible for managing and disposing of

PFAS contaminated soil, IAW guidelines attached in:

1. ENCLOSURE 1: DAF PFAS Soil BMPs Playbook 4MAR2025

2. ENCLOSURE 2: MEMORANDUM SUBJECT: Updated Interim Guidance on Destruction or Disposal of Materials Containing Per and Polyfluoroalkyl Substances in the United States (20FEB2026)

2. For disposal of soil contaminated with PFAS, contractors may only use solid waste landfills with environmental permits that have composite liners, and gas and leachate collection and treatment systems

(not an option for AFFF concentrate), must be used.

9. Spill Notification & Prevention: The contractor shall notify the Base Defense Operations Center (BDOC) (503-335-4752) upon spilling any quantity of hazardous materials/waste. BDOC will notify the Base Fire Department who will act as spill first responders and incident command. Spill Containment Control and Countermeasures shall be provided by the contractor in accordance with 20 CFR 112. All projects with the potential for spills to the environment must have a worksite Spill Management Plan which includes site-specific spill response procedures and training for all site workers. Contact 142 CES/CEV for additional information.

10. Asbestos Management: Accomplish all surveys, permits, plans, training, applications or fees associated with asbestos in accordance with state DEQ requirements. Except as OAR 340-248-0250 provides, before performing a demolition or renovation, the contractor must have an accredited inspector complete a survey according to OAR 340-248-0270(3). The demolition or renovation activity that requires a survey under OAR 340-248-0270(1) must send a copy of the asbestos survey report to 142 CES/CEV, and to the OR DEQ, upon request. A copy of the Asbestos Survey Report must be kept onsite at the facility during a demolition or renovation activity. Additional information and requirements can be found at:

https://secure.sos.state.or.us/oard/displayDivisionRules.action?selectedDivision=1557

11. Asbestos Plans: The base asbestos management program consists of an Asbestos Management Plan (AMP) and an Asbestos Operating Plan (AOP) available through the Base Facility Manager, phone (503) 335- 4476. The asbestos surveys conducted as part of the AMP are nondestructive surveys, as such, if areas are involved in major renovation or demolition, an additional survey is required. The contractor shall provide adequate protection to the environment and their workers as defined by Oregon DEQ and OSHA. In the event that the survey or the contractor encounters any materials believed to contain asbestos, the contractor shall notify the contracting officer immediately.

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 62 of 68

12. Environmental Management System (EMS): The contractor shall obtain the base EMS policy letter from this web site: https://www.142wg.ang.af.mil/; all contractor personnel associated with this project are required to review the policy letter. The contractor shall submit a record to the contracting officer stating that all personnel associated with this contract (general and subcontractors) have read the EMS policy.

13. Archaeological Preservation: Consult with Base Environmental prior to disturbing any areas within 100 feet of the south and east base boundary fence lines. All remaining areas on base are subject to these conditions:

1. Triggering Events: Discovery of human bone or unmarked graves, possibly associated with Native

American artifacts such as stone tools and ceramics, and archeological features.

1) Immediately stop activity at the near the discovery location

2) Immediately notify the base Environmental Manager (971-404-7698)

3) Establish a 150 foot buffer zone around the location.

4) Avoid the buffer zone. Stay on existing roads if traveling through the buffer zone.

5) Await further instructions through the chain of command, possibly including the preparation of a plan of action if the objects must be removed.

14. MS4 Permit Compliance: The contractor shall meet all requirements imposed by the Port of Portland for compliance with the airport MS4 permit and the associated Design Standards Manual through coordination and approval by the Port of Portland authorized agent, Brian Freeman, 503 415-6350, brian.freeman@portofportland.com or Dan Gilkison, Engineering Director, Dan.Gilkison@PortofPortland.com. This requires the contractor to submit an MS4 permit application and obtain permit approval prior to commencing any regulated activities.

15. Drilling Through Groundwater: Soil borings, drilling operation and any other activity that would disturb groundwater requires OR DEQ approval of methods that would prevent downward migration of existing contaminants. The contractor shall coordinate with the 142 CES/CEV for DEQ approval of these protective measures prior to beginning work. The contractors shall provide this written approval to the contracting officer prior to beginning work.

16. Sample and Analysis Results: The Contractor will provide ANG with copies of all sample and analysis results reports generated during project planning and execution. Note, GPS data for samples collected must be included. Reports will be provided to 142 CES/CEV as soon as possible upon receipt (within 1 week).

17. EISA 438 Compliance: Provide permanent on-site retention and treatment for stormwater runoff from all new facility impervious surface area to be constructed with greater than 5,000 square feet. This can be done anywhere on base given approval from the base civil engineer. Options include: returning equal areas of existing impervious surfaces areas on base to pervious, retaining an equivalent impervious and/or pervious surface area on base that currently discharges off base, or retaining the new impervious surface area on base in an above ground (rock filled to avoid standing water to eliminate bird attraction) or underground basin. Ensure retention basins are designed not to require a UIC permit (prohibited by the Port of Portland and not manageable by the base). Follow guidance from: AFMAN32-1067 (current edition), UFC 3-210-10 (figure 2-1), current NGB project manager guidance.

18. Combining EISA 438 and MS4 Requirements: The contractor shall provide permanent features (i.e. – Low Impact Development (LID) Features) for control of stormwater discharges from new impervious surface areas as they relate to compliance with EISA 438 and MS4 permitting. EISA 438 requires stormwater discharged from new impervious surface areas to be retained on base (see UFC 3-210-10). Possible permanent features, subject to base commander approval, that could comply with EISA 438, without creating standing water features, such as:

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 63 of 68

1. Option A: Converting existing pervious pavements on a one-to-one basis within parcels A, B and potentially D-1 and D-2.

2. Option B: Designing new pavements as pervious

3. Option C: Designing infiltration basins that will not need Oregon DEQ Underground Injection Control (UIC) permits. https://www.oregon.gov/deq/wq/wqpermits/Pages/UIC-Guidance.aspx. (Note: This option requires approval from Base Civil Engineer for siting and land availability and coordination with

OR DEQ; contact 142 CES/CEV for assistance).

4. Treatment of stormwater discharges from new impervious surface areas requires a MS4 permit issued by the Port of Portland (Brian Freeman) as provided by the contractor. If EISA 438 compliance is obtained by converting existing impervious pavement to pervious (Option A. above), the MS4 permit will require demonstrating that the use of our existing open ditchline and retention ponds will treat pollutants to the extent they meet pollutant reductions specified in the Port’s MS4 Design Standards Manual. The issuance of an MS4 permit from the Port is predicated on the fact that our existing open ditchline/retention ponds treatment system has additional capacity to treat new stormwater loads. The MS4 permit application itself is rather complex. Calculating the capacity of our existing open ditchline/retention ponds treatment system for new stormwater loads, in terms of new impervious surface area, is also complex. Given these complexities, Century West Engineering (Bill Brackett, (541) 322-8962, WBrackett@centurywest.com) has been used exclusively to submit/obtain MS4 permits and determine future treatment loading capacities in our existing open ditchline/retention ponds treatment system. Currently, Century West Engineering has determined that our existing open ditchline/retention ponds treatment system has an additional treatment capacity of 269,800 square feet of impervious surface area (current as of 16OCT25).

5. If EISA 438 compliance is obtained by designing a new infiltration basin (Option C. above) you will have to obtain an MS4 permit as described above.

19. Air Permit Compliance: Construction that includes new installation or replacement of equipment with potential to impact air quality (e.g., – fuel burning HVAC equipment, paint/blast booths, generators, tanks, or other equipment that produces emissions) requires submittal of an AQ104 – Notice of Intent to Construct (NOI-C), with the Oregon DEQ. The Contractor is responsible for preparing all NOI-C application documentation (including any required air emissions modelling) for ANG review and submittal to DEQ. The Contractor is responsible for paying any costs associated with this submittal. The NOI-C is submitted under the ANG’s Air Permit; the ANG remains the Responsible Party for all compliance actions and outcomes under this permit and NOI-C. Written approval from the Oregon DEQ is required prior to installation of any emission source with the exception of Type 1 “Notice and Go” NOI-C submittals. OR DEQ requires that all submittals be made digitally on the Your DEQ Online (YDO) Portal. Contractors must obtain a “consultant account” on the Oregon Air National Guard YDO facility homepage. Contact

142 CES/CEV for details.

20. The Contractor may be held responsible for the payment (or reimbursement) of any fines or penalties incurred from EPA or State DEQ regulatory enforcement actions, issued as a direct result of the

Contractor’s action (or failure to act) as outlined within these Specifications or project specific permits.

21. Sanitary Sewer Discharge Permit Compliance: All new discharges must meet the current city of Portland sanitary sewer permit conditions: no rainwater discharge to sanitary, and oil/water separator design to meet oil/grease limits. See current permit provided by the environmental office.

22. Building Demolition Waste: The Contractor shall collect, containerize and dispose of demolition debris components in a manner approved by the base commander or base environmental officer. The contractor shall submit their collection, containerization, and disposal plan to the base commander or base environmental officer through the contracting officer for approval, prior to commencing demolition. The Contractor is required to provide the COR and 142 CES/CEV with data and records showing disposal or

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 64 of 68 diversion of demolition debris. The contractor may not offer hazardous building components for recycling upon removal. Hazardous building components include shall include (but not limited to):

1. Refrigerant reclaimed from air conditioning equipment (required to be removed by a licensed operator of

EPA registered recovery equipment)

2. Fluorescent light tubes

3. Lighting ballasts (except those with factory markings “NON-PCB”)

4. Transformers

5. Mercury Switches (including thermostats)

6. Lead based paint

7. Asbestos

8. Oil Water separators and contained sludge/liquids

9. Storage tanks (underground or above ground)

23. Hazardous Waste (as defined by the Resource Conservation and Recovery Act (RCRA)): All hazardous waste generated from the use of hazardous materials becomes the property of the government to dispose of at the contractor’s expense. The contractor shall make the base environmental office (142 WG/CES/CEV, phone 503-335-4475) aware of all hazardous waste accumulation requiring disposal. The contractor is responsible for proper management and storage of hazardous materials and waste until accepted by ANG for disposal. The Contractor will coordinate for disposal (at the Contractor’s expense) through the base

Hazardous Waste Program Manager (142 CES/CEV), with a minimum of 2-weeks’ notice.

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 65 of 68

Attachments:

1. MS4 Overview:

Municipal Separate Storm Sewer System Permit Construction Design Coordination with Port of Portland Port of Portland is a permittee of a Municipal Separate Storm Sewer System Permit (MS4 No. 101314). In accordance with this MS4 permit, the Port has the authority to define stormwater management requirements at Port-owned properties and has chosen to enforce a Design Standards Manual (DSM), as part of their post-construction stormwater pollutant and runoff control program, on “any new development or redevelopment project that creates or replaces 1000 square feet or more of impervious surface” (with consideration for the larger common plan of development for the project site).

The Port’s DSM effects all “airside” areas within the airport fence including the Oregon Air National

Guard. Under the tenant/host lease agreement, the Oregon Air National Guard must comply and defer to the Port for any stormwater management designs on any applicable construction project. The Port has the authority to prevent a project from proceeding to construction if it is determined that the project design is not sufficiently compliant with Port’s stormwater management requirements.

Applicability of the DSM to a proposed development or redevelopment project (or portions thereof) will be determined initially by the Port at the start of the project. Should the nature of the project change substantially with respect to DSM applicability or exemption eligibility, the Port reserves the right to update their determination of DSM applicability to the project.

Designers of stormwater management systems at the Oregon Air National Guard are required to adhere to the Stormwater Management Standards (SWM), Chapter 4 of the DSM. The Port review processes requires project designers submit documentation on proposed measures for complying with the SWM standards to the Port and obtain approval from the Port prior to finalization of the design. The Port recognizes that project-specific and site-specific constraints may interfere with the ability to fully meet the requirements of the DSM. As such, the DSM allows for the possibility of a variance from the DSM SWM standards and design criteria, with Port approval. Although the DSM standards, criteria, and compliance approaches incorporate some flexibility to account for these constraints, designers may coordinate with the Port and follow the official variance request process.

The DSM shall also apply if there is a larger common plan of development for the project site that creates or replaces 1000 square feet or more of impervious surface”.

Key terms pertaining to applicability are defined below:

Disturbance Area – The area where soil is exposed during construction of the development or redevelopment project.

Development – The addition of any impervious surface to a project site where the existing land cover is less than 35 percent impervious prior to the addition of the new impervious surface. Compare to the definition for redevelopment.

Impervious Surface – The MS4 permit defines this term as “any surface resulting from development activities that prevents the infiltration of water or results in more runoff than in the undeveloped condition.

Common impervious surfaces include building roofs, traditional concrete or asphalt paving on walkways, driveways, parking lots, gravel roads, and packed earthen materials.”5 For consistency with the City SWMM, surfaces such as gravel roads and packed earthen materials will be considered impervious when the runoff coefficient is greater than 0.8, and otherwise will be considered to be pervious.

Project Site – The site that is selected for land development and redevelopment activities, including the functional project area, as well as areas used for stormwater management within the project limits of construction. The site also encompasses the full disturbance area, including areas that will ultimately be pervious and impervious.

Redevelopment – The MS4 permit defines this term as “a project on a previously developed site that results in the addition or replacement of impervious surface.”6 For purposes of the DSM, a project is considered

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 66 of 68 to be redevelopment if the existing land cover at the project site is greater than or equal to 35 percent impervious prior to the addition or replacement of impervious surface.

Replacement – The MS4 permit defines this term as “the removal of an impervious surface that exposes soil followed by the placement of an impervious surface.

Larger Common Plan of Development – The United States Environmental Protection Agency (EPA) defines this term as “a contiguous area where multiple separate (development) activities may be taking place at different times… under one plan.” (EPA 2013a)

To set up a construction stormwater management review with the Port of Portland, contact:

Brian A. Freeman, P.E. LEED AP

503 415-6350 brian.freeman@portofportland.com

DOJ Approved Version 8-5-25 ITB S-24800-00018342 Page 67 of 68