This document is a Statement of Work for snow plowing and removal services at two sites managed by the Ottawa National Forest, a part of the U.S. Department of Agriculture Forest Service.

The key details are:

  • Scope of work includes snow plowing/removal at the Ontonagon Ranger District office and the Bergland heritage site, which are approximately 30 miles apart.
  • For the Ontonagon site, plowing must be completed by 6:30 AM EST Monday-Friday when snowfall exceeds 4 inches, with payments based on actual on-site time. Contractor is responsible for lawn repairs.
  • For the Bergland site, plowing is required when snowfall exceeds 10 inches to maintain emergency vehicle access, with payments also based on actual on-site time. Lawn repair requirements are the same.
  • Contractors must provide proof of liability insurance and submit quotes detailing technical capabilities, equipment, past performance, and pricing.
  • The related federal contract opportunity is Solicitation Number 12444625Q0004 for snow plowing and removal services at the Ottawa National Forest.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project

General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Attachment

Project Ottawa NF, Ontonagon & Bergland admin. site snowplowing (NOTE:THESE SITES ARE ABOUT 30

MILES FROM EACH OTHER.)

General Information

1.0 Scope of Work

Snow plowing/removal at the Ontonagon RD office and the Bergland heritage site.

2.0 Background

Snow plowing of driveways/parking areas and snow removal when the snowbanks become significant.

Contractor Requirements

3.0 Technical Requirements / Tasks

Ontonagon Ranger District – 1209 Rockland Road, Ontonagon, MI 49953

• Plowing will be completed by 6:30 a.m. Eastern Time, Monday through Friday, excluding legal holidays, when snow accumulation is four inches (4”) or more.

• Payments will be based on actual on-site plowing time. Travel time to the site is not included. End loader/tractor may be required to remove snowbanks mid-season, depending on accumulation of snow.

• Contractor is responsible for lawn repairs caused from snow plowing (i.e. removal of gravel pushed on lawn, sod turned up, seeding and mulching areas of exposed soil). Contractor is required to make repairs in the spring, before May 10th, at their own cost.

• Proof of liability insurance is required.

• Quotes submitted must include technical capability, including type(s) of equipment, past performance and pricing

Bergland Site – 691 W M-28, Bergland, MI 49910

• The site will be plowed when snow accumulation is ten inches (10”) or greater, providing sufficient access for emergency vehicles (fire trucks, etc.) is the primary objective for this site.

• Payments will be based on actual on-site plowing time. Travel time to the site is not included. End loader/tractor may be required to remove snowbanks mid-season, depending on accumulation of snow.

• Contractor is responsible for lawn repairs caused from snow plowing (i.e. removal of gravel pushed on lawn, sod turned up, seeding and mulching areas of exposed soil). Contractor is required to make repairs in the spring, before May 10th, at their own cost.

• Proof of liability insurance is required.

• Quotes submitted must include technical capability, including type(s) of equipment, past performance and pricing.

4.0 Government Furnished

NONE

5.0 Deliverables / Schedule

NONE

6.0 Travel

NONE

7.0 Contractor’s Key Personnel

NONE

8.0 Security Requirements

NONE

9.0 Data Rights

NONE

10.0 Section 508 – Electronic and Information Technology Standards

NONE