Attachment A Specifications 2026-0929 HCWWPS.pdf
PDF 1 MB Posted
- Solicitation number
- IFB-131851
- Issued by
- Stafford County, Virginia
About this file
This file consists of technical specifications for the Stafford County Utilities Hoof and Claw Wastewater Pump Station (WWPS), Communication No. 221027, issued for construction on September 18, 2026. The specifications cover a comprehensive range of construction work including concrete forming and accessories, concrete reinforcing, cast-in-place concrete, high-performance coatings, fabricated pre-engineered precast concrete structures, and electrical systems. The project requires a precast concrete building measuring 10 feet by 12 feet by 8 feet in height with specific design loads including 30 PSF roof live load for snow, 150 PSF floor live load, and 120 MPH wind loading. The concrete specifications call for 5000 PSI minimum 28-day compressive strength with air entrainment, reinforcing steel complying with ASTM A615 Grade 60, and post-tensioning strand for roof and floor sections. High-performance epoxy coating systems rated for continuous submerged service in wastewater environments are required for concrete and ductile iron substrates within the wet well, with 125 MDFT thickness for topcoat applications.
The precast concrete building producer must be a plant-certified member of either the National Precast Concrete Association (NPCA), the Precast/Prestressed Concrete Institute (PCI), or an approved equivalent, with minimum five years' experience manufacturing and setting precast concrete. Approved manufacturers for high-performance coatings include PPG Industries or approved equals. The specifications require extensive quality assurance including ACI-certified personnel for concrete work, qualified testing agencies complying with ASTM C1077 and ASTM E329, and comprehensive field quality control testing including compressive strength tests, slump testing, air content analysis, and high-voltage holiday spark detection for coating systems. All materials must be stored at temperatures between 60 and 100 degrees Fahrenheit, and concrete placement is restricted when ambient temperatures fall below 40 degrees Fahrenheit or exceed hot-weather thresholds. The project includes detailed requirements for surface preparation to SSPC-SP 13/NACE No. 6 standards and pH testing of concrete substrates with minimum acceptable pH of 9.0, with testing frequency of once every 500 square feet for the first 500 square feet and once every 1000 square feet thereafter.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stafford County Utilities Hoof and Claw WWPS
Comm. No.: 221027
Technical Specifications Issued for Construction
18 September 2026
TABLE OF CONTENTS TOC - i
WILEY|WILSON STAFFORD COUNTY UTILITIES
HOOF AND CLAW WWPS
COMM. NO.: 221027
Table of Contents
Division Section Title Pages
DIVISION 03 - CONCRETE
031000 ....... CONCRETE FORMING AND ACCESSORIES
032000 ....... CONCRETE REINFORCING
033000 ....... CAST-IN-PLACE CONCRETE
DIVISION 09 - FINISHES
099600 ....... HIGH-PERFORMANCE COATINGS
DIVISION 13 - SPECIAL CONSTRUCTION
133400 ....... FABRICATED PRE-ENGINEERED PRECAST CONCRETE STRUCTURES
DIVISION 26 - ELECTRICAL
260010 ....... SUPPLEMENTAL REQUIREMENTS FOR ELECTRICAL
260011 ....... FACILITY PERFORMANCE REQUIREMENTS FOR ELECTRICAL
260519 ....... LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260523 ....... CONTROL-VOLTAGE ELECTRICAL POWER CABLES
260526 ....... GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 ....... HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533.13 .. CONDUITS FOR ELECTRICAL SYSTEMS
260533.16 .. BOXES AND COVERS FOR ELECTRICAL SYSTEMS
260553 ....... IDENTIFICATION FOR ELECTRICAL SYSTEMS
262213 ....... LOW-VOLTAGE DISTRIBUTION TRANSFORMERS
262416 ....... PANELBOARDS
262726 ....... WIRING DEVICES
262816 ....... ENCLOSED SWITCHES AND CIRCUIT BREAKERS
262923 ....... VARIABLE-FREQUENCY MOTOR CONTROLLERS
26321313 ... DIESEL-ENGINE-DRIVEN GENERATOR SETS
263600 ....... TRANSFER SWITCHES
264313 ....... SURGE PROTECTIVE DEVICES FOR LOW-VOLTAGE ELECTRICAL POWER
CIRCUITS
265000 ....... LIGHTING
265613 ....... LIGHTING POLES AND STANDARDS
DIVISION 31 - EARTHWORK
311000 ....... SITE CLEARING
312000 ....... EARTH MOVING
312319 ....... DEWATERING
315000 ....... EXCAVATION SUPPORT AND PROTECTION
TABLE OF CONTENTS TOC - ii
HOOF AND CLAW WWPS
COMM. NO.: 221027
DIVISION 32 - EXTERIOR IMPROVEMENTS
323113 ....... CHAIN LINK FENCES AND GATES
DIVISION 33 - UTILITIES
330130 ....... SEWER FLOW CONTROL
33052316 ... BORE AND JACK
333105 ....... SUBMERSIBLE PUMP STATION
END OF TABLE OF CONTENTS
CONCRETE FORMING AND ACCESSORIES 031000 - 1
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
SECTION 031000 - CONCRETE FORMING AND ACCESSORIES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Form-facing material for cast-in-place concrete.
2. Shoring, bracing, and anchoring.
B. Related Requirements:
1.3 DEFINITIONS
A. Form-Facing Material: Temporary structure or mold for the support of concrete while the concrete is setting and gaining sufficient strength to be self-supporting.
B. Formwork: The total system of support of freshly placed concrete, including the mold or sheathing that contacts the concrete, as well as supporting members, hardware, and necessary bracing.
1.4 ACTION SUBMITTALS
A. Product Data: For each of the following:
1. Exposed surface form-facing material.
2. Concealed surface form-facing material.
3. Form ties.
4. Form-release agent.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Concrete Formwork: Design, engineer, erect, shore, brace, and maintain formwork in accordance with ACI 301 (ACI 301M), to support vertical, lateral, static, and dynamic loads, CONCRETE FORMING AND ACCESSORIES 031000 - 2
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
and construction loads that might be applied, until structure can support such loads, so that resulting concrete conforms to the required shapes, lines, and dimensions.
1. Design wood panel forms in accordance with APA's "Concrete Forming
Design/Construction Guide."
2. Design formwork to limit deflection of form-facing material to 1/240 of center-to-center spacing of supports.
2.2 FORM-FACING MATERIALS
A. As-Cast Surface Form-Facing Material:
1. Provide continuous, true, and smooth concrete surfaces.
2. Furnish in largest practicable sizes to minimize number of joints.
3. Acceptable Materials: As required to comply with Surface Finish designations specified in Section 033000 "Cast-In-Place Concrete, and as follows:
a. Plywood, metal, or other approved panel materials.
B. Concealed Surface Form-Facing Material: Lumber, plywood, metal, plastic, or another approved material.
1. Provide lumber dressed on at least two edges and one side for tight fit.
C. Forms for Cylindrical Columns, Pedestals, and Supports: Metal, glass-fiber-reinforced plastic, paper, or fiber tubes that produce surfaces with gradual irregularities not exceeding specified formwork surface class.
1. Provide forms with sufficient wall thickness to resist plastic concrete loads without detrimental deformation.
2.3 RELATED MATERIALS
A. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch (19 by 19 mm), minimum.
B. Form-Release Agent: Commercially formulated form-release agent that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materials.
2. Form release agent for form liners shall be acceptable to form liner manufacturer.
C. Form Ties: Factory-fabricated, removable or snap-off, glass-fiber-reinforced plastic or metal form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.
1. Furnish units that leave no corrodible metal closer than 1 inch (25 mm) to the plane of exposed concrete surface.
CONCRETE FORMING AND ACCESSORIES 031000 - 3
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
PART 3 - EXECUTION
3.1 INSTALLATION OF FORMWORK
A. Comply with ACI 301 (ACI 301M).
B. Construct formwork, so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117 (ACI 117M) and to comply with the Surface Finish designations specified in Section 033000 "Cast-In-Place Concrete" for as-cast finishes.
C. Limit concrete surface irregularities as follows:
1. Surface Finish-2.0: ACI 117 Class B, 1/4 inch (6 mm).
D. Construct forms tight enough to prevent loss of concrete mortar.
1. Minimize joints.
2. Exposed Concrete: Symmetrically align joints in forms.
E. Construct removable forms for easy removal without hammering or prying against concrete surfaces.
1. Provide crush or wrecking plates where stripping may damage cast-concrete surfaces.
2. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.
3. Install keyways, reglets, recesses, and other accessories, for easy removal.
F. Do not use rust-stained, steel, form-facing material.
G. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces.
1. Provide and secure units to support screed strips.
2. Use strike-off templates or compacting-type screeds.
H. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible.
1. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar.
2. Locate temporary openings in forms at inconspicuous locations.
I. Chamfer exterior corners and edges of permanently exposed concrete.
J. At construction joints, overlap forms onto previously placed concrete not less than 12 inches (305 mm).
CONCRETE FORMING AND ACCESSORIES 031000 - 4
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
K. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work.
1. Determine sizes and locations from trades providing such items.
L. Construction and Movement Joints:
1. Construct joints true to line with faces perpendicular to surface plane of concrete.
2. Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.
3. Place joints perpendicular to main reinforcement.
4. Locate joints for beams, slabs, joists, and girders in the middle third of spans.
a. Offset joints in girders a minimum distance of twice the beam width from a beam-girder intersection.
M. Provide temporary ports or openings in formwork where required to facilitate cleaning and inspection.
1. Locate ports and openings in bottom of vertical forms, in inconspicuous location, to allow flushing water to drain.
2. Close temporary ports and openings with tight-fitting panels, flush with inside face of form, and neatly fitted, so joints will not be apparent in exposed concrete surfaces.
N. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.
O. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.
P. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.
3.2 INSTALLATION OF EMBEDDED ITEMS
A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete.
1. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.
2. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC 303.
3. Install reglets to receive waterproofing and to receive through-wall flashings in outer face of concrete frame at exterior walls, where flashing is shown at lintels, shelf angles, and other conditions.
4. Clean embedded items immediately prior to concrete placement.
CONCRETE FORMING AND ACCESSORIES 031000 - 5
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
3.3 REMOVING AND REUSING FORMS
A. Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F (10 deg C) for 24 hours after placing concrete. Concrete has to be hard enough to not be damaged by form-removal operations, and curing and protection operations need to be maintained.
B. Clean and repair surfaces of forms to be reused in the Work.
1. Split, frayed, delaminated, or otherwise damaged form-facing material are unacceptable for exposed surfaces.
2. Apply new form-release agent.
C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints.
1. Align and secure joints to avoid offsets.
2. Do not use patched forms for exposed concrete surfaces unless approved by Architect.
3.4 FIELD QUALITY CONTROL
A. Special Inspections: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.
B. Inspections:
1. Inspect formwork for shape, location, and dimensions of the concrete member being formed.
END OF SECTION 031000
CONCRETE REINFORCING 032000 - 1
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
SECTION 032000 - CONCRETE REINFORCING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Steel reinforcement bars.
2. Welded-wire reinforcement.
B. Related Requirements:
1.2 ACTION SUBMITTALS
A. Product Data: For the following:
1. Each type of steel reinforcement.
B. Shop Drawings: Comply with ACI SP-066:
1. Include placing drawings that detail fabrication, bending, and placement.
2. Include bar sizes, lengths, materials, grades, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, location of splices, lengths of lap splices, details of mechanical splice couplers, details of welding splices, tie spacing, hoop spacing, and supports for concrete reinforcement.
C. Construction Joint Layout: Indicate proposed construction joints required to build the structure.
1.3 INFORMATIONAL SUBMITTALS
A. Material Test Reports: For the following, from a qualified testing agency:
1. Steel Reinforcement:
a. For reinforcement to be welded, mill test analysis for chemical composition and carbon equivalent of the steel in accordance with ASTM A706/A706M.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage.
1. Store reinforcement to avoid contact with earth.
CONCRETE REINFORCING 032000 - 2
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
PART 2 - PRODUCTS
2.1 STEEL REINFORCEMENT
A. Reinforcing Bars: ASTM A615/A615M, Grade 60 (Grade 420), deformed.
B. Plain-Steel Welded-Wire Reinforcement: ASTM A1064/A1064M, plain, fabricated from as-drawn steel wire into flat sheets.
C. Deformed-Steel Welded-Wire Reinforcement: ASTM A1064/A1064M, flat sheet.
2.2 REINFORCEMENT ACCESSORIES
A. Joint Dowel Bars: ASTM A615/A615M, Grade 60 (Grade 420), plain-steel bars, cut true to length with ends square and free of burrs.
B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place.
1. Manufacture bar supports from steel wire, plastic, or precast concrete in accordance with CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:
2.3 FABRICATING REINFORCEMENT
A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."
PART 3 - EXECUTION
3.1 PREPARATION
A. Protection of In-Place Conditions:
1. Do not cut or puncture vapor retarder.
2. Repair damage and reseal vapor retarder before placing concrete.
B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that reduce bond to concrete.
3.2 INSTALLATION OF STEEL REINFORCEMENT
A. Comply with CRSI's "Manual of Standard Practice" for placing and supporting reinforcement.
CONCRETE REINFORCING 032000 - 3
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
B. Accurately position, support, and secure reinforcement against displacement.
1. Locate and support reinforcement with bar supports to maintain minimum concrete cover.
2. Do not tack weld crossing reinforcing bars.
C. Preserve clearance between bars of not less than 1 inch (25 mm), not less than one bar diameter, or not less than 1-1/3 times size of large aggregate, whichever is greater.
D. Provide concrete coverage in accordance with ACI 318 (ACI 318M).
E. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
F. Splices: Lap splices as indicated on Drawings.
1. Bars indicated to be continuous, and all vertical bars to be lapped not less than 36 bar diameters at splices, or 24 inches (610 mm), whichever is greater.
2. Stagger splices in accordance with ACI 318 (ACI 318M).
G. Install welded-wire reinforcement in longest practicable lengths.
1. Support welded-wire reinforcement in accordance with CRSI "Manual of Standard Practice."
a. For reinforcement less than W4.0 or D4.0, continuous support spacing to not exceed 12 inches (305 mm).
2. Lap edges and ends of adjoining sheets at least one wire spacing plus 2 inches (50 mm) for plain wire and 8 inches (200 mm) for deformed wire.
3. Offset laps of adjoining sheet widths to prevent continuous laps in either direction.
4. Lace overlaps with wire.
3.3 JOINTS
A. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.
1. Place joints perpendicular to main reinforcement.
2. Continue reinforcement across construction joints unless otherwise indicated.
3. Do not continue reinforcement through sides of strip placements of floors and slabs.
3.4 INSTALLATION TOLERANCES
A. Comply with ACI 117 (ACI 117M).
CONCRETE REINFORCING 032000 - 4
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
3.5 FIELD QUALITY CONTROL
A. Testing Agency: Owner will engage a qualified testing and inspecting agency to perform tests and inspections and to submit reports.
B. Inspections:
1. Steel-reinforcement placement.
END OF SECTION 032000
CAST-IN-PLACE CONCRETE 033000 - 1
HOOF AND CLAW PUMP STATION
COMM. NO.: 221027
SECTION 033000 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Cast-in-place concrete, including concrete materials, mixture design, placement procedures, and finishes.
B. Related Requirements:
1. Section 031000 "Concrete Forming and Accessories" for form-facing materials, form liners, insulating concrete forms, and waterstops.
2. Section 032000 "Concrete Reinforcing" for steel reinforcing bars and welded-wire reinforcement.
1.2 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash, slag cement, other pozzolans, and silica fume;
materials subject to compliance with requirements.
B. Water/Cement Ratio (w/cm): The ratio by weight of water to cementitious materials.
1.3 ACTION SUBMITTALS
A. Product Data: For each of the following.
1. Portland cement.
2. Fly ash.
3. Slag cement.
4. Aggregates.
5. Admixtures:
a. Include limitations of use, including restrictions on cementitious materials, supplementary cementitious materials, air entrainment, aggregates, temperature at time of concrete placement, relative humidity at time of concrete placement, curing conditions, and use of other admixtures.
6. Vapor retarders.
7. Curing materials.
8. Repair materials.
CAST-IN-PLACE CONCRETE 033000 - 2
B. Design Mixtures: For each concrete mixture, include the following:
1. Mixture identification.
2. Minimum 28-day compressive strength.
3. Durability exposure class.
4. Maximum w/cm.
5. Slump limit.
6. Air content.
7. Nominal maximum aggregate size.
8. Indicate amounts of mixing water to be withheld for later addition at Project site if permitted.
C. Shop Drawings:
1. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.
a. Location of construction joints is subject to approval of the Architect.
1.4 INFORMATIONAL SUBMITTALS
A. Material Certificates: For each of the following, signed by manufacturers:
1. Cementitious materials.
2. Admixtures.
3. Curing compounds.
4. Adhesives.
5. Vapor retarders.
6. Repair materials.
B. Material Test Reports: For the following, from a qualified testing agency:
1. Portland cement.
2. Fly ash.
3. Slag cement.
4. Aggregates.
5. Admixtures.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs Project personnel qualified as an ACI-certified Flatwork Technician and Finisher and a supervisor who is a certified ACI Flatwork Concrete Finisher/Technician or an ACI Concrete Flatwork Technician with experience installing and finishing concrete, incorporating permeability-reducing admixtures.
1. Post-Installed Concrete Anchors Installers: ACI-certified Adhesive Anchor Installer.
CAST-IN-PLACE CONCRETE 033000 - 3
B. Ready-Mixed Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C94/C94M requirements for production facilities and equipment.
1. Manufacturer certified in accordance with NRMCA's "Certification of Ready Mixed
Concrete Production Facilities."
C. Laboratory Testing Agency Qualifications: A testing agency qualified in accordance with ASTM C1077 and ASTM E329 for testing indicated and employing an ACI-certified Concrete Quality Control Technical Manager.
1. Personnel performing laboratory tests to be an ACI-certified Concrete Strength Testing Technician and Concrete Laboratory Testing Technician, Grade I. Testing agency laboratory supervisor to be an ACI-certified Concrete Laboratory Testing Technician, Grade II.
D. Field Quality-Control Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified in accordance with ASTM C1077 and ASTM E329 for testing indicated.
1. Personnel conducting field tests to be qualified as an ACI Concrete Field Testing Technician, Grade 1, in accordance with ACI CPP 610.1 or an equivalent certification program.
1.6 PRECONSTRUCTION TESTING
A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on each concrete mixture.
1. Include the following information in each test report:
a. Admixture dosage rates.
b. Slump.
c. Air content.
d. Seven-day compressive strength.
e. 28-day compressive strength.
f. Permeability.
1.7 DELIVERY, STORAGE, AND HANDLING
A. Comply with ASTM C94/C94M and ACI 301 (ACI 301M).
1.8 FIELD CONDITIONS
A. Cold-Weather Placement: Comply with ACI 301 (ACI 301M) and ACI 306.1 and as follows.
CAST-IN-PLACE CONCRETE 033000 - 4
1. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
2. When average high and low temperature is expected to fall below 40 deg F (4.4 deg C) for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301 (ACI 301M).
3. Do not use frozen materials or materials containing ice or snow.
4. Do not place concrete in contact with surfaces less than 35 deg F (1.7 deg C), other than reinforcing steel.
5. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.
B. Hot-Weather Placement: Comply with ACI 301 (ACI 301M) and ACI 305.1 (ACI 305.1M), and as follows:
1. Maintain concrete temperature at time of discharge to not exceed 95 deg F (35 deg C).
2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas.
1.9 WARRANTY
A. Manufacturer's Warranty: Manufacturer agrees to furnish replacement sheet vapor retarder/termite barrier material and accessories for sheet vapor retarder/ termite barrier and accessories that do not comply with requirements or that fail to resist penetration by termites within specified warranty period.
1. Warranty Period: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 CONCRETE, GENERAL
A. ACI Publications: Comply with ACI 301 (ACI 301M) unless modified by requirements in the Contract Documents.
2.2 CONCRETE MATERIALS
A. Source Limitations:
1. Obtain all concrete mixtures from a single ready-mixed concrete manufacturer for entire Project.
2. Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant.
3. Obtain aggregate from single source.
4. Obtain each type of admixture from single source from single manufacturer.
CAST-IN-PLACE CONCRETE 033000 - 5
B. Cementitious Materials:
1. Portland Cement: ASTM C150/C150M, Type II, gray.
2. Fly Ash: ASTM C618, Class C or F.
3. Slag Cement: ASTM C989/C989M, Grade 100 or 120.
C. Normal-Weight Aggregates: ASTM C33/C33M, Class 1N coarse aggregate or better, graded.
Provide aggregates from a single source.
1. Maximum Coarse-Aggregate Size: 1-1/2 inches (38 mm) nominal.
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
D. Air-Entraining Admixture: ASTM C260/C260M.
E. Chemical Admixtures: Certified by manufacturer to be compatible with other admixtures that do not contribute water-soluble chloride ions exceeding those permitted in hardened concrete.
Do not use calcium chloride or admixtures containing calcium chloride.
1. Water-Reducing Admixture: ASTM C494/C494M, Type A.
2. Retarding Admixture: ASTM C494/C494M, Type B.
3. Water-Reducing and -Retarding Admixture: ASTM C494/C494M, Type D.
4. High-Range, Water-Reducing Admixture: ASTM C494/C494M, Type F.
5. High-Range, Water-Reducing and -Retarding Admixture: ASTM C494/C494M, Type G.
6. Plasticizing and Retarding Admixture: ASTM C1017/C1017M, Type II.
F. Water and Water Used to Make Ice: ASTM C94/C94M, potable.
2.3 VAPOR RETARDERS
A. Sheet Vapor Retarder, Class C: ASTM E1745, Class C; not less than 10 mils (0.25 mm) thick.
Include manufacturer's recommended adhesive or pressure-sensitive joint tape.
2.4 CURING MATERIALS
A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.
B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m) when dry.
C. Moisture-Retaining Cover: ASTM C171, polyethylene film burlap-polyethylene sheet.
1. Color:
a. Ambient Temperature Below 50 deg F (10 deg C): Black.
b. Ambient Temperature between 50 deg F (10 deg C) and 85 deg F (29 deg C): Any color.
CAST-IN-PLACE CONCRETE 033000 - 6
c. Ambient Temperature Above 85 deg F (29 deg C): White.
D. Curing Paper: 8-feet- (2438-mm-) wide paper, consisting of two layers of fibered kraft paper laminated with double coating of asphalt.
E. Water: Potable or complying with ASTM C1602/C1602M.
2.5 REPAIR MATERIALS
A. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/4 inch (6 mm) and that can be filled in over a scarified surface to match adjacent floor elevations.
1. Cement Binder: ASTM C150/C150M portland cement or hydraulic or blended hydraulic cement, as defined in ASTM C219.
2. Primer: Product of topping manufacturer recommended for substrate, conditions, and application.
3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch (3.2 to 6 mm) or coarse sand as recommended by topping manufacturer.
4. Compressive Strength: Not less than 5000 psi (34.5 MPa) at 28 days when tested in accordance with ASTM C109/C109M.
2.6 CONCRETE MIXTURES, GENERAL
A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, in accordance with ACI 301 (ACI 301M).
1. Use a qualified testing agency for preparing and reporting proposed mixture designs, based on laboratory trial mixtures.
B. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:
1. Fly Ash or Other Pozzolans: 30 percent by mass.
2. Slag Cement: 30 percent by mass.
3. Total of Fly Ash or Other Pozzolans and Silica Fume: 30 percent by mass with fly ash or pozzolans not exceeding 20 percent by mass and silica fume not exceeding 10 percent by mass.
C. Admixtures: Use admixtures in accordance with manufacturer's written instructions.
2.7 CONCRETE MIXTURES
A. Class A: Normal-weight concrete used for footings, grade beams, tie beams, and exterior slabs on ground.
CAST-IN-PLACE CONCRETE 033000 - 7
1. Exposure Class: ACI 318 (ACI 318M) F2 S0 W0 C0.
2. Minimum Compressive Strength: 4500 psi (31 MPa) at 28 days.
3. Maximum w/cm: 0.45.
4. Slump Limit: 5 inches (125 mm), plus or minus 1 inch (25 mm)
5. Air Content:
a. Exposure Classes F2 and F3: 5.5 percent, plus or minus 1.5 percent at point of delivery for concrete containing 1-1/2-inch (38-mm) nominal maximum aggregate size.
6. Limit water-soluble, chloride-ion content in hardened concrete to 1.00 percent by weight of cement.
2.8 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete in accordance with ASTM C94/C94M and furnish batch ticket information.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verification of Conditions:
1. Before placing concrete, verify that installation of concrete forms, accessories, and reinforcement, and embedded items is complete and that required inspections have been performed.
2. Do not proceed until unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Provide reasonable auxiliary services to accommodate field testing and inspections, acceptable to testing agency, including the following:
1. Daily access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Secure space for storage, initial curing, and field curing of test samples, including source of water and continuous electrical power at Project site during site curing period for test samples.
4. Security and protection for test samples and for testing and inspection equipment at Project site.
CAST-IN-PLACE CONCRETE 033000 - 8
3.3 INSTALLATION OF EMBEDDED ITEMS
A. Place and secure anchorage devices and other embedded items required for adjoining Work that is attached to or supported by cast-in-place concrete.
1. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.
2. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of ANSI/AISC 303.
3.4 JOINTS
A. Isolation Joints in Slabs-on-Ground: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.
1. Terminate full-width joint-filler strips not less than 1/2 inch (13 mm) or more than 1 inch
(25 mm) below finished concrete surface.
2. Install joint-filler strips in lengths as long as practicable. Where more than one length is required, lace or clip sections together.
B. Doweled Joints:
1. Install dowel bars and support assemblies at joints where indicated on Drawings.
2. Lubricate or asphalt coat one-half of dowel bar length to prevent concrete bonding to one side of joint.
3.5 CONCRETE PLACEMENT
A. Before placing concrete, verify that installation of formwork, reinforcement, embedded items, and vapor retarder is complete and that required inspections are completed.
1. Immediately prior to concrete placement, inspect vapor retarder for damage and deficient installation, and repair defective areas.
2. Provide continuous inspection of vapor retarder during concrete placement and make necessary repairs to damaged areas as Work progresses.
B. Notify testing and inspection agencies 24 hours prior to commencement of concrete placement.
C. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301 (ACI 301M), but not to exceed the amount indicated on the concrete delivery ticket.
1. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.
CAST-IN-PLACE CONCRETE 033000 - 9
D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness.
1. If a section cannot be placed continuously, provide construction joints as indicated.
2. Deposit concrete to avoid segregation.
3. Deposit concrete in horizontal layers of depth not to exceed formwork design pressures and in a manner to avoid inclined construction joints.
4. Consolidate placed concrete with mechanical vibrating equipment in accordance with
ACI 301 (ACI 301M).
a. Do not use vibrators to transport concrete inside forms.
b. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches (150 mm) into preceding layer.
c. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity.
d. At each insertion, limit duration of vibration to time necessary to consolidate concrete, and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.
E. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.
1. Do not place concrete floors and slabs in a checkerboard sequence.
2. Consolidate concrete during placement operations, so concrete is thoroughly worked around reinforcement and other embedded items and into corners.
3. Maintain reinforcement in position on chairs during concrete placement.
4. Screed slab surfaces with a straightedge and strike off to correct elevations.
5. Level concrete, cut high areas, and fill low areas.
6. Slope surfaces uniformly to drains where required.
7. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane, before excess bleedwater appears on the surface.
8. Do not further disturb slab surfaces before starting finishing operations.
3.6 FINISHING FORMED SURFACES
A. As-Cast Surface Finishes:
1. ACI 301 (ACI 301M) Surface Finish SF-1.0: As-cast concrete texture imparted by form-facing material.
a. Patch voids larger than 1-1/2 inches (38 mm) wide or 1/2 inch (13 mm) deep.
b. Remove projections larger than 1 inch (25 mm).
c. Tie holes do not require patching.
d. Surface Tolerance: ACI 117 (ACI 117M) Class D.
e. Apply to concrete surfaces not exposed to public view.
CAST-IN-PLACE CONCRETE 033000 - 10
3.7 FINISHING FLOORS AND SLABS
A. Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.
B. Float Finish:
1. When bleedwater sheen has disappeared and concrete surface has stiffened sufficiently to permit operation of specific float apparatus, consolidate concrete surface with power-driven floats or by hand floating if area is small or inaccessible to power-driven floats.
2. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture and complies with ACI 117 (ACI A117M) tolerances for conventional concrete.
C. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, ramps, and locations indicated on Drawings.
1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route.
2. Coordinate required final finish with Architect before application.
3.8 CONCRETE CURING
A. Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.
1. Comply with ACI 301 (ACI 301M) and ACI 306.1 for cold weather protection during curing.
2. Comply with ACI 301 (ACI 301M) and ACI 305.1 (ACI 305.1M) for hot-weather protection during curing.
3. Maintain moisture loss no more than 0.2 lb/sq. ft. x h (1 kg/sq. m x h), calculated in accordance with ACI 305.1, before and during finishing operations.
B. Curing Unformed Surfaces: Comply with ACI 308.1 (ACI 308.1M) as follows:
1. Begin curing immediately after finishing concrete.
3.9 TOLERANCES
A. Conform to ACI 117 (ACI 117M).
3.10 CONCRETE SURFACE REPAIRS
A. Defective Concrete:
CAST-IN-PLACE CONCRETE 033000 - 11
1. Repair and patch defective areas when approved by Architect.
2. Remove and replace concrete that cannot be repaired and patched to Architect's approval.
B. Patching Mortar: Mix dry-pack patching mortar, consisting of 1-part portland cement to 2-1/2 parts fine aggregate passing a No. 16 (1.18-mm) sieve, using only enough water for handling and placing.
C. Repairing Unformed Surfaces:
1. Test unformed surfaces, such as floors and slabs, for finish, and verify surface tolerances specified for each surface.
a. Correct low and high areas.
b. Test surfaces sloped to drain for trueness of slope and smoothness; use a sloped template.
2. Repair finished surfaces containing surface defects, including spalls, popouts, honeycombs, rock pockets, crazing, and cracks in excess of 0.01 inch (0.25 mm) wide or that penetrate to reinforcement or completely through unreinforced sections regardless of width, and other objectionable conditions.
3. After concrete has cured at least 14 days, correct high areas by grinding.
4. Correct localized low areas during, or immediately after, completing surface-finishing operations by cutting out low areas and replacing with patching mortar.
a. Finish repaired areas to blend into adjacent concrete.
5. Correct other low areas scheduled to remain exposed with repair topping.
a. Cut out low areas to ensure a minimum repair topping depth of 1/4 inch (6 mm) to match adjacent floor elevations.
b. Prepare, mix, and apply repair topping and primer in accordance with manufacturer's written instructions to produce a smooth, uniform, plane, and level surface.
6. Repair random cracks and single holes 1 inch (25 mm) or less in diameter with patching mortar.
a. Groove top of cracks and cut out holes to sound concrete, and clean off dust, dirt, and loose particles.
b. Dampen cleaned concrete surfaces and apply bonding agent.
c. Place patching mortar before bonding agent has dried.
d. Compact patching mortar and finish to match adjacent concrete.
e. Keep patched area continuously moist for at least 72 hours.
D. Perform structural repairs of concrete, subject to Architect's approval, using epoxy adhesive and patching mortar.
E. Repair materials and installation not specified above may be used, subject to Architect's approval.
CAST-IN-PLACE CONCRETE 033000 - 12
3.11 FIELD QUALITY CONTROL
A. Testing Agency: Owner will engage a qualified testing and inspecting agency to perform tests and inspections and to submit reports.
1. Testing agency to be responsible for providing curing container for composite samples on Site and verifying that field-cured composite samples are cured in accordance with
ASTM C31/C31M.
2. Testing agency to immediately report to Architect, Contractor, and concrete manufacturer any failure of Work to comply with Contract Documents.
3. Testing agency to report results of tests and inspections, in writing, to Owner, Architect, Contractor, and concrete manufacturer within 48 hours of inspections and tests.
a. Test reports to include reporting requirements of ASTM C31/C31M, ASTM C39/C39M, and ACI 301, including the following as applicable to each test and inspection:
1) Project name.
2) Name of testing agency.
3) Names and certification numbers of field and laboratory technicians performing inspections and testing.
4) Name of concrete manufacturer.
5) Date and time of inspection, sampling, and field testing.
6) Date and time of concrete placement.
7) Location in Work of concrete represented by samples.
8) Date and time sample was obtained.
9) Truck and batch ticket numbers.
10) Design compressive strength at 28 days.
11) Concrete mixture designation, proportions, and materials.
12) Field test results.
13) Information on storage and curing of samples before testing, including curing method and maximum and minimum temperatures during initial curing period.
14) Type of fracture and compressive break strengths at seven days and 28 days.
B. Batch Tickets: For each load delivered, submit three copies of batch delivery ticket to testing agency, indicating quantity, mix identification, admixtures, design strength, aggregate size, design air content, design slump at time of batching, and amount of water that can be added at Project site.
C. Inspections:
1. Headed bolts and studs.
2. Verification of use of required design mixture.
3. Concrete placement, including conveying and depositing.
4. Curing procedures and maintenance of curing temperature.
5. Batch Plant Inspections: On a random basis, as determined by Architect.
CAST-IN-PLACE CONCRETE 033000 - 13
D. Concrete Tests: Testing of composite samples of fresh concrete obtained in accordance with ASTM C 172/C 172M to be performed in accordance with the following requirements:
1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete mixture exceeding 5 cu. yd. (4 cu. m), but less than 25 cu. yd. (19 cu. m), plus one set for each additional 50 cu. yd. (38 cu. m) or fraction thereof.
a. When frequency of testing provides fewer than five compressive-strength tests for each concrete mixture, testing to be conducted from at least five randomly selected batches or from each batch if fewer than five are used.
2. Slump: ASTM C143/C143M:
a. One test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture.
b. Perform additional tests when concrete consistency appears to change.
3. Air Content: ASTM C231/C231M pressure method, for normal weight concrete;
a. One test for each composite sample, but not less than one test for each day's pour of each concrete mixture.
4. Concrete Temperature: ASTM C1064/C1064M:
a. One test hourly when air temperature is 40 deg F (4.4 deg C) and below or 80 deg F (27 deg C) and above, and one test for each composite sample.
5. Compression Test Specimens: ASTM C31/C31M:
a. Cast and laboratory cure two sets of three 6-inch (150 mm) by 12-inch (300 mm) or 4-inch (100 mm) by 8-inch (200 mm) cylinder specimens for each composite sample.
6. Compressive-Strength Tests: ASTM C39/C39M.
a. Test one set of two laboratory-cured specimens at seven days and one set of two specimens at 28 days. Keep remaining cylinder sin reserve to be tested only if compressive strength of 28-day cylinders does not meet strength requirements.
7. Strength of each concrete mixture will be satisfactory if every average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength, and no compressive-strength test value falls below specified compressive strength by more than 500 psi (3.4 MPa) if specified compressive strength is 5000 psi (34.5 MPa), or no compressive strength test value is less than 10 percent of specified compressive strength if specified compressive strength is greater than 5000 psi (34.5 MPa).
8. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Architect but will not be used as sole basis for approval or rejection of concrete.
9. Additional Tests:
CAST-IN-PLACE CONCRETE 033000 - 14
a. Testing and inspecting agency to make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Architect.
b. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C42/C42M or by other methods as directed by Architect.
1) Acceptance criteria for concrete strength to be in accordance with ACI 301 (ACI 301M), Section 1.6.6.3.
10. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.
11. Correct deficiencies in the Work that test reports and inspections indicate do not comply with the Contract Documents.
3.12 PROTECTION
A. Protect concrete surfaces as follows:
1. Protect from petroleum stains.
2. Diaper hydraulic equipment used over concrete surfaces.
3. Prohibit use of pipe-cutting machinery over concrete surfaces.
4. Prohibit placement of steel items on concrete surfaces.
5. Prohibit use of acids or acidic detergents over concrete surfaces.
END OF SECTION 033000
HIGH-PERFORMANCE COATINGS 099600 - 1
HOOF AND CLAW WWPS
COMM. NO.: 221027
SECTION 099600 - HIGH-PERFORMANCE COATINGS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes surface preparation and the application of high-performance coating systems on the following substrates:
1. Substrates:
a. Concrete, vertical, horizontal, and overhead surfaces.
b. Ductile Iron
1.3 REFERENCES
A. American Concrete Institute, ACI
B. ASTM International, ASTM
C. International Concrete Repair Institute, ICRI
D. NACE International, NACE
E. SSPC: The Society for Protective Coatings, SSPC
F. Association for Materials Protection and Performance, AMPP
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product. Include preparation requirements, application instructions, and material safety data sheets.
B. Product List: Cross-reference to coating system and locations of application areas. Use same designations indicated on Drawings and in schedules. Include color designations where applicable.
HIGH-PERFORMANCE COATINGS 099600 - 2
HOOF AND CLAW WWPS
COMM. NO.: 221027
1.5 QUALITY ASSURANCE
A. Quality Assurance Submittals:
1. Manufacturer’s project reference lists with coating systems specified herein, stating project location, Owner contact information, Engineer contact information, Installer contact information, containing a minimum of 10 projects of similar capacity with a minimum of 5 years of satisfactory service.
2. Product Data Sheets: Copies of current technical data for each component specified and applied as outlined in this Section.
3. Safety Data Sheets: Copies of current SDS for any materials brought on-site including all clean-up solvents, repair or resurfacing mortars and lining materials.
4. Qualification Data: Approved Installer Certification from manufacturer.
5. Performance Testing Reports: Copies of test data for the entire physical, chemical, and permeation properties listed herein and as outlined within this Section.
6. Installation Instructions: Manufacturer’s written installation instructions for the materials specified in this Section.
7. Jobsite Reports:
a. Daily Reports: Include surface preparation, substrate conditions, ambient conditions, application procedures, coatings materials applied, material quantities, material batch numbers, and a description of the work completed and its location.
b. Quality Control Reports: Provide reports for all quality control and physical testing specified herein.
c. Contractor must maintain a copy of records until the expiration of the specified warranty period.
B. Applicator’s Qualifications:
1. Contractor shall be a certified Applicator by the Structural Epoxy manufacturer prior to bid date. Submit proof of Applicator certification by manufacturer to Engineer.
2. Installation equipment shall be acceptable to the manufacturer. If spraying Structural Epoxy, Applicator must utilize equipment approved by Structural Epoxy manufacturer.
3. Applicator shall establish quality control procedures and practices to monitor phases of surface preparation, storage, mixing, application, and inspection throughout the duration of the project. Contractor to provide a fulltime, on-site person whose dedicated responsibilities will include quality control of the Structural Epoxy linings and completed manufacturing certification training.
4. Applicator’s quality control procedures and practices must include the following items:
a. Training of personnel in the proper surface preparation requirements.
b. Training of personnel in the proper storing, mixing, and application and quality control testing of the Structural Epoxy linings.
c. If spraying, training of personnel with the spray equipment to ensure proper film build, film quality, and ratio control.
HIGH-PERFORMANCE COATINGS 099600 - 3
HOOF AND CLAW WWPS
COMM. NO.: 221027
1.6 DELIVERY, STORAGE, AND HANDLING
A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 60 deg F and not greater than 100 deg F.
All materials must be stored and handled in accordance with the Manufacturer’s instructions and recommendations.
1. Maintain containers in clean condition, free of foreign materials and residue.
2. Remove rags and waste from storage areas daily.
1.7 FIELD CONDITIONS
A. Apply coatings only when temperature of surfaces to be coated, humidity, substrate moisture conditions, and ambient air temperatures are within the tolerances specified by the Manufacturer for the product being applied.
B. Do not apply coatings when relative humidity exceeds 85 percent; at ambient air temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.
C. Do not apply exterior coatings in snow, rain, fog, or mist.
1.8 WARRANTY
A. The coatings Manufacturer must warranty its products as free from material defects for a minimum period of three (3) years. Manufacturer must provide a Warranty Certificate to the Owner upon successful installation and acceptance of each coatings systems.
B. The Contractor must warranty each coatings system as free from workmanship defects for a minimum period of three (3) years.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Approved Manufacturers:
1. PPG Industries
2. Or Approved Equal
B. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to products listed in the Exterior High-Performance Coating Schedule or Interior High-Performance Coating Schedule for the coating category indicated.
HIGH-PERFORMANCE COATINGS 099600 - 4
HOOF AND CLAW WWPS
COMM. NO.: 221027
2.2 HIGH-PERFORMANCE COATINGS, GENERAL
A. Material Compatibility:
1. Materials for use within each paint and coatings system shall be compatible with one another and substrates indicated herein and, on the Drawings, including concrete crack and spall repair materials, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience. In the event of an incompatibility between materials and substrates, notify the Engineer immediately to coordinate alternative product selections.
2. For each coat in a paint system, products shall be recommended in writing by topcoat manufacturers for use in paint system and on substrate indicated.
3. Products shall be of same manufacturer for each coat in a coating system.
B. Colors: As selected by Owner and Engineer from manufacturer's full range.
2.3 EPOXY CEMENTITIOUS RESURFACER
A. Epoxy cementitious resurfacer shall be an epoxy-modified aggregate reinforce material for surfacing, patching, and filling voids and bugholes in concrete. The material shall be suitable for the application down to 1/16 inch thickness. The resurfacer must be approved by the coatings manufacturer as an acceptable substrate for application of the epoxy coating system.
B. Epoxy cementitious resurfacer shall exhibit high bond strength and high mechanical strengths.
Initial set time occurs early (4 hours @ 77 deg F) to allow for structural epoxy coating. The epoxy cementitious resurface must not require any further preparation or conditioning within 36 hours (at 77 deg F) to accept epoxy top coats.
2.4 CONCRETE CRACK AND SPALL REPAIR MATERIALS
A. Concrete Crack Repair materials and methods must be in accordance with the methodologies, materials, and manufacturers included in the Drawings on sheet S-501. Where cracks are repaired by injection, excess materials and spills must be removed by mechanically so that the repaired crack is flush with the surrounding concrete surface.
B. Concrete Spall Repair materials and methods must be in accordance with the methodologies, materials, and manufacturers included in the Drawings on sheet S-501.
C. The Contractor must verify the compatibility of all concrete repair materials with the resurfacing and coatings materials to be installed over top of the repairs prior to ordering. In the event of incompatibility, notify the Engineer.
2.5 SOURCE QUALITY CONTROL
A. Testing of Coating Materials: Owner reserves the right to invoke the following procedure:
HIGH-PERFORMANCE…
This is the start of the file's text. The full file is on GovTribe.