ATTACHMENT_A_Segment_Locations_Priority_Points_Pictures.pdf
PDF 6 MB Posted
- Solicitation number
- 2027-09 (SCPRT RTP Project No. P28052601226)
- Issued by
- Dillon County, South Carolina
About this file
This attachment to an Invitation for Bids document from Dorchester County, South Carolina, provides segment locations, priority points, and visual documentation for the Ashley River Scenic Blue Trail Obstruction Clearing project. The document identifies specific sections of the trail requiring obstruction clearing services and establishes a priority-based allocation system to guide contractors in addressing removal work across multiple segments. The attachment includes photographs and mapping information that visually illustrate the condition and location of obstructions along the designated trail sections, enabling bidders to assess the scope and nature of clearing work required at each priority-ranked segment.
The priority points system appears designed to allow flexibility in bid structuring and project execution, with segments weighted according to need or urgency. This documentation serves as a critical reference tool for qualified firms developing cost estimates and project methodologies, as it provides the geographic and photographic detail necessary to prepare accurate bids for the obstruction clearing services. The visual exhibits enable bidders to evaluate terrain conditions, vegetation types, and obstruction severity across the trail alignment, supporting more precise pricing and resource planning for the clearing operations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Segment boundaries, mapped locations, GPS coordinates, and priority points are provided to identify the general limits and sequence of Work. Coordinates are approximate. Priority points reflect conditions documented during the March 2025 assessment and do not constitute a complete or current inventory of obstructions.
Bidders remain responsible for evaluating current conditions.
Segment Location Map
GPS coordinate ranges for Segments A – E are outlined below and are not precise.
Segment A – W 80.201, N 32.959 to W 80.210, N 32.955
Segment B – W 80.210, N 32.955 to W 80.221, N 32.961
Segment C – W 80.221, N 32.961 to W 80.230, N 32.964
Segment D – W 80.230, N 32.964 to W 80.247, N 32.964
Segment E – W 80.247, N 32.964 to W 80.253, N 32.969
The County’s prioritization begins at the Ashley River Park Boat Landing and moves upriver.
USACE Identified Priority Points
Below are priority clearings indicated by point identification conducted by USACE and included in the March 2025 assessment. Again, top priority would be Point 25 and move upriver. Priority Clearings: (Indicated by point identification conducted by USACE). Below the list is the map found in the assessment.
Point 2: N 32.969489, W 80.249083
Point 6: N 32.963063, W 80.236927
Point 7: N 32.964500, W 80.232888
Point 10: N 32.963046, W 80.228185
Point 11: N 32.962322, W 80.227266
Point 13: N 32.961248, W 80.221802
Point 15: N 32.961103, W 80.221402
Point 16: N 32.959346, W 80.217806
Point 17: N 32.958357, W 80.216233
Point 19: N 32.955491, W 80.212508
Point 23: N 32.957223, W 80.204443
Point 25: N 32.955225, W 80.197138
Pictures from June 2026
Aerial Photos from October 2024