About this file

This Request for Information from the National Aeronautics and Space Administration and the United States Geological Survey seeks industry feedback on a proposed Landsat Next mission concept. The Landsat Next concept would collect superspectral land observations with higher 10-20-30 meter spatial resolution and additional spectral bands beyond Landsat 8 and 9 capabilities. It aims to provide improved data for applications like agriculture, ecology, urban monitoring, water resources and more. Responses to the RFI will help inform requirements for the Landsat Next system planned for operations beginning in the late 2020s. The mission concept looks to continue the 48-year Landsat program's free and open data policies to support natural resource management and global change research.

View the file

Other files for this federal contract opportunity

Other files attached to Landsat Next, newest first.
File Type Posted
LNext SNR Note.pdf PDF
Landsat Next Draft SMRD.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A

Table 1. Comparison of proposed Landsat Next capabilities with Landsat 8/9

Landsat 8/9 Landsat Next Concept Spectral bands 9 VSWIR, 2 TIR 20 VSWIR, 5 TIR

Spatial resolution 15m panchromatic, 30m VSWIR, 120m TIR

10/20/30/60m VSWIR, 60m

TIR

Temporal revisit 16 days <= 16 days

SNR (VSWIR) OLI heritage OLI heritage (when aggregated to 30m)

NEdT (TIR, @300K) <0.4K required <0.2K required Radiometric Accuracy (VSWIR)

<5% at-sensor radiance error, <3% reflectance

<5% at-sensor radiance error, <3% reflectance

Radiometric Accuracy (TIR)

<2% radiance error @ 300K (1 sigma)

<1% radiance error @ 300K (1 sigma)

Table 2. Current Landsat Next Space Segment architecture options

Constellation Observatory Single-Platform

Observatory Global land revisit <=16 days <=16 days Orbit Sun-synch, altitude TBD Sun-synch, altitude TBD

Instruments per platform 1 (VSWIR+TIR) or 2

(VSWIR, TIR)

1 (VSWIR+TIR) or 2

(VSWIR, TIR)

Platforms Notionally 3 to 5 1 Swath-width per platform 40-80km >=185km

Risk Approach

Constellation Class B, via redundant Class C or lower platforms Class B