Attachment_A_-_Deliverables_and_Payment_Schedule_Rev_4__Amendment_6.pdf
PDF 264 KB Posted
- Attached to
- Master Agreement AZ|CTR052815
- Contract number
- CTR052815
- Issued by
- Arizona
About this file
This document is Attachment A - Deliverables and Payment Schedule (Revision 4, Amendment 6) for a state-level technology project, specifically involving the Arizona Department of Economic Security (ADES). The document appears to be part of a comprehensive contract for a large-scale system replacement or enhancement project, detailing specific deliverables, tasks, and associated costs across 19 distinct tasks.
The contract encompasses a wide range of technology implementation services, including application lifecycle management, system development, data conversion, testing, training, and operational transition. The total project cost is $38,539,646.08, with a total updated project cost of $41,670,843.58. Each task contains multiple deliverables with specific unit costs, quantities, and percentage holdbacks. Key tasks include Application Lifecycle Management, System Security Planning, Requirements Development, Data Conversion, User Training, Certification Compliance, Warranty Support, and Operations Transition. The deliverables are structured with detailed specifications, and many tasks have optional components "as dictated by ADES", suggesting flexibility in the project's scope and implementation.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A - Deliverables and Payment Schedule Rev 4, Amendment 6
Scope of Work Section #
Deliverable
ID #
Deliverable Unit of Measur
Qty Unit Cost Total Cost 10% Holdback Amount until fully certified
# of Staff assigned per deliverable
5.2.1.5.A 1.1 Application Lifecycle Management Plan Each 1 $ 783,542.77 $ 783,542.77 $ 78,354.28 14 5.2.1.5.B 1.2 Application Lifecycle and Source Code Each 1 $ 645,310.47 $ 645,310.47 $ 64,531.05 18 5.2.1.5.C 1.3 Populated ALM and SCM Systems Each 1 $ 1,018,911.27 $ 1,018,911.27 $ 101,891.13 22
$ 2,447,764.51 $ 244,776.45
5.2.2.5.A 2.1 Project Facility and equipment Plan (Optional as dictated by ADES) Each 1 $ 621,824.00 $ 621,824.00 $ 62,182.40 10 5.2.2.5.B 2.2 Certificate of Occupancy (Optional as dictated by ADES) Each 1 $ - $ - $ - 5 5.2.2.5.C 2.3 Project Facility (Optional as dictated by ADES) Each 50 $ 79,082.26 $ 3,954,113.00 $ 395,411.30 10
$ 4,575,937.00 $ 457,593.70
5.2.3.5.A 3.1 System Security Plan Each 1 $ 747,201.60 $ 747,201.60 $ 74,720.16 10
$ 747,201.60 $ 74,720.16
5.2.4.5.A 4.1 Project Implementation Plan and Project Schedule Each 1 $ 1,046,082.24 $ 1,046,082.24 $ 104,608.22 16 5.2.4.5.B 4.2 Weekly Project Status Reports, Meeting Agendas and Minutes Each 1 $ - $ - $ - 12 5.2.4.5.C 4.3 Monthly Project Status Reports Each 51 $ 14,944.03 $ 762,145.53 $ 76,214.55 12
$ 1,808,227.77 $ 180,822.78
5.2.5.5.A 5.1 Systems Development Life Cycle (SDLC) Methodology Each 1 $ 1,385,719.33 $ 1,385,719.33 $ 138,571.93 18 5.2.5.5.B 5.2 Requirements Refinement Strategy Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 8 5.2.5.5.C 5.3 Detailed Requirements Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 20 5.2.5.5.D 5.4 Requirements Traceability Matrix Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 20 5.2.5.5.E 5.5 System Architecture Document Each 1 $ 1,186,838.69 $ 1,186,838.69 $ 118,683.87 16 5.2.5.5.F 5.6 Functional System Design Each 16.5 $ 145,129.54 $ 2,394,637.41 $ 239,463.74 35 5.2.5.5.G 5.7 Technical System Design Each 16.5 $ 187,929.54 $ 3,100,837.41 $ 310,083.74 50 5.2.5.5.H 5.8 Application Development Plan Each 1 $ 747,201.60 $ 747,201.60 $ 74,720.16 10 5.2.5.5.I 5.9 Development Hardware and Software Plan Each 1 $ 747,201.60 $ 747,201.60 $ 74,720.16 16 5.2.5.5.J 5.10 Database Development Plan Each 1 $ 747,201.60 $ 747,201.60 $ 74,720.16 12 5.2.5.5.K 5.11 Entity Relationship Diagram Each 1 $ 1,018,911.27 $ 1,018,911.27 $ 101,891.13 16
$ 13,366,371.45 $ 1,336,637.15
5.2.6.5.A 6.1 Data Conversion and Migration Management Strategy Each 1 $ 1,018,911.27 $ 1,018,911.27 $ 101,891.13 10 5.2.6.5.B 6.2 Data Conversion and Migration Management Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 6 5.2.6.5.C 6.3 Data Conversion and Migration Test Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 6 5.2.6.5.D 6.4 Data Conversion and Migration Test Results Reports Each 1 $ 1,018,911.27 $ 1,018,911.27 $ 101,891.13 8
5.2.6.5.E 6.5 Converted Data Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 6
$ 4,075,645.08 $ 407,564.51
5.2.7.5.A 7.1 Configuration Management Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 12
5.2.7.5.B 7.2 Database Configuration Management Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 12 5.2.7.5.C 7.3 Systems Operating and Maintenance Procedures Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 8
5.2.7.5.D 7.4 System Development Environment Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 9
$ 2,377,459.63 $ 237,745.96
5.2.8.5.A 8.1 System Test Management Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 12
5.2.8.5.B 8.2 Test Environment and Documentation Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 10
5.2.8.5.C 8.3 System Test Documentation and Results Reports Each 16.5 $ 63,790.32 $ 1,052,540.30 $ 105,254.03 18
$ 2,411,088.66 $ 241,108.87
Total Cost for Task 3
Task 1
Total Cost for Task 1 Task 2*
Total Cost for Task 2 Task 3
Task 4
Total Cost for Task 4 Task 5
Total Cost for Task 5 Task 6
Total Cost for Task 6 Task 7
Total Cost for Task 7 Task 8
Total Cost for Task 8 Task 9
5.2.9.5.A 9.1 User Acceptance Test Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 11
5.2.9.5.B 9.2 Tools Implemented and System Ready to Test Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 10
5.2.9.5.C 9.3 User Acceptance Test Results Report Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 20
5.2.9.5.D 9.4 Update ALM and SCM Systems Content Each 1 $ 713,237.89 $ 713,237.89 $ 71,323.79 20
$ 2,751,060.43 $ 275,106.04
5.2.10.5.A 10.1 User Training Management Plan Each 1 $ 541,637.09 $ 541,637.09 $ 54,163.71 10
5.2.10.5.B 10.2 User Training Materials Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 16 5.2.10.5.C 10.3 User Training Reports Each 1 $ 759,637.09 $ 759,637.09 $ 75,963.71 6
5.2.10.5.D 10.4 Training Environment and Documentation Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 6
$ 2,659,822.54 $ 265,982.25
5.2.11.5.A 11.1 Technical Training and Knowledge Transfer Plan (Optional as dictated by ADES) Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 3 5.2.11.5.B 11.2 Technical Training Materials (Optional as dictated by ADES) Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 3 5.2.11.5.C 11.3 Technical Training and Knowledge Transfer Reports (Optional as dictated by ADES) Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 3
$ 50,945.55 $ 5,094.56
5.2.12.5.A 12.1 Readiness Assessment Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 20 5.2.12.5.B 12.2 Implementation Operations Plan Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 11 5.2.12.5.C 12.3 Implementation Plan Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 11 5.2.12.5.D 12.4 Implementation and Initialization Reports Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 10 5.2.12.5.E 12.5 Production ATLAS Replacement System Environment and Documentation Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 10
$ 1,698,185.45 $ 169,818.55
5.2.13.5.A 13.1 Certification Compliance Demonstration Materials Each 1 $ 169,818.55 $ 169,818.55 $ 16,981.86 10
5.2.13.5.B 13.2 Certification Review Materials Each 1 $ 169,818.55 $ 169,818.55 $ 16,981.86 6
5.2.13.5.C 13.3 PRWORA Distribution Test Deck Documentation Each 1 $ 169,818.55 $ 169,818.55 $ 16,981.86 10
5.2.13.5.D 13.4 Certification Compliance Corrections Results Each 1 $ 84,909.27 $ 84,909.27 $ 8,490.93 10
5.2.13.5.E 13.5 Certification Report Each 1 $ 84,909.27 $ 84,909.27 $ 8,490.93 10
$ 679,274.19 $ 67,927.42
5.2.14.5.A 14.1 Warranty Support Plan Each 1 $ 339,637.09 $ 339,637.09 $ 33,963.71 6
5.2.14.5.B 14.2 Weekly Warranty Reports Each 52 $ 3,265.74 $ 169,818.55 $ 16,981.86 2
5.2.14.5.C 14.3 Monthly Warranty Reports Each 12 $ 14,151.55 $ 169,818.55 $ 16,981.86 2
5.2.14.5.D 14.4 Warranty Completion Report Each 1 $ 30,567.34 $ 30,567.34 $ 3,056.73 2
$ 709,841.53 $ 70,984.15
5.2.15.5.G 15.1 Operations Plan Each 1 $ 679,274.18 $ 679,274.18 $ 67,927.42 6
5.2.15.5.H 15.2 Monthly Status Reports* Each 50 $ 339.64 $ 16,982.00 $ 1,698.20 6
5.2.15.5.I 15.3 Operations Documentation Each 1 $ 14,604.39 $ 14,604.39 $ 1,460.44 3
5.2.15.5.J 15.4 Annual Report Each 5 $ 14,944.03 $ 74,720.16 $ 7,472.02 6
5.2.15.5.K 15.5 System Documentation Update Each 1 $ 78,116.53 $ 78,116.53 $ 7,811.65 13
5.2.15.5.L 15.6 Business Continuity and Disaster Recovery Plan Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 4
$ 880,679.11 $ 88,067.91
5.2.16.5.A 16.1 Enhancement Plan Each 1 $ 91,702.01 $ 91,702.01 $ 9,170.20 3
$ 91,702.01 $ 9,170.20
5.2.17.5.A 17.1 Operations Transition Plan Each 1 $ 84,909.27 $ 84,909.27 $ 8,490.93 6
5.2.17.5.B 17.2 Operations and Technical Training Plan Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 6
5.2.17.5.C 17.3. Operations and Technical Training Report Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 6
Total Cost for Task 9
Total Cost for Task 15
Task 10
Total Cost for Task 10 Task 11
Total Cost for Task 11 Task 12
Total Cost for Task 12 Task 13
Total Cost for Task 13 Task 14
Total Cost for Task 14 Task 15
Task 16
Total Cost for Task 16 Task 17
5.2.17.5.D 17.4 Operations Transition Report Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 6
$ 135,854.82 $ 13,585.48
5.2.18.5.A 18.1 Various Environment Creation Each 1 $ 186,800.40 $ 186,800.40 $ 18,680.04 3 $ 186,800.40 $ 18,680.04
5.2.19.5.A 19.1 Project Closeout Report Each 1 $ 16,981.85 $ 16,981.85 $ 1,698.19 2 $ 16,981.85 $ 1,698.19
$ 38,539,646.08 $ 3,853,964.61 $ 41,670,843.58 $ 4,167,084.36
Task 19
Total Cost for Task 19 Total Project Cost
Total Updated Project Cost
Total Cost for Task 17 Task 18
Total Cost for Task 18