Attachment 7 - VANCHCS Mare Island Project Manual.pdf

PDF 2 MB Posted

Attached to
Y1BG--612-21-2-6702-0001 612-20-702 EHRM Infrastructure Upgrade - Mare Island (VA-21-00047806)
Solicitation number
36C77621R0171
Issued by

About this file

This notice provides details for an upcoming Design-Build firm-fixed-price contract solicitation to upgrade telecommunications infrastructure at the Mare Island VA Clinic to meet Electronic Health Records Modernization standards. The Department of Veterans Affairs, through its Veterans Health Administration Program Contracting Activity Central office, will solicit proposals to relocate or remodel approximately five existing telecommunications rooms and one data center. Offered work includes design, pre-construction, construction, and closeout services to deliver turnkey upgraded spaces adhering to Office of Information Technology and EHRM requirements. The solicitation will be conducted under FAR Part 36 Two-Phase Design-Build Procedures and issued as a total Service-Disabled Veteran-Owned Small Business set-aside in July 2021, with a performance period of approximately 540 calendar days from notice to proceed. The project magnitude is estimated between $2,000,000 to $5,000,000.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VISN 21 CM/PM Electronic Health

Records Modernization (EHRM) PHASE I Support Task

PO# 612C209

Northern California Health Care System Martinez VA Medical Center

Mare Is land VA Cl in ic

Fairf ie ld VA Cl in ic

Ta b l e o f C o n t e n t s

Project TeamContributors:

Vicinity Map/Building Addresses

Campus Map / Building Information

VAMC Fiber Distances

Door Security Requirements

Martinez VAMC– Bldg. 14

First Floor Plan

Martinez VAMC– Bldg. 15

First Floor Plan

Martinez VAMC– Bldg. 19

First Floor Plan

Second Floor Plan

Martinez VAMC– Bldg. 20

First Floor Plan - Napa

First Floor Plan – Shasta

First Floor Plan - Main

First Floor Plan - Tahoe

Martinez VAMC– Bldg. 21

First Floor Plan

Second Floor Plan

Third Floor Plan

Fourth Floor Plan

Martinez VAMC– Bldg. 22

First Floor Plan

Martinez VAMC– Bldg. 23

Second Floor Plan

Martinez VAMC– Bldg. 24

First Floor Plan

Identification of Network Spaces:

12 30

Identification of Off Campus Network

Spaces:

Network Space Design:

Bldg. 14:

Wall Hung Cabinet

Design Matrix

Enlarged Plan – Existing

Bldg. 15:

Wall Hung Cabinet

Design Matrix

Enlarged Plan – Existing

Bldg. 19:

A203

Design Matrix

Enlarged Plan – Existing

Bldg. 19:

D204

Design Matrix

Enlarged Plan - Existing

Bldg. 20:

N114A

Design Matrix

Enlarged Plan – Existing

Fairfield OPC – Bldg. 778

First Floor Plan

Fairfield OPC – Bldg. 790

First Floor Plan

Mare Island OPC

First Floor Plan

Second Floor Plan

Martinez VAMC– Bldg. 26

Second Floor Plan

Martinez VAMC– Bldg. R1

First Floor Plan

VHAMACGomezM Text Box This package is for Mare Island only. Ignore all the information about Martinez and Fairfield

Bldg. 21:

E100

Design Matrix

Enlarged Plan – Existing

Bldg. 21:

E110

Design Matrix

Enlarged Plan – Existing

Bldg. 21:

E404

Design Matrix

Enlarged Plan – Existing

Bldg. 22:

Design Matrix

Enlarged Plan – Existing

Bldg. 23:

Design Matrix

Enlarged Plan – Existing

Bldg. 24:

BC02

Design Matrix

Enlarged Plan – Existing

Bldg. 26:

Design Matrix

Enlarged Plan – Existing

Network Space Design (cont’d)

Ta b l e o f C o n t e n t s

Appendix A – Power Installation Example

Appendix B – Compliance Requirements

Appendix C – Rack Labeling Standard

Appendix

Bldg. R1:

R142

Design Matrix

Enlarged Plan – Existing

Fairfield – Bldg. 778:

A145

Design Matrix

Enlarged Plan – Existing

Fairfield - Bldg. 778:

B126

Design Matrix

Enlarged Plan – Existing

Fairfield - Bldg. 790:

S108

Design Matrix

Enlarged Plan – Existing

Mare Island OPC:

Design Matrix

Enlarged Plan – Existing

Mare Island OPC:

2081 & 2082

Design Matrix

Enlarged Plan – Existing

Bldg. 20:

H141

Design Matrix

Enlarged Plan – Existing

Bldg. 20:

T126

Design Matrix

Enlarged Plan – Existing

Off Campus Network Space Design

Bldg. 20:

S143A

Design Matrix

Enlarged Plan – Existing

VHAMACGomezM

P R O J E C T C O N TA C T D I R E C T O R Y

Concourse Federal Group

123 S. Royal Street Alexandria, Virginia 22314

Tim Hower, Project Manager ........................................................................................thower@concousefederal.com

Lorena Alvarez................................................................................................................IaIvarez@concousefederaI.com

Mike Olson ................................................................................................................... molson@concousefederal.com

Marshall Contino, Concourse A|E Vice President ....................................................... mcontino@concousefederal.com

DHE Engineering 3300 N. Central Ave. 3300 Tower Suite, 1520, Phoenix, AZ 85012

Jasper Lim Electrical Engineer.................................................................................... jlim@dheeng.com

Kory Young, EIT, Senior Mechanical Engineer................................................................kyoung@dheeng.com

VA Northern California Health Care System

Travis Dilts (Sacramento, Chief Engineer)…………………………………………………………………Travis.Dilts2@va.gov

Jonathan Bassignani (Sacramento, Chief of Projects)……………………………………………….Jonathan.Bassignani@va.gov

V i c i n i t y M a p B u i l d i n g A d d r e s s e s

M a r e I s l a n d V A C l i n i c 2 0 1 W a l n u t A v e n u e B u i l d i n g 2 0 1 M a r e I s l a n d , C A 9 4 5 9 2

M a r t í n e z V A M e d i c a l C e n t e r 1 5 0 M u i r R o a d M a r t í n e z , C A 9 4 5 5 3

F a i r f i e l d V A C l i n i c 1 0 3 B o d i n C i r c l e T r a v i s A F B , C A 9 4 5 3 51

3 1

VHAMACGomezM Polygon

VHAMACGomezM

M a r t i n e z B u i l d i n g I n f o r m a t i o n

Bldg. # Bldg. Name TR Qty Levels

12,13,14 Engineering Shops 1 2

15 Engineering Warehouse 1 1

19 Outpatient Clinic 2 2

20 Center for Rehab & Extended Care 4 1

21 Administration 1 4

22 Neuro-Rehab 1 2

23 Center of Integrated Brain & Health Wellness 1 2

24 Mental Health Clinic 1 2

R1 Research Lab/CPAC/Social Work SVC 1 1

Bldg. # Bldg. Name Data Ctr Levels

21 Administration 1 1

M a r t i n e z C a m p u s M a p

VAMC FIBER DISTANCES

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

CREATE REDUNDANT WAN PATH – ASSUME 1000’-0”

CONCRETE ENCASED 6” PVC OR HDPE WITH (6) 1”

INTERDUCTS

VAMC Martinez

Building Floor Room

Distance (Ft.) from Fiber Hub

Fiber Type Notes Interior - 4" EMT

Exterior –Fiber to be pulled through new duct loop provided via project and described in note below. (Intent is to feed each building from two (2) directions around the loop

30 - ACC 1 1-B11 24 strand singlemode

30 - ACC 2 2-B45 24 strand singlemode

15 1 Engineering Office 200 2600 24 strand singlemode

15 1 103 300 2600 24 strand singlemode

19 2 A203 500 2600 24 strand singlemode

19 2 D203 525 2600 24 strand multimode

19 2 D204 550 2600 24 strand multimode

20 - NAPA 1 N114A 200 2600 24 strand multimode

20 - SHASTA 1 S143A 150 2600 24 strand multimode

20 - MAIN 1 H121 150 2600 24 strand multimode

20 - TAHOE 1 T126 150 2600 24 strand multimode

21 1 E110 Server Room

21 1 E100 80 24 strand multimode

21 4 E404 180 24 strand multimode

22 1 125 150 2600 24 strand multimode

23 2 220 100 2600 24 strand multimode

24 1 BC02 150 2600 24 strand multimode

R1 1 R142 250 2600 24 strand multimode

CREATE UNDERGROUND LOOP TO ENABLE DUAL FEEDING OF FIBER FROM SERVER ROOM TO EACH BUILDING (2600’-0”) LOOP TO BE CREATED WITH CONCRETE ENCASED 6” PVC OR HDPE CONDUITS WITH (6) 1” INTERDUCTS IN EACH

CONDUIT

DOOR SECURITY REQUIREMENTS

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

Remediated, expanded and newly created spaces must have security access control and monitoring IAW Appendix A

(chart)

I D E N T I F I C AT I O N O F N E T WO R K S PAC E S

BLDG: 1 4

LEVEL: 1

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

REMEDIATE IN PLACE

ENGINEERING OFFICE

WALL HUNG CABINET.

REPLACE EXISTING

CABINET WITH A SECURE IT

CABINET

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

BLDG: 1 5

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

REMEDIATE IN PLACE

CABINET LOCATED ON WALL

OFFICE

ROOM 103

(VERIFY LOCATION)

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NOTE: ROOM NOT VISITED BY RFP DEVELOPER.

SCOPE DERIVED FROM FACILITY SELF-ASSESSMENT

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

OI&T / ELECTRICAL ROOM A113

RELOCATE IT EQUIPMENT TO NEW TR ROOM A203

ROOM A113 TO BECOME DEDICATED ELECTRICAL ROOM

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

ELECTRICAL/IT ROOM D101

RELOCATE IT EQUIPMENT TO NEW TR ROOM A203

ROOM D101 TO BECOME DEDICATED ELECTRICAL ROOM

ELECTRICAL / IT ROOM D105

RELOCATE IT EQUIPMENT TO NEW TR ROOM A203

ROOM D105 TO BECOME DEDICATED ELECTIRICAL ROOM

N

BLDG: 1 9

LEVEL: 1

SCALE: 1/32” = 1’-0”

DATE: 12/22/2020

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

• PROVIDE NEW DROP-IN CEILING

• PROVIDE NEW LIGHTING

EXISTING TR LOCATION(S)

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

N

REMEDIATE IN PLACE

OI&T

EQUIPMENT

D204

NEW TR ROOM

A203

BLDG: 1 9

LEVEL: 2

SCALE: 1/32” = 1’-0”

DATE: 12/22/2020

ELECTRICAL / OI&T ROOM D207

RELOCATE IT EQUIPMENT TO NEW TR ROOM A203

ROOM D207 TO BECOME DEDICATED ELECTRICAL ROOM

ELECTRICAL / IT ROOM A202

RELOCATE IT EQUIPMENT TO NEW TR ROOM A203

ROOM A202 TO BECOME DEDICATED ELECTRICAL ROOM

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

BLDG: 2 0 - N A P A

SCALE: 1/16” = 1’-0”

DATE: 12/22/2020

N

EQUIPMENT ROOM N141

RELOCATE TO NEW TR ROOM

N114A

EXISTING SPACE TO BE USED AS

GENERAL STORAGE

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR ROOM

N114A

155 SF

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

BLDG: 2 0 - S H A S T A

SCALE: 1/16” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR

ROOM S143A

148 SF

EQUIPMENT ROOM S141

RELOCATE TO NEW TR ROOM S143A

EXISTING SPACE TO BE USED AS GENERAL

STORAGE

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

BLDG: 2 0 - M A I N

SCALE: 1/16” = 1’-0”

DATE: 12/22/2020

N

REMEDIATE IN PLACE

EQUIPMENT

ROOM H121

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 2 0 - T A H O E

SCALE: 1/16” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR ROOM

T126

EQUIPMENT ROOM T128

RELOCATE TO NEW TR ROOM T126

EXISTING SPACE TO BE USED AS

GENERAL STORAGE

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

BLDG: 2 1

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

REMEDIATE IN PLACE

SERVER ROOM

ROOM E110

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

IT ROOM

ROOM E100

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

LEVEL: 2

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

RELOCATE TO ROOM E404

IT ROOM

ROOM E200

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

LEVEL: 3

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

RELOCATE TO ROOM E404

IT ROOM

ROOM E300

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

LEVEL: 4

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

COMPUTER ROOM

ROOM E404

RELOCATE TO ROOM E404

IT ROOM

ROOM E400

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 2 2

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

IT ROOM

ROOM 125

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 2 3

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

OI&T AND ELECTRICAL

ROOM 220

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 2 4

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

IT

ROOM BC02

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 2 6

SCALE: 3/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

TEL/DATA

ROOM 211

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: R 1

SCALE: 1/16” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR ROOM R142

IT ROOM R128B

RELOCATE TO NEW TR ROOM R142

EXISTING SPACE TO BE USED AS

GENERAL STORAGE LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

I D E N T I F I C AT I O N O F O F F C A M P U S N E T WO R K S PAC E S

BLDG: 778 - FAIRFIELD

SCALE: 1/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

FAIRFIELD VA OPC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

IT

ROOM A145

REMEDIATE IN PLACE

IT

ROOM B126

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 790 - FAIRFIELD

SCALE: 1/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

FAIRFIELD VA OPC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

MECHANICAL

ROOM S108

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

BLDG: 201 - MARE ISLAND

SCALE: 1/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARE ISLAND VA OPC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

REMEDIATE IN PLACE

IT

ROOM 1048

IT ROOM 1066

RELOCATE TO IT ROOM 1048

EXISTING SPACE TO BE USED AS

GENERAL STORAGE

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

BLDG: 201 - MARE ISLAND

SCALE: 1/32” = 1’-0”

DATE: 12/22/2020

N

EXISTING TR LOCATION(S)

MARE ISLAND VA OPC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

EXPAND IN PLACE

IT

ROOM 2081

IT ROOM 2043

RELOCATE TO IT ROOM 1048

EXISTING SPACE TO BE USED AS

GENERAL STORAGE

LEGEND

LOCATION OF EXISTING

TR /DC

POTENTIAL LOCATION

FOR RELOCATED TR

ROOMS TO EXPAND IN

PLACE

NOTE:

ALL ABANDONED TR ROOMS ARE TO BE

REPURPOSED AS GENERAL STORAGE OR AS

INDICATED ON FLOOR PLAN. MINIMUM

REQUIREMENTS FOR TR ROOMS TO BE

ABANDONED:

• REMOVE ALL IT EQUIPMENT

• SEAL ALL PENETRATIONS IN ACCORDANCE

WITH FIRE REQUIREMENTS

• PROVIDE NEW VCT FLOORING

• REMOVE EXISTING PLYWOOD ON WALLS,

PATCH, REPAIR AND PAINT WALLS

N E T WO R K S PAC E D E S I G N

** See Appendix D for Excel PDF with Estimated data from initial investigation

BLDG: 1 4

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

WALL HUNG CABINET

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NOTE: REPLACE WALL HUNG CABINET WITH A

SECURE IT CABINET

ENGINEERING OFFICE

WALL MOUNTED CABINET

MARTINEZ BLDG 14

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment Relocate piping or pipe trough

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 450 Approximate total cable length =

74250

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment Provide new rack as required.

BLDG: 1 5

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

WALL HUNG CABINET

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NOTE: ROOM NOT VISITED BY RFP DEVELOPER.

SCOPE DERIVED FROM FACILITY SELF-ASSESSMENT

OFFICE

ROOM 103

MARTINEZ BLDG. 15 ROOM 103 UNSURVEYED

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment If water piping overhead then relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = TBD Approximate total cable length = TBD

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

Inadequate rack space for new equipment Provide new rack as required.

NOTE: REPLACE WALL HUNG CABINET WITH A

SECURE IT CABINET

VERIFY LOCATION

X

BLDG: 1 9

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

A203

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR ROOM

ROOM A203

101 SF

MARTINEZ BLDG. 19 ROOM A203 NEW TR

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment If water piping overhead, then relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 450 Approximate total cable length =

74250’

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment

BLDG: 1 9

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

D204

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

OI&T

EQUIPMENT

ROOM D204

MARTINEZ BLDG. 19 ROOM D204

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 300 Approximate total cable length =

49500’

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

Inadequate rack space for new equipment

BLDG: 2 0 N A P A

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N114A

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

EXISTING

ELECTRICAL

ROOM N112

EXISTING

TOLIET

RM N114B

NEW WALL

MARTINEZ BLDG. 20 ROOM N114A NEW TR

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment If water piping overhead then relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 800 Approximate total cable length = 132000’

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment Provide new rack as required.

NEW TR ROOM

ROOM N114A

155 SF

REMOVE EXISTING WALL

BLDG: 2 0 S H A S T A

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

S143A

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

MARTINEZ BLDG. 20 ROOM S143A NEW TR

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and

Special Telecommunications Systems Design

Manual

X Piping over equipment If water piping then relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per

VA Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = TBD Approximate total cable length = TBD

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260'

(70-80M)

Inadequate rack space for new equipment Provide new rack as required.

EXISTING

EQUIPMENT

ROOM S141

NEW TR ROOM

ROOM S143A

148 SF

EXISTING

TOLIET

RM S143B

NEW WALL

REMOVE

EXISTING

WALL

BLDG: 2 0 - M A I N

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

H141

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

IRM

ROOM H141

MARTINEZ BLDG. 20 ROOM H141

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 200 Approximate total cable length =

33000’

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M) x Inadequate rack space for new equipment Provide one new rack as required.

BLDG: 2 0 - T A H O E

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

NEW TR T126

MARTINEZ VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR ROOM

ROOM T126

73 SF

MARTINEZ BLDG. 20 ROOM T126 NEW TR

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment If water piping then relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 200 Approximate total cable length =

33000’

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

E100

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

IT ROOM

E100

MARTINEZ BLDG. 21 ROOM E100

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 800. Approximate total cable length =

132000'.

X

Micro condensate pump

Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment Provide 8 new racks.

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

E110

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

SERVER ROOM

E110

The electrical panels in the server room need to be re-located into the electrical room or

E100. Install an AC unit. Reorganize and clean room to allow for Cerner equipment. . There are usable racks that are nearly empty and will be consolidated to allow for new racks.

Verify with end users which equipment will remain, and which equipment will relocate.

MARTINEZ BLDG. 21 ROOM E110 (DATA CENTER)

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient Central UPS power backup.

Design Build contractor to determine size of Central

UPS.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing Telecom Main Ground Bar

(TMGB)

Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs three (3) new temperature monitoring sensors and humidity sensors per rack.

Provide controls from BMS

X Inadequate grounding connections to metal objects in date canter.

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment Relocate piping or pipe trough

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X

No redundant fiber optic cable feeds entering the building on opposite faces.

Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 400 Approximate total cable length = 66000'

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment

LEVEL: 4

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

E404

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

COMPUTER ROOM

E404

MARTINEZ BLDG. 21 ROOM 404

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate

Replace existing Liebert units like-for-like. Board up windows with insulation to reduce heat transfer.

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat X

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = 400 Approximate total cable length =

66000’

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment Provide 10 new racks.

BLDG: 2 2

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

IT

MARTINEZ BLDG. 22 ROOM 125

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = TBD Approximate total cable length = TBD

X Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

X Inadequate rack space for new equipment Provide one new rack.

BLDG: 2 3

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

OI&T AND

ELECTRICAL

MARTINEZ BLDG. 23 ROOM 220

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = TBD Approximate total cable length = TBD

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

Inadequate rack space for new equipment Provide new rack as required.

BLDG: 2 4

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

BC02

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

IT

BC02

ADDITIONAL SECURITY FEATURES REQUIRED:

HOLD OPEN ALERT

PIN PAD

ELECTRIC STRIKE

MARTINEZ BLDG. 24 ROOM BC02

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

X Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = TBD Approximate total cable length = TBD

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

Inadequate rack space for new equipment Provide new rack as required.

BLDG: 2 6

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

TELE/DATA

MARTINEZ BLDG. 26 ROOM 211

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X Rack Temperature/Humidity

Monitoring Inadequate

Rack needs one (1) new temperature monitoring sensors, humidity sensor, and controls from

BMS

X Inadequate grounding connections to metal objects in TR

Provide bonding conductors to non-energized metal surfaces per VA Telecommunications and Special

Telecommunications Systems Design Manual

Piping over equipment Relocate piping or pipe trough X

TR ground bar not connected to

Telecom Main Ground Bar (TMGB) in the data room

Provide grounding cable to MDF ground bar.

X UPS Central Monitoring BACnet conversion X No telecommunications bonding backbone to other TR grounding bars

Provide grounding conductor to nearest TR per VA

Telecommunications and Special

Telecommunications Systems Design Manual

X No condensate leak detection Needs condensate leak detection

C A

B

LI

N G

X Inadequate fiber optic cabling to TR Install new as required

Remote Controlled battery thermostat Wired thermostat

Horizontal and/or patch data cabling below minimum Cat 5e.

Replace all cabling with Cat 6A. Approximate number of cables = TBD Approximate total cable length = TBD

Micro condensate pump Commercial condensate pump X Horizontal cable run not to exceed 292 feet

Conduct diamond analysis to verify maximum horizontal distance does not exceed 230-260' (70-

80M)

Inadequate rack space for new equipment Provide new rack as required.

BLDG: R 1

SCALE: 1/4” = 1’-0”

DATE: 12/22/2020

N

R142

SACREMENTO VAMC

NORTHERN CALIFORNIA HEALTH CARE SYSTEM

NEW TR ROOM

R142

93 SF

MARTINEZ BLDG. R1 ROOM R142 NEW TR

C O

O

LI

N G

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

E

LE

C T

R

IC

A L

"X" EXISTING ISSUES RECOMMENDED SOLUTIONS

X Cooling inadequate Needs dedicated 1.5 ton ductless split HVAC unit

X Insufficient redundant power connections for network equipment.

Provide (2) 30A, 208V, 5 wire NEMA L21-30R receptacles, each power from an independent power source, mounted near the equipment rack containing the zone PDU

X Insufficient UPS power backup.

Provide UPS with minimum 20 minute run time capacity and redundant, hot swappable batteries.

X Room Temperature/Humidity

Monitoring Inadequate

Room needs new COMBINATION temperature and humidity monitoring and/or controls from

BMS

X Missing grounding bus bar Install copper grounding bus bar

X…