This price sheet outlines pricing for road maintenance and facility cleaning services required by the Department of Agriculture Forest Service under solicitation number 1240BF23Q0072. The services include roadside brushing, grading, rest room cleaning, floor cleaning of various surface types across three categories of facilities, continuous cleaning of a physical fitness center, and special/emergency/bio-hazard cleaning. Pricing is provided on a unit rate basis by item and totals are calculated based on estimated quantities. The period of performance for the base year is 11 months from date of award through 30 November 2023. Responses to this solicitation are due by the date specified in the opportunity notice.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240BF23Q0072-0001 Combined SS for WRD Road Maintenance.pdf | ||
| Attachment 9 - Questions and Answers.pdf | ||
| Attachment 5 - Vicinity Map.pdf | ||
| Attachment 2 - FSSS Requisition.pdf | ||
| Attachment 4 - Typical Brushing.pdf | ||
| Attachment 8 - SCA WD 2015-5685 R20 (2023.07.27) TNF.pdf | ||
| Attachment 3 - Typical Overlay.pdf | ||
| 1240BF23Q0072 Combined SS for WRD Road Maintenance.pdf | ||
| Attachment 1 - PWS for WRD Road Maintenence.pdf | ||
| Attachment 6 - PBS 800-861.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SUMMARY SHEET
ONLY FILL OUT THE YELLOW HIGHLIGHTED CELLS THROUGHOUT THIS BID SHEET, THEY WILL FEED INTO THE OTHER SECTIONS. DO NOT CHANGE THE FORMULAS IN THIS SHEET.
WRD Road Maintenance
1240BF23Q0072
| Company Name: |
| Point of Contact: |
| CAGE Code: |
| UEI Number: |
| Address: |
| Phone: |
| E-mail: |
| BASE PERIOD (Date of Award - 30 November 2023) | |||||
| Item Number | Description | Estimated Quantity | Unit of Issue | Unit Price | Total |
| 0001 | WRD Road Maintenance | 1 | Job | $ - 0 | |
| Mobilization | 1 | Each | $ - 0 | ||
| Roadside Brushing Method A (Per Attachment 7, Section 842) | 14.5 | Mile | $ - 0 | ||
| Roadside Brushing Method B (Per Attachment 7, Section 842) | 13.3 | Mile | $ - 0 | ||
| Road Grading Compaction A (Per Attachment 7, Section 811) | 57.5 | Mile | $ - 0 | ||
| Road Grading Compaction B (Per Attachment 7, Section 811) | 6.3 | Mile | $ - 0 |
NOTES: (1) The quantities in this price sheet are estimates only. The unit prices will not change based on quantities ordered.
Sheet1
| BASE YEAR | |||||||||
| CLIN # | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL COST | ||||
| 0002 | Category I Administrative Buildings | ||||||||
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. | |||||||||
| Period of Performance: 11 months (Base Year) | |||||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ||||||
| 0002AA | Category I Administrative Buildings Rest Room Cleans | 2,620,889 | sq. ft | $ 0.0408 | $ 106,932.25 | *55,026x47.63= 2,620,888.58 SF (11month period) | 55026.0041990342 | 52 | 2,861,352.22 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period. | 0 | 52 | 0.00 | ||||||
| Period of Performance: 11 months (Base Year) | 0 | 52 | 0.00 | ||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ERROR:#VALUE! | 52 | ERROR:#VALUE! | |||
| 0002AB | Category I Administrative Buildings Hard Floor Cleans | 6,586,752 | sq. ft | $ 0.0231 | $ 152,153.97 | *94,515x47.63= 4,501,749.45 SF | 138289.986773042 | 52 | 7,191,079.31 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period. | 0 | 52 | 0.00 | ||||||
| Period of Performance: 11 months (Base Year) | 0 | 52 | 0.00 | ||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ERROR:#VALUE! | 52 | ERROR:#VALUE! | |||
| 0002AC | Category I Administrative Buildings Carpet Floor Cleans | 1,204,420 | sq. ft | $ 0.0192 | $ 23,124.87 | *19,831x47.63= 944,550.53 SF | 25287.0098677304 | 52 | 1,314,924.51 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period. | $ 282,211.10 | 0 | 52 | 0.00 | |||||
| Period of Performance: 11 months (Base Year) | 0 | 52 | 0.00 | ||||||
| 0 | 52 | 0.00 | |||||||
| CLIN # | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL COST | 52 | 0.00 | ||
| 0003 | Category II Child Development Facilities | 52 | 0.00 | ||||||
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. | 52 | ||||||||
| Period of Performance: 11 months (Base Year). | |||||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ||||||
| 0003AA | Category II Child Development Facilities Hard Floor Cleans | 11,485,212 | sq. ft | $ 0.0252 | $ 289,427.35 | *390,060x238.15weeks = 9,302,139 SF | TOTAL: 11,485,212.42 SF | ||
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period. | *7,639x285.78 weeks = 2,183,073 SF | ||||||||
| Period of Performance: 11 months (Base Year) | |||||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ||||||
| 0003AB | Category II Child Development Facilities Carpet Floor Cleans | 685,729 | sq. ft | $ 0.0194 | $ 13,303.14 | *1113x238.15 weeks = 265,060.95 SF | TOTAL: 685,729.11 | ||
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period. | *1472x285.78 weeks = 420,668.16 SF | ||||||||
| Period of Performance: 11 months (Base Year) | $ 302,730.50 |
| CLIN # | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL COST | |||
| 0004 | Category III Physical Fitness Centers | |||||||
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. | ||||||||
| Period of Performance: 11 months (Base Year). | ||||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | |||||
| 0004AA | Category III Physical Fitness Centers Hard Floor Cleans | 3,010,146 | sq. ft | $ 0.0344 | $ 103,549.02 | Bldg 3452(6W) 1,330,305.90 SF | 1W*Hockey 1,323x17.32 = 22,914.36 SF | 1,330,305.90 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period. | Bldg 3709 (7W) 1,416,325.68 SF | 6W*Hockey 1,323x30.31= 240,600.00 SF | 1,416,325.68 | |||||
| Period of Performance: 11 months (Base Year). | 22,914.36 | |||||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | 240,600.00 | ||||
| 0004AB | Category III Continuous Cleaning Physical Fitness Center Bldg 3709 | 11 | monthly | $ 4,322.26 | $ 47,544.86 | Total Hours 1,657.05 | Provide locker room cleaning from 13:00-15:30 daily 1Male/1Female 2-1/2 hours each. | 3,010,145.94 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. | ||||||||
| Period of Performance: 11 months (Base Year). |
| CLIN # | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL COST |
| 0005 | Special /Emergency/Bio-Hazard Cleans | ||||
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. | |||||
| Period of Performance: 11 months (Base Year). | |||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ||
| 0005AA | Special Cleaning | 40,538 | per sq. ft | $ 0.28 | $ 11,472.25 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 20% of the total square footage for the contract. | |||||
| Period of Performance: 11 months (Base Year). |
| QTY | UNIT | UNIT PRICE | TOTAL COST | ||
| 0005AB | Emergency Cleaning | 22,296 | per sq. ft | $ 0.38 | $ 8,405.59 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Emergency Cleaning CLIN represents 11% of the total square footage for the contract. | |||||
| Period of Performance: 11 months (Base Year). | |||||
| QTY | UNIT | UNIT PRICE | TOTAL COST | ||
| 0005AC | Bio-Hazard Cleaning | 10,134 | per sq. ft | $ 1.13 | $ 11,471.69 |
| The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 5% of the total square footage for the contract. | |||||
| Period of Performance: 11 months (Base Year). |
| CLIN # | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL COST |
| 0006 | CONTRACT MANPOWER REPORTING | 1 | EA | $ 100.0000 | $ 100.0000 |
| Contractor Manpower Reporting Costs: 1 May 2016 to 30 March 2017. The Contractor Manpower Reporting requirement is associated with the Office of the Assistant Secretary of the Army (Manpower and Reserve Affairs) requirement to obtain better visibility of the Contractor service workforce. | |||||
| The Contractor is required to enter data into the Contractor Manpower Reporting Application (CMRA) system as outlined in local information titled Contractor Manpower Reporting located with the clauses incorporated into the contract. Reporting period will be the period of performance not to exceed 12 months ending 30 September of each Government fiscal year and must be reported by 31 October of each calendar year. Data must be accurate and complete and entered into CMRA during the data gathering period of every year, or part of a year, for which the contract is in force. NOTE: If the reporting of Manpower Equivalents is not separately priced, insert “NSP in the blank shown. | |||||
| BASE YEAR TOTAL COST: | $ 767,485.01 |