Attachment 7 - 2024 WCS Brushing FSSS.pdf
PDF 460 KB Posted
- Solicitation number
- 1284LL24Q0088
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is an attachment to a federal contract opportunity for Clearing & Brushing Services at Various Locations in Rexford and Fortine Ranger Districts, Kootenai National Forest, Montana.
The key details are:
- This is a 100% Small Business Set-Aside procurement using Lowest Price Technically Acceptable (LPTA) evaluation procedures to award a firm-fixed-price Purchase Order.
- The due date for quotes/proposals is 5:00 p.m. Central Time on 16 September 2024.
- All questions must be submitted to mary.harding@usda.gov no later than 09 September 2024.
- There will not be a Site Visit, but contractors can visit the site on their own by contacting the Eureka Ranger Station Technical Services at 406-296-7180.
- The Statement of Work covers clearing and brushing requirements within designated clearing limits, including scalloping clearing lines, clearing vistas, thinning vegetation, and removal of individual trees and stumps.
- Specific details are provided on measurement and payment terms, use of roads by the contractor, disposal of materials, and other technical requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04
104.06 Use of Roads by Contractor
105 - Control of Material
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05
108 - Prosecution and Progress
Delete Section 108
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09
109.01 Measurement of Work
109.02 Measurement Terms and Definitions
155 - Schedules for Construction Contracts
Delete Section 155
201 - Clearing and Grubbing
201.06 Disposal
202 - Additional Clearing and Grubbing
203 - Removal of Structures and Obstructions
203.04 (b) General
203.05 Disposing of Material
Preface Preface_wo_04_24_2024
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016
Add the following paragraph to Subsection 101.01:
101.01 Meaning of Terms.
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_National_11_9_2016
Add the following to Subsection 101.03:
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations
AFPA — American Forest and Paper Association
FSAR — Forest Service Acquisition Regulations
MSHA — Mine Safety and Health Administration
NESC — National Electrical Safety Code
WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
101.04_National_1_22_2020
Make the following changes to Subsection 101.04:
101.04 Definitions.
Delete these definitions and replace the following:
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Add the following definitions:
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards —
The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and IRTC contract provisions to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016
Delete Section 102 in its entirety.
Delete Section 102.
103 - Scope of Work 103.00_National_11_9_2016
Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work 104.00_National_11_9_2016
Delete Subsections 104.01, 104.02, and 104.04.
Delete Subsections 104.01, 104.02, 104.04.
104.06_National_11_9_2016
Add the following to Subsection 104.06:
104.06 Use of Roads by Contractor.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.05_National_6_29_2020
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.
106 - Acceptance of Work 106.01_National_7_18_2017
Delete Subsection 106.01 and replace with the following:
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project.
When the Government tests work, copies of test reports are furnished to the Contractor upon request.
Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.
The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;
providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
1. Sampling method;
2. Number of samples;
3. Sample transport;
4. Test procedures;
5. Testing laboratories;
6. Reporting;
7. Estimated time and costs; and
8. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
1. Have the work accepted at a reduced price; or
2. Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02_National_11_9_2016
Delete Subsection 106.02 and replace with the following:
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.
107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017
Delete Subsection 107.05.
Delete Subsection 107.05.
108 - Prosecution and Progress 108.00_National_11_9_2016
Delete Section 108 in its entirety.
Delete Section 108.
109 - Measurement and Payment 109.00_National_11_9_2016
Delete Subsections 109.06, 109.07, 109.08, and 109.09:
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.01_National_2_22_2019
Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:
109.01 Measurement of Work.
Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.
Table 109-1
Decimal Accuracy of Quantities for Final Payment
Pay Item Level of Precision Linear Foot 1
Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1 Cubic Yard 1
Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;
0.1
Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1
Exception--Calcium Chloride;
Sodium Chloride; Hydrated Lime;
Bituminous Materials; Pavements;
Bed Course Materials
0.01
Hour 0.1
MFBM 0.01
Station Yard 1 Cubic Yard Mile 1 Ton Mile 1
109.02_National_11_9_2016
Add the following sentence to Subsection 109.02(b):
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
155 - Schedules for Construction Contracts 155.00_National_11_9_2016
Delete Section 155 in its entirety.
Delete Section 155.
201 - Clearing and Grubbing 201.03_Regional_8_16_2021
Delete the last sentence in the second paragraph of Subsection 201.03.
201.03 General.
Delete paragraph (c) and (d) of Subsection 201.04 and replace with the following:
201.04 Clearing.
3. (c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within six inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract; and
4.
5. (d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of 14 FT. If required, remove other branches to present a balanced appearance. Trim according to accepted tree surgery practices. Treat wounds with tree wound dressing.
201.06_National_2_22_2018
Delete the first sentence of Subsection 201.06 and replace the following:
201.06 Disposal.
Merchantable timber is Government property.
202 - Additional Clearing and Grubbing 202.04_Regional_8_2_2021
Delete the Subsection 202.01 and replace the following:
202.01 This work consists of clearing and grubbing within clearing limits as designated in the plans. This work also includes scalloping clearing lines, clearing vistas, thinning vegetation, special clearing and grubbing and the removal of individual trees and stumps designated in the plans that may be outside the clearing limits.
Add the following to Subsection 202.04:
202.04 Selective Clearing.
(a) Roadside Clearing. Cut all brush and small trees, four inches in diameter or less at the point of cut, inside the roadside clearing limits and outside the roadway no higher than four inches above ground level. If rocks or other obstructions are encountered, cut no higher than 6 inches above the obstruction. Limb live trees with a diameter larger than four inches to a height of 14 feet above the road surface.
Add the following to Subsection 202.06:
202.06 Special Clearing and Grubbing.
(a) Roadway and Roadside Clearing and Grubbing. Clear Within the roadside clearing limits. Grub the roadway and horizontally five feet beyond each shoulder. Dispose of merchantable timber according to Subsection 201.06
203 - Removal of Structures and Obstructions 203.04_National_11_2_2016
Make the following changes to Subsection 203.04(b):
203.04 (b) General.
Delete the fifth paragraph of Subsection 203.04(b) and replace with the following:
Remove structures and obstructions in the roadbed to 12 inches (300 millimeters) below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches (300 millimeters) below finished ground or to the natural stream bottom.
Delete the seventh paragraph of Subsection 203.04(b) and replace with the following:
When abandoning an existing culvert pipe, remove the upstream and downstream portion of the culvert to within 12 inches (300 millimeters) of the subgrade or embankment slope. Ensure the abandoned pipe is at least 48 inches (1200 millimeters) from a new culvert or structure. Seal the abandoned culvert ends with a tight-fitting plug of concrete at least 6 inches (150 millimeters) thick. Ensure the structure does not entrap water.
203.05_National_9_10_2018
Add the following to Subsection 203.05:
203.05 Disposing of Material.
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.
(f) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another.
Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.
(g) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking. Remove brush from designated log deck areas. Limb and top logs.
Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than ten feet and decked in designated log deck location.
Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).
Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.
| Preface |
| 101 - Terms¸ Format¸ and Definitions |
| 101.01 Meaning of Terms. |
| 101.03 Abbreviations. |
| 101.04 Definitions. |
| 102 - Bid¸ Award¸ and Execution of Contract |
| Delete Section 102. |
| 103 - Scope of Work |
| Delete Subsections 103.02, 103.03, 103.04, 103.05. |
| 104 - Control of Work |
| Delete Subsections 104.01, 104.02, 104.04. |
| 104.06 Use of Roads by Contractor. |
| 105 - Control of Material |
| 105.05 Use of Material Found in the Work. |
| 106 - Acceptance of Work |
| 106.01 Conformity with Contract Requirements. |
| 106.02 Visual Inspection. |
| 107 - Legal Relations and Responsibility to the Public |
| Delete Subsection 107.05. |
| 108 - Prosecution and Progress |
| Delete Section 108. |
| 109 - Measurement and Payment |
| Delete Subsections 109.06, 109.07, 109.08, 109.09. |
| 109.01 Measurement of Work. |
| 109.02 Measurement Terms and Definitions. |
| 155 - Schedules for Construction Contracts |
| Delete Section 155. |
| 201 - Clearing and Grubbing |
| 201.03 General. |
| 201.04 Clearing. |
| 201.06 Disposal. |
| 202 - Additional Clearing and Grubbing |
| 202.01 This work consists of clearing and grubbing within clearing limits as designated in the plans. This work also includes scalloping clearing lines, clearing vistas, thinning vegetation, special clearing and grubbing and the removal of individual... |
| 202.04 Selective Clearing. |
| 202.06 Special Clearing and Grubbing. |
| 203 - Removal of Structures and Obstructions |
| 203.04 (b) General. |
| 203.05 Disposing of Material. |
File details come from the government source that posted it. Updated .