Attachment 6 - FOPR for Seed Project.pdf

PDF 210 KB Posted

Attached to
IT/FIBER INFRASTRUCTURE MACC Indefinite Delivery-Indefinite Quantity (IDIQ) Federal contract opportunity
Solicitation number
FA452822R0006
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4528-22-R-0006

Attachment 6

5 May 2022

MEMORANDUM FOR: RESPONDENTS TO SOLICITATION FA4528-22-R-0006

FROM: 5 CONS/PKA

SUBJECT: Fair Opportunity Proposal Request (FOPR) for Fiber Optic Install B870 – B1034 Tower at Minot AFB, ND

1. This is a FOPR for subject project to be awarded on a fair opportunity basis pursuant to Federal Acquisition Regulation (FAR) 16.505 ordering procedures, the terms and conditions of the IT/Fiber Infrastructure MACC Indefinite Delivery-Indefinite Quantity (IDIQ), and the specific requirements outlined in this request with attachments. This project consists of the all work associated with SOO ITB 870 to B1034 Tower 12 SM 26 Jan 2022 (Attachment 2) at Minot AFB, ND.

2. The selection methodology for award of this Task Order will be made to the responsive Awardee proposal with the overall lowest price (competition consisting only of those offers awarded an initial contract). The Government may determine that an offer is unacceptable if the construction cost is unreasonable. The Government intends to award a single FFP Task Order for the subject project. The Government reserves the right to conduct interchanges (see Attachment 7 –IT Fiber Infrastructure MACC Provisions).

3. A site visit will be held 18 May 2022. We will initially meet in the 5 CONS lobby, Bldg 165, Minot AFB, ND, and then after sign in of all attendees and an overview of the project all attendees will depart for the project site. Please provide all requests for base access no later than 13 May 2022.

4. Wage Determination: Use contract Attachment 3 – DBA Wage Determination ND20220043 in performance of this Task Order.

5. The following clauses, in addition to the IDIQ clauses, will be included in this Task Order:

No additional clauses

6. Questions and Answers/Assumptions and Exceptions: Contractors are cautioned that all communications are to be channeled through the Contracting Officer. Any questions whether technical or contractual in nature shall be submitted in writing. Questions and Answers may be submitted in writing to the Contract Administrator, TSgt Jonathan Panganiban, jonathan.panganiban@us.af.mil by 26 May 2022, Questions will be consolidated and responses will be forwarded to all contractors through an amendment to solicitation FA4528-22-R-0006. No further questions will be addressed on this project after this date. Contractors shall address any assumptions and proposed exceptions to the Contracting Officer in their proposal.

7. This FOPR is not authorization to begin performance, and in no way obligates the Government for any costs incurred by the offeror associated with developing a proposal. The Government reserves the right not to award an order in response to this FOPR. Prior to commencement of any activities associated with performance of this requirement, the Government will issue a written directive or a contractual document signed by the Contracting Officer with appropriate consideration established.

DEPARTMENT OF THE AIR FORCE

5TH CONTRACTING SQUADRON (AFGSC)

MINOT AIR FORCE BASE NORTH DAKOTA

mailto:jonathan.panganiban@us.af.mil

FA4528-22-R-0006

Attachment 6

8. All proposals must be received by the 5th Contracting Squadron in response to solicitation FA4528- 22-R-0006.

9. Payment and Performance Bonds:

a. Payment and Performance Bonds are required for construction contracts greater than $150,000.

b. For construction contracts greater than $35,000 but not greater than $150,000, a payment bond or an irrevocable letter of credit (ILC) are required.

c. The FOPR awardee must submit the appropriate bonding within 10 days after TO Award.

10. Project Magnitude: Between $25,000 and $100,000.

11. Liquidated Damages for this project in accordance with contract clause 52.211-12 in the amount of $205.09 for the first day and $ 162.71 for each additional day _X_ are applicable ______ are not applicable.

12. Performance Period: The performance period for this Task Order will be 120 days after issuance of the Notice to Proceed.

13. For either the site visit or submission of proposals all personnel requesting access to Minot Air Force Base must possess a valid State or Government picture identification card. Furthermore, individuals presenting identification cards from a state that is non-compliant with the REAL ID Act will require additional documentation to gain unescorted base access. Additional documentation include a valid U.S.

or foreign government issued passport, an employment authorization document that contains a photograph, or identification cards issued by federal state or local government agencies that include a photo and biographic information. A full list of REAL ID Act compliant and non-complaint states can be found at the following site:

https://www.dhs.gov/current-status-states-territories

14. Offer Schedule: Provide the proposal for the seed project – Fiber Optic Install ITB 870 – B1034 Tower 12 SM in the table below.

Item Description Quantity Unit Price Total 0001 Fiber Optic Install ITB 870 –

B1034 Tower 12 SM

15. If you have any questions concerning this FOPR, contact TSgt Jonathan Panganiban, jonathan.panganiban@us.af.mil.

Lisa Peckham, GS-12, USAF Contracting Officer

Attachments:

1. Attachment 2 - SOO ITB 870 to B1034 Tower 12 SM 26 Jan 2022

2. Attachment 3 - Wage Determination ND20220043

3. Attachment 7 - IT Fiber Infrastructure MACC Provisions https://www.dhs.gov/current-status-states-territories mailto:jonathan.panganiban@us.af.mil

FROM: 5 CONS/PKA

20509 for the first day and 16271 for each additional day X are applicable:
0001:
Unit Price1:
Total1:
2022-05-05T15:16:09-0500
PECKHAM.LISA.L.1141302937