ATTACHMENT 6: ESTIMATED TIMELINES

ACTION
TIMELINE
DTRA response for receipt of Phase I Quad /Whitepaper Submissions
5 Working Days
DTRA RD OPI review of Phase I Quad /Whitepaper Submissions
30 Days
Responses to questions on DTRA RD BAA posted to SAM
14 Days after notification of questions
Phase 1 Quad/Whitepaper notification date (Selection/Non-Selection)
60 Days after date of Phase I Submission
Phase II Proposal invite
60 Days after date of Phase I Submission
Phase II Proposal notification date (Selection/Non-Selection)
60 Days after date of Phase II Submissions
Phase II Proposal non-selection notification de-brief request
Expires 5 working days after non-selection notification
Estimate Contract Award Date
TBD (1,2)
Reserve List of Proposals
12 months after date of selection 2

Notes:

1: Actual award dates will vary based on complexity, statutory requirements, quality of proposal, pricing considerations, DCAA audits of proposed rates, type of instrument, number of awards, and other considerations. All dates are subject to change.

2: Awards will be made subject to the availability of funds.

File details come from the government source that posted it. Updated .