This document is an informational attachment for a concrete repair project at the Brackish Groundwater National Desalination Research Facility (BGNDRF). The primary contract objectives include reducing water drainage from the roof and fire suppression system, creating a new concrete slab capable of supporting a forklift with a full load, and raising a manhole and utility box above grade.
The specific work involves three main tasks: (1) installing a new 4 ft by 16 ft concrete section between an existing slab and acid room wall, (2) creating new concrete sections in front of the workshop (an 8 ft x 16 ft rectangle plus a 4 ft x 4 ft square) and between the workshop and electrical room door, and (3) raising the manhole cover and utility box above ground level. The project requires removing existing rock, preparing the base, pouring concrete, and installing expansion joints according to the Statement of Work (SOW). The attached images provide visual documentation of the current site conditions and proposed work areas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_2_-_Revised_Price_Schedule_0002.docx | DOCX document | |
| Attachment_1_-_Revised_Statement_of_Work_0002.docx | DOCX document | |
| Sol_140R4025Q0031_Amd_0002.pdf | ||
| Sol_140R4025Q0031_Amd_0001.pdf | ||
| Attachment_1_-_Statement_of_Work_BGNDRF_Concrete.docx | DOCX document | |
| Sol_140R4025Q0031.pdf | ||
| Attachment_4_-_Drawings.pdf | ||
| Attachment_3_-_SAM_gov_Davis-Bacon_Act_WD_NM20250025_02-14-2025.pdf | ||
| Attachment_2_-_Price_Schedule.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overall Picture with BGNDRF Measurements – for informa onal purposes
Main goals of this contract:
1. Reduce amount water that drains off roof and fire suppression drain to soil area near exis ng slabs. The roof does not have any gu ers. The new slab in front of the rollup door needs to be able to support our forkli with a full load.
2. Raise manhole and u lity box above grade.
Individual work to be done:
1. New 4 by 16 sec on of concrete between exis ng slab and acid room wall
a. Remove exis ng rock
b. Dig deep enough for base plus concrete
c. Pour concrete & install expansion joints as per SOW
2. New sec on in front of workshop.
a. Area in front of workshop (8 x 16 rectangle plus addi onal 4 x 4 square):
i. Remove or level exis ng surface as needed. The area was le this way a er repairs were performed on a buried line and le as‐is to make the concrete work easier.
ii. Add base material as needed
iii. Pour concrete & install expansion joints as per SOW
b. Area between workshop and electrical room door (4 x 8 ):
i. Remove exis ng rock
ii. Dig deep enough for base plus concrete
iii. Pour concrete & install expansion joints as per SOW
3. Raise manhole cover and round u lity box above grade:
a. Manhole is circled in yellow and u lity box is in green in the photos below. A third manhole cover is shown for context – this one is above grade.