Appendix C: Other Documents
XLWU 22-8124
REPAIR BEACON BEACH ROAD
Department of the Air Force
325 Fighter Wing (ACC)
Tyndall Air Force Base, Florida
Repair Beacon Beach Road
AF IMT 332:
Base Civil Engineer Work Request
Department of the Air Force
325 Fighter Wing (ACC)
1. FROM (Organization) 3. DATE OF REQUEST 4. WORK REQUEST NO. (For BCE Use)
5. NAME AND PHONE NO. OF REQUESTER 6. REQUIRED COMPLETION DATE
8. DESCRIPTION OF WORK TO BE ACCOMPLISHED (Include Sketch or Plan, when appropriate)
9. BRIEF JUSTIFICATION FOR WORK TO BE ACCOMPLISHED (Not required for maintenance and repair)
10. DONATED RESOURCES: ASSETS YOUR UNIT WILL PROVIDE TO GET PROJECT COMPLETED. IF THERE ARE NO DONATED RESOURCES, MARK NONE.
11. NAME OF REQUESTER, UNIT CC (See Instructions) 12. GRADE
BASE CIVIL ENGINEER WORK REQUEST
SECTION I - TO BE COMPLETED BY REQUESTER
SYMBOL
2. OFFICE
7. BUILDING, FACILITY OR STREET ADDRESS
WHERE WORK IS TO BE ACCOMPLISHED
BASE CIVIL ENGINEER WORK REQUEST
FUNDS LABOR MATERIAL CONTRACT BY REQUESTER NONE
13. SIGNATURE OF REQUESTER
1. From (Organization): This is the requesting organization
2. Office Symbol: This is the requestor’s office symbol
3. Date of Request: This is the date the form is completed up to item 10.
4. Work Request No: For BCE use only
5. Name and Phone No. of Requester: Name and DSN telephone number of request (Note, requesters should be facility managers. Exceptions will be routed through CE Customer Service for approval)
6. Required Completion Date: List the desired completion date. Include any justifications on dates in item 9.
7. Building, Facility or Street Address where work is to be Accomplished: Self explanatory
8. Description of Work to be Accomplished: Please provide a detailed description of requested work. Include any sketches, plans, diagrams, specifications, photographs, and any other data or information that provides a complete description of the location and scope of work requested.
9. Brief Justification for Work to be Accomplished: Please provide justification or reason work needs to be done. The justification should be factual and indicate the urgency of the request. If any documents/directives are referenced (e.g., T.O., A.F.I, AF manual) please attached the referenced page stating the requirement to the this form.
10. Donated Resources: Check any resources the requesting unit will provide to CE in order to complete the work. If there are no donated resources, check none.
11. Name of requester, Unit CC: This should be signed by the requesting facility manager. If the requested work is new work, modification, or minor construction, the organization's commander should sign the request.
12. Grade: List the grade of the person listed in block 11.
13. Signature of requester’s leadership: Electronic or wet signature of the person listed in block 11.
INSTRUCTIONS
SECTION II - TO BE COMPLETED BY APPROVING AUTHORITY
ESTIMATED TOTAL COST
DATESIGNATURE NAME AND GRADE
REMARKS WORK CLASS
1157440345C Sticky Note Accepted set by 1157440345C
1157440345C Sticky Note Accepted set by 1157440345C
1157440345C Sticky Note Accepted set by 1157440345C
1157440345C Sticky Note Accepted set by 1157440345C
1157440345C Sticky Note Accepted set by 1157440345C
AF 813 Form:
Environmental Impact Analysis
Department of the Air Force
325 Fighter Wing (ACC)
AF Form 66:
Schedule of Material Submittals
Department of the Air Force
325 Fighter Wing (ACC)
PROJECT NUMBER SOLICITATION/CONTRACT NO.
FA4819-20-C-XXXX
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C
ER
TI
FI
C
AT
E O
F C
O M
PL
IA
N C
E
SH
O
P D
R
AW
IN
G
S
SA
M
PL
ES
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
C
TU
R
ER
'S R
EC
O
M M
EN
D
AT
IO
N S
M
AN
U
FA
C
TU
R
ER
'S W
AR
R
AN
TY
C
AT
AL
O
G D
AT
A
O
PE
R
AT
IN
G
IN
ST
R U
C
TI
O N
S
AS
-B U
IL
T
D R
AW
IN
G S
D
IS
K
D O
C U
M
EN
TA
TI
O N
A S
R
EQ
U
IR
ED
R
EQ
U
IR
ED
SU
BM
IS
SI
O N
D
AT
E
D
AT
E R
EC
EI
VE
D
IN
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
EN
G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
SE
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
DATE CONTRACTOR NOTIFIED
C O
N
TR
AC
TO
R
ES
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
APPROVED DISAPPROVED
1 Design Charrette NA
2 Meeting Minutes (All Meetings) Meeting + 2 Days
3 Contractor Badging Applications Award + 14 Days
4 Project Schedule - AF Form 3064 NTP + 14 Days
5 Work Clearance Request / Digging Permit - AF Form 103
10 Days Prior to Commencing
Work
6 HAZMAT Inventory Form 81 & 82 14 Days Prior to
Commencing Work
7 Progress Report - AF Form 3065 Weekly
8 Material Approval - AF Form 3000 1 1 1 1 5 Days Prior to Order
9 Regulatory Permit Application
Prior to submitting to
Permitting Agency
0 Construction Materials Testing Reports Upon Receipt
1 Welding/Burn Permit - As Required
Prior to Commencing
Work
Draft DD 1354 - Transfer & Acceptance of Military Real Property NTP + 160 Days
3 Pre-Final Inspection Report Pre-Final + 3
Days
Contractor Environmental Reporting Entry - TAFB Form 83
Prior to Final Inspection
5 Equipment Manuals and Parts Lists Prior to Final
Inspection
1 1
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT TITLE
XLWU 21-8111 Repair Roads to Support Rebuild
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
AF Form 66
PROJECT NUMBER SOLICITATION/CONTRACT NO.
FA4819-20-C-XXXX
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C
ER
TI
FI
C
AT
E O
F C
O M
PL
IA
N C
E
SH
O
P D
R
AW
IN
G
S
SA
M
PL
ES
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
C
TU
R
ER
'S R
EC
O
M M
EN
D
AT
IO
N S
M
AN
U
FA
C
TU
R
ER
'S W
AR
R
AN
TY
C
AT
AL
O
G D
AT
A
O
PE
R
AT
IN
G
IN
ST
R U
C
TI
O N
S
AS
-B U
IL
T
D R
AW
IN
G S
D
IS
K
D O
C U
M
EN
TA
TI
O N
A S
R
EQ
U
IR
ED
R
EQ
U
IR
ED
SU
BM
IS
SI
O N
D
AT
E
D
AT
E R
EC
EI
VE
IN
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
SE
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
DATE CONTRACTOR NOTIFIED
C O
N
TR
AC
TO
ES
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
REMARKS
APPROVED DISAPPROVED
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT TITLE
XLWU 21-8111 REPAIR ROADS TO SUPPORT REBUILD
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
Final DD 1354 - Transfer & Acceptance of Military Real Property
At Final Inspection
7 Final Inspection Report
Final Inspection + 5
Days
8 Project Close Out Documents 1
Final Inspection + 7
Days
1 1 1 1 1
AF Form 66
| Work Request - Repair Beacon Beach Road.pdf |
| Blank Page |
| 1 FROM Organization: 325 CES |
| SYMBOL 2 OFFICE: CENP |
| 3 DATE OF REQUEST: 20220407 |
| 4 WORK REQUEST NO For BCE Use: |
| 5 NAME AND PHONE NO OF REQUESTER: Quentin Morales, 523-2763 |
| 6 REQUIRED COMPLETION DATE: 20220516 |
| 7 BUILDING FACILITY OR STREET ADDRESS WHERE WORK IS TO BE ACCOMPLISHED: Beacon Beach Road |
| 8 DESCRIPTION OF WORK TO BE ACCOMPLISHED Include Sketch or Plan when appropriate: The intent of the project if it is a full replacement of the road using an alternate base due to the water table within the area. The affected portions of Prime Beef Road to Suwannee Road. Total area is approximately 325,000 SF. Ensure maintenance of traffic during working hours throughout performance period. |
A. Remove existing asphalt pavement, base materials, and excess soils B. Compact subgrade to 95% Modified Proctor value C. Install 8 inches of graded aggregate base (GAB) such as crushed concrete D. Layer SP9.5 or SP12.5 asphalt pavement with standard cross slopes (crown) to shed water E. Install barrier system between the road and walking path at the locations where it abuts the roadway F. Paint new reflective pavement markings G. Address any ancillary work required for a complete and usable roadway
| 9 BRIEF JUSTIFICATION FOR WORK TO BE ACCOMPLISHED Not required for maintenance and repair: Road is being repaired and maintained as part of Tyndall's Pavement Sustainment Plan. Work is being accomplished IAW the latest geo-technical and AFCEC PCI reports performed for Tyndall. |
| Check Box5: Off |
| Check Box3: Off |
| Check Box2: Off |
| Check Box1: Off |
| 11 Requestor, UNIT CC: Quentin Morales |
| 12 GRADE: GS-12 |
| Check Box4: Off |
| Date2_af_date: |
| Name And Grade: |
| Text4: |
| Remarks: |
| Total Cost: |
File details come from the government source that posted it. Updated .