ATTACHMENT 5 - Availability Schedule-Kidd 8-19-24.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
USS KIDD Hull Preservation Federal contract opportunity
Solicitation number
N4523A24R0567
Issued by
Department of the Navy Naval Supply Systems Command

About this file

This document is an Attachment 5 - Availability Schedule related to a Request for Quote (RFQ) for the USS KIDD (DDG-100) hull preservation project. The RFQ, solicitation number N4523A24R0567, is being issued by the Department of the Navy Naval Supply Systems Command as an unrestricted procurement under FAR Part 13 Simplified Acquisition Procedures.

The Availability Schedule outlines key milestones and dates for the project, including the availability start date, docking the ship, paint representative arrival, inspection milestones, undocking, crew move aboard, completion of availability work, start of trials, and the end of the contractor's period of performance. The applicable NAICS code is 325510 Paint and Coating Manufacturing, and the contractor will be responsible for delivering paint coatings and related products to the USS KIDD in Seattle and Everett, WA.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Attachment 5 Availability Schedule - Request for Quote N
ADVANCED PLANNING MILESTONES USS KIDD (DDG-100)
EXECUTION MILESTONES
EventMilestoneProjected Date
AVAIL STARTA+0Wednesday, January 6, 2025
Paint Arrival at shipyardA+0Wednesday, January 6, 2025
Dock ShipA+16Wednesday, January 22 2025
Paint Representative at ShipyardA+29Wednesday, February 04, 2025
Open/Inspect Complete (20%) HighPriA+60Friday, March 7, 2025
Open/Inspect Complete (20%) AllA+105Friday, April 21, 2025
25% ConferenceA+130Friday, May 16, 2025
Undock Ship (Key Event)A+235Friday, August 29, 2025
50% ConferenceA+270Tuesday, September 23, 2025
75% ConferenceA+390Wednesday, January 21, 2026
Hab CompleteA+409Monday, February 9, 2026
Crew Move AboardA+410Monday, February 10, 2026
C5ILO (Key Event)A+420Friday, February 20, 2026
PCD (Key Event)A+434Friday, March 6, 2026
Work Complete (Key Event)A+501Tuesday, May 12, 2026
LOAA+514Monday, May 25, 2026
Start Dock Trial (Key Event)A+529Tuesday, June 9, 2026
Start Fast Cruise (Key Event)A+530Wednesday, June 10, 2026
Start Sea Trials (Key Event)A+535Monday, June 15, 2026
End of KTR Period of PerformanceA+539Friday, June 19, 2026