Attachment 4 - MSS.xls

XLS spreadsheet 58 KB Posted

Attached to
Replace Carpet at Bay Breeze Event Center Federal contract opportunity
Solicitation number
FA301023R0018
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document is a Material Submittals Schedule for a federal contract with the Department of the Air Force Air Education and Training Command to replace carpet at the Bay Breeze Event Center. The schedule outlines 21 items or descriptions of work requiring submittals from the contractor, including product data, shop drawings, samples, and warranties. It specifies the number of copies required for submittals and establishes due dates for initial submissions as well as dates for responses and resubmittals. Key deadlines include submittals being due 10 days following notice to proceed for items like tile carpeting, resilient flooring, and paint work. The schedule provides a framework for the contractor to receive design approvals from the contracting agency for materials and finishes before proceeding with installation.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
231011Project Title:
MAHG231011 Replace Carpet BBECSolicitation / Contract Number:

FA301023R0018; Attachment #4

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1HazMat Questionnaire335 Days Prior to Start Date
2HazMat MSDS335 Days Prior to Start DateMust be filled out if Contractor answers YES to to the HazMat questinnaire
3HazMat Reporting Entry Form335 Days Prior to Start DateSubmot Final Quantities
4HazMat Reporting entry Form33End of Contract
5Recycling and Landfill Report33End of Contract
6Warranty (Manufacture's)33End of Contract
71-Year Warranty (Contractor's)33End of Contract
8Digital Lock Set3310 Days Following NTP
8Section 096813-Tile Carpeting11113310 Days Following NTP
8Section 096500-Resilient and Luxury Vinyl Tile11113310 Days Following Issuance of Award
9Section 096813-Tile Carpeting11113310 Days Following Issuance of Award
10Section 090170-Repair of Exterior Insulation Finish System113310 Days Following NTP
9Section 062000-Finish Carpentry General11111110 Days Following NTP
10Section 079200-Joint Sealants1111110 Days Following NTP
11Section 081113-Steel Frames1111110 Days Following NTP
12Section 082000-Wood Doors1111110 Days Following NTP
13Section 084010-Aluminum Doors and Frames1111110 Days Following NTP
14Section 092550-Gypsum Board Assemblies1111110 Days Following NTP
15Section 093013-Tile and Grout1111110 Days Following NTP
16Section 093050-Tile Setting Materials and Accessories1111110 Days Following NTP
17Section 095110-Acoustical Panel Ceilings1111110 Days Following NTP
18Section 096500-Resilient and LVT Flooring1111110 Days Following NTP
19Section 099100-Paint1111110 Days Following NTP
20Section 099323-Stains and Transparent Finishes1111110 Days Following NTP
21Section 123600-Countertops1111110 Days Following NTP
14
15
16
17
18
19
20
21
22
23
24
11Section 099000-Painting and Coating113310 Days Following NTP

&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).

&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

File details come from the government source that posted it. Updated .